Home / Browse projects / Latur, Maharashtra / SHRI GAJANAN RESIDENCY

Registered No litigation declared Residential / Group Housing project

SHRI GAJANAN RESIDENCY

By SIDDESHWAR INFRASTRUCTURE

RG-MH-43055 · RERA P52400027410 · Last updated on MahaRERA portal: 11 Aug 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 32 months
  • 1 extension taken
  • Rs 10.00 crore secured on the land, in favour of OSMANABAD JANATA SAHAKARI BANK

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Latur registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 32 months from the original
39 of 110Construction stages doneacross 10 buildings; furthest along: Sanitary Fittings within the flats /..., 95%
62 of 200Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 190 documents Report an error

SHRI GAJANAN RESIDENCY is a Residential / Group Housing project by SIDDESHWAR INFRASTRUCTURE in Latur, Maharashtra, registered with MahaRERA as P52400027410 on 8 Dec 2020. Possession is promised by 31 Dec 2028. The completion date has moved by 32 months from the original filing. 138 of the 200 units on this registration are recorded sold or booked, and 39 of 110 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSHRI GAJANAN RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • RING ROAD
    • OPP. DMART LATUR
    • Latur (M Cl)
    • Latur
    • 413512
  • Pincode413512
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52400027410
  • ReraGenie IDRG-MH-43055

Builder

  • NameSIDDESHWAR INFRASTRUCTURE
  • Entity typePartnership
  • PartnersDHARMVEER YOGIRAJ BHARATI, NAGNATH LAXMAN GITTE, NAGNATH LAXMAN GITTE, DHARMVEER YOGIRAJ BHARATI

Key dates

this monthRegisteredDec 2020First promiseApr 2026Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Dec 2020
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 20 Apr 2026)
  • Buildings10 building records
  • Documents filed190 files

Current status

69%138 of 200 units booked

Figures as on 11 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA6520020
BNA6520020
CNA6520020
DNA6520020
ENA6520020
FNA6520020
GNA6520020
HNA6520020
INA6520020
JNA6520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building10

As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

39 of 110 construction stages are filed complete across 10 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

A70%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)50%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
B70%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)50%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
C70%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)50%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
D74%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
E74%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
F74%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
G32%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
H32%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
I32%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
J32%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)50%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities31

As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
Visitor parking spaceYes0%
Solar water for master bed roomYes0%
Earthling for lightning provision.Yes0%
Provision of softener for entire residential schemeYes0%
Provision of Chimney (Exhaust) to every flat.Yes0%
Provision of garbage chute on every floorYes0%
Jogging trackYes0%
Designated car parking for every flatYes0%
Entrance gate with designer security cabinYes0%
Lift provision on back up energyYes0%
Servant toilet on ground floor for every two wingYes0%
Shree ganesh ji MandirYes0%
Children or toddler swimming poolYes0%
Children sand pitYes0%
Senior citizens sittingYes0%
Club House with well Equipped GymYes0%

Parking filed19

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots19
Closed/Covered19
BuildingClosed/CoveredTotal
A1010
B11
C11
D11
E11
F11
G11
H11
I11
J11

Land and ownership2

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area5,282 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared present
Charge in favour ofOSMANABAD JANATA SAHAKARI BANK
Secured amountRs 10.00 crore
CERSAI search filedYes
Declared on29 Jun 2026
LandownerVillageDistrict
DHARMVEER YOGIRAJ BHARATILatur (M Cl)Latur
NAGNATH LAXMAN GITTELatur (M Cl)Latur

Approvals and building plan

Sanctioning authorityLARTUR MUNCIPAL CORPORATION
Permissible FSI8985.9
Proposed, not sanctioned8,986 sq m
Buildings approved10
Buildings sanctioned10

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAMBAJOGAI ROAD , LATUR

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKISHOR BHANSALI
EngineerGANESH C PURI
EngineerKalyan Lature
Chartered AccountantMAROTI R GIRI
Chartered AccountantPatel and Sharma Chartered Accountants
Chartered AccountantABSB AND ASSOCIATES CHARTED ACCOUNTANT
Chartered AccountantDIPALI SHELAR
PartnerRole in project
SIDDESHWAR INFRASTRUCTURE-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA29062621595Apr 2026 → Dec 2028

Reason as filed by the promoter1. Impact of the COVID-19 Pandemic The project commenced post to the outbreak of the COVID-19 pandemic. However, from March 2020 to February 2022, construction activities were severely affected due to nationwide lockdowns, movement restrictions, and mandatory safety protocols. The pandemic caused widespread disruption in the availability of skilled and unskilled labour, as well as in the supply chain for construction materials and equipment. These constraints resulted in prolonged inactivity and slow progress on site. Despite these unprecedented conditions, continuous efforts were made to sust

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12400434Pawan Vinod MoteSIDDESHWAR INFRASTRUCTURE17/10/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Dec 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Dec 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Nov 2020Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed190

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 190 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2 A 25-2026.pdf11 Aug 2026
Form 1File: form 1 final.pdf25 Jun 2026
Form 2File: Form 2 April 26.pdf25 Jun 2026
Form 3File: Form 3 April 26.pdf25 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold.pdf25 Jun 2026
Form 5 (FY 2020-2021)File: Form 5 Shri Gajanan Residency FY 2020-21 Signed.pdf18 Jun 2026
Form 5 (FY 2021-2022)File: Form 5 Signed 21-22.pdf18 Jun 2026
Form 5 (FY 2022-2023)File: FY 2022-23.pdf18 Jun 2026
Form 5 (FY 2023-2024)File: Form 5-Final23-24.pdf18 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: engineer certificate .pdf17 Jun 2026
Form 3File: form 3 Sep 24.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: Dis of sold unsold.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 01 31-12-2020-ok.pdf17 Jun 2026
Form 3File: 01 -31 12 2020_0001-ok.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 01 31-12-2020-ok.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 02 31-03-2021-ok.pdf17 Jun 2026
Form 3File: 02 -31 03 2021_0001-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 02 31-3-2021-ok.pdf17 Jun 2026
Form 2File: 03 30-6-2021-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 3File: 03 -30 06 2021_0001-ok.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 03 30-06-2021-ok.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 04 30-09-2021-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 04 31-9-2021-ok.pdf17 Jun 2026
Form 3File: 04 -30 09 2021_0001-ok.pdf17 Jun 2026
Form 3File: 05 -31 12 2021_0001.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 05 31-12-2021-ok.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 05 31-12-2021-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 06 31-03-2022-ok.pdf17 Jun 2026
Form 2File: 06 31-3-2022-ok.pdf17 Jun 2026
Form 3File: 06 -31 03 2022_0001.pdf17 Jun 2026
Form 3File: 07 -30 06 2022_0001.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 07 31-6-2022-ok.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 07 30-06-2022-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 08 30-09-2022-ok.pdf17 Jun 2026
Form 2File: 08 30-9-2022-ok.pdf17 Jun 2026
Form 3File: 08 -30 09 2022_0001.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 3File: 09 -31 12 2022_0001.pdf17 Jun 2026
Form 2File: 09 31-12-2022-ok.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 09 31-12-2022-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 10 31-03-2023-ok.pdf17 Jun 2026
Form 2File: 10 31-3-2023-ok.pdf17 Jun 2026
Form 3File: 10 -31 03 2023_0001.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 11 31-6-2023-ok.pdf17 Jun 2026
Form 3File: 11 -30 06 2023_0001.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 11 30-06-2023-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 12 31-9-2023-ok.pdf17 Jun 2026
Form 3File: 12 -30 09 2023_0001.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 12 30-09-2023-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Form 2File: 13 31-12-2023-ok.pdf17 Jun 2026
Form 3File: 13 -31 12 2023_0001.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 13 31-12-2023-ok.pdf17 Jun 2026
Form 1File: Form 1.pdf17 Jun 2026
Disclosure of Sold and Booked InventoryFile: 14 31-03-2024-ok.pdf17 Jun 2026
Form 2File: 14 31-03-2024-ok.pdf17 Jun 2026
Form 3File: 14 -31 03 2024_0001.pdf17 Jun 2026
Form 2A (FY 2020-2021)File: 01 31-03-2021-ok.pdf17 Jun 2026
Form 2A (FY 2021-2022)File: 02 31-03-2022-ok.pdf17 Jun 2026
Form 2A (FY 2022-2023)File: 03 31-03-2023-ok.pdf17 Jun 2026
Form 2A (FY 2023-2024)File: 04 31-03-2024-ok.pdf17 Jun 2026
Form 3File: Form 3 Signed Upload.pdf10 Jun 2026
Form 2File: engineer certificate .pdf10 Jun 2026
Form 1File: Form 1.pdf10 Jun 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf10 Jun 2026
Form 1File: form 1.pdf9 Jun 2026
Form 2File: form 2.pdf9 Jun 2026
Form 3File: form 3.pdf9 Jun 2026

How this compares with Latur

69%of this project is bookeddistrict median 0%
10%of Latur projects moved their completion datethis one moved by 32 months
31%of Latur registrations have lapsed or been cancelledthis one is on the register

Computed across the 150+ Latur projects on ReraGenie, from their own filings.

Keep SHRI GAJANAN RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near OPP. DMART LATUR150+ in Latur

2 kmSHRI GAJANAN RESIDENCYCompleted 1Lapsed / revoked 1Other 9Dot size: filed unitsN

Filed coordinates, straight-line distance. 11 registered projects within 2 km.

Builder: SIDDESHWAR INFRASTRUCTURE

SIDDESHWAR INFRASTRUCTURE has 1 registration on MahaRERA, including SHRI GAJANAN RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Latur district page.

Frequently asked questions

What are my rights if SHRI GAJANAN RESIDENCY is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHRI GAJANAN RESIDENCY?

The registered promoter entity is SIDDESHWAR INFRASTRUCTURE, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHRI GAJANAN RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHRI GAJANAN RESIDENCY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHRI GAJANAN RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHRI GAJANAN RESIDENCY?

The professionals named in the filing: Architect: KISHOR BHANSALI; Engineer: GANESH C PURI; Engineer: Kalyan Lature; Chartered Accountant: MAROTI R GIRI; Chartered Accountant: Patel and Sharma Chartered Accountants; Chartered Accountant: ABSB AND ASSOCIATES CHARTED ACCOUNTANT. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHRI GAJANAN RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHRI GAJANAN RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHRI GAJANAN RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.