Red flags
- Allotment letter deviates from the model form
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- All 1 earlier projects delivered on promise
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 10 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KASLIWAL NIWARA is a Residential / Group Housing project by SANJAY SUGANCHAND KASLIWAL in Aurangabad, Maharashtra, registered with MahaRERA as PR1040002601653 on 25 Aug 2026. Possession is promised by 31 Dec 2032.
At a glance
Project
- NameKASLIWAL NIWARA
- TypeResidential / Group Housing
- Location
- Jalna Road
- Chikalthana
- Aurangabad
- 431003
- Pincode431003
- MapView location on Google Maps (as filed on RERA)
- RERA no.PR1040002601653
- ReraGenie IDRG-MH-64312
Builder
- NameSANJAY SUGANCHAND KASLIWAL
- Entity typeProprietor
- GSTIN27ACEPK1886A2ZS
- Track record1 past project →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Aug 2026
- Promised completion31 Dec 2032
- Revised completionNone
- Buildings6 building records
- Documents filed10 files
Current status
Figures as on 23 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Row Buglow 17-21 | NA | 4 | 3 | 5 | 0 | 5 |
| Row Bunglow 23-28 | NA | 4 | 3 | 6 | 0 | 6 |
| Row Bunglow 29-32 | NA | 4 | 3 | 4 | 0 | 4 |
| Row Bunglow 33-37 | NA | 4 | 3 | 5 | 0 | 5 |
| Row Bunglow 38-42 | NA | 4 | 3 | 5 | 0 | 5 |
| A Type Building | NA | 7 | 6 | 12 | 0 | 12 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building6
As on 23 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing.
Row Buglow 17-2117%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row Bunglow 23-2817%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row Bunglow 29-3217%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row Bunglow 33-3717%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Row Bunglow 38-4217%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 50% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A Type Building23%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 10% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 23 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | 40% |
| Water Supply | No | 50% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | 50% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | No | 0% |
| Street Lighting | No | 0% |
| Community Buildings | No | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | 0% |
| Aggregate area of recreational Open Space | No | 50% |
| Open Parking | No | Not applicable |
Parking filed112
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Stilt / Ground | Total |
|---|---|---|
| Row Buglow 17-21 | 20 | 20 |
| Row Bunglow 23-28 | 24 | 24 |
| Row Bunglow 29-32 | 16 | 16 |
| Row Bunglow 33-37 | 20 | 20 |
| Row Bunglow 38-42 | 20 | 20 |
| A Type Building | 12 | 12 |
Land and ownership
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA.
Certifying professionals and partners1
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Chartered Accountant | M A GANGWAL and ASSOCIATES |
| Partner | Role in project |
|---|---|
| KASLIWAL NIWARA | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
Documents filed10
As listed on the registration. The files themselves are on the MahaRERA portal.
| Document | Uploaded |
|---|---|
| Layout with Makred Area | 23 Jul 2026 |
| Annexure A | 23 Jul 2026 |
| DWG - Niwara 2-9 | 23 Jun 2026 |
| DWG - Niwara 3-9 | 23 Jun 2026 |
| DWG - Niwara 4-9 | 23 Jun 2026 |
| DWG - Niwara 5-9 | 23 Jun 2026 |
| DWG - Niwara 6-9 | 23 Jun 2026 |
| DWG - Niwara 7-9 | 23 Jun 2026 |
| DWG - Niwara 8-9 | 23 Jun 2026 |
| DWG - Niwara 9-9 | 23 Jun 2026 |
Promoter's earlier projects1
As disclosed by the promoter in this filing.
| Project | Status | Promised | Delivered | Litigation |
|---|---|---|---|---|
| KASLIWAL NIWARA PHASE I | Completed | Aug 2025 | Jun 2023 | No |
How this compares with Aurangabad
Computed across the 1,482 Aurangabad projects on ReraGenie, from their own filings.
Keep KASLIWAL NIWARA on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chikalthana1,482 in Aurangabad
VILLO 67
CHOUDHARY BHAISHREE LANDMARKS LLP
Nabhraj Gharkul
Nabhraj Construction
Gursahani Twin Tower
Shree Hinglajmata Constructions
MADHURA PARK
Madhura Land Developers
VYANKATESH PARADISE
TIRUPATI INFRA
DEEPNAND RESIDENCY
DEEPNAND DEVELOPERS
See every Aurangabad project, with the district possession charts
Builder: SANJAY SUGANCHAND KASLIWAL
Sanjay Suganchand Kasliwal has 2 registrations on MahaRERA, including KASLIWAL NIWARA PHASE I and KASLIWAL NIWARA. Its filings disclose 1 earlier MahaRERA project: 1 of 1 past projects completed on time. Read the full track record. See more projects on the Aurangabad district page.
Frequently asked questions
What are my rights if KASLIWAL NIWARA is delayed beyond 31 Dec 2032?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KASLIWAL NIWARA?
The registered promoter entity is SANJAY SUGANCHAND KASLIWAL, a proprietor as per the filing. Its GSTIN 27ACEPK1886A2ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KASLIWAL NIWARA?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KASLIWAL NIWARA?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KASLIWAL NIWARA?
The professionals named in the filing: Chartered Accountant: M A GANGWAL and ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KASLIWAL NIWARA?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback