Home / Browse projects / Mumbai City, Maharashtra / SHREEJI SERENITY
SHREEJI SERENITY
By SPACE INFRA
RG-MH-30925 · RERA P51900079259 · Last updated on MahaRERA portal: 29 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Rs 30.00 crore secured on the land, in favour of ICICI HOME FINANCE COMPANY LIMITED
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREEJI SERENITY is a Residential / Group Housing project by SPACE INFRA in Mumbai City, Maharashtra, registered with MahaRERA as P51900079259 on 24 Feb 2025. Possession is promised by 31 Mar 2028. 15 of the 67 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.
At a glance
Project
- NameSHREEJI SERENITY
- TypeResidential / Group Housing
- Location
- PLOT NO. 138 & 143 NAIGAON ESTATE BUILDING NO.85-A & 85-E PROPERTY KNOWN AS “MAKKA MANZIL”
- “ZAVER NIWAS” SITUATED AT GOVINDJI KENI ROAD & ST. PAUL STREET
- ...
- Pincode400014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900079259
- ReraGenie IDRG-MH-30925
Builder
- NameSPACE INFRA
- Entity typePartnership
- Other registrations1 more →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on24 Feb 2025
- Promised completion31 Mar 2028
- Revised completionNone
- Buildings2 building records
- Documents filed79 files
Current status
Figures as on 29 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREEJI SERENITY WING A | NA | 22 | 22 | 36 | 4 | 40 |
| SHREEJI SERENITY WING B | NA | 18 | 18 | 23 | 4 | 27 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building2
As on 29 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 90%.
SHREEJI SERENITY WING A52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 65% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
SHREEJI SERENITY WING B52%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 70% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 65% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | No | Not applicable |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed37
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| SHREEJI SERENITY WING A | 20 | 20 |
| SHREEJI SERENITY WING B | 17 | 17 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHREEJI SERENITY WING A | NA | Rs 27.44 cr | Rs 21.72 cr |
| SHREEJI SERENITY WING B | NA | Rs 27.44 cr | Rs 21.72 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | S G DALVI & ASSOCIATES |
| Engineer | STRUCT BOMBAY CONSULTANTA |
| Engineer | SUNNYRAJ SHINDE |
| Engineer | SACHIN SHASHIKANT SHIRKE |
| Chartered Accountant | VAYEDA AND ASSOCIATES |
| Chartered Accountant | KOTHHARI AND CO |
| Partner | Role in project |
|---|---|
| SPACE INFRA | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 3 Feb 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 23 Oct 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 23 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Mar 2028
Documents filed79
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: FORM 2A 2024-2025.pdf | 29 Aug 2026 |
| Form 2A (FY 2025-2026)File: FORM 2A 2025-2026.pdf | 29 Aug 2026 |
| Form 5 (FY 2024-2025)File: FORM 5 2024-2025.pdf | 29 Aug 2026 |
| Withdrawal Update Form 1File: FORM 1 - 21-07-2026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 - 21-07-2026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 - 20-07-2026.pdf | 23 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Architect Certificate 31-03-2026.pdf | 6 May 2026 |
| Withdrawal Update Form 2File: Form 2 Engineers Certificate 31-03-2026.pdf | 6 May 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate 31-03-2026.pdf | 6 May 2026 |
| Withdrawal Update Form 1File: Form 1 - 31-12-2025.pdf | 28 Apr 2026 |
| Withdrawal Update Form 2File: Form 2.pdf | 28 Apr 2026 |
| Withdrawal Update Form 3File: FORM 3.pdf | 28 Apr 2026 |
| Form 1File: Form 1.pdf | 16 Oct 2025 |
| Form 2File: Form 2.pdf | 16 Oct 2025 |
| Form 3File: Form 3.pdf | 16 Oct 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF REHAB SOLD UNSOLD INVENTORY.pdf | 16 Oct 2025 |
| Form 1File: Form 1 - Architect Certificate.pdf | 24 Jul 2025 |
| Form 2File: Form 2 - Engineer Certificate.pdf | 24 Jul 2025 |
| Form 3File: Form 3 - CA Certificate.pdf | 24 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF REHAB SOLD UNSOLD INVENTORY.pdf | 24 Jul 2025 |
| Copy of the legal title reportFile: output.pdf | 3 Feb 2025 |
| CERSAI detailsFile: output (9).pdf | 1 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE FINANCE.pdf | 24 Dec 2024 |
| Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE FINANCE.pdf | 24 Dec 2024 |
| Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCE FINANCE.PDF | 19 Nov 2024 |
| Other - LegalFile: 8.pdf | 19 Nov 2024 |
| Other - LegalFile: 10.pdf | 19 Nov 2024 |
| Other - LegalFile: 9.pdf | 19 Nov 2024 |
| Other - LegalFile: 8.pdf | 19 Nov 2024 |
| Other - LegalFile: 7.pdf | 19 Nov 2024 |
| Other - LegalFile: 6.pdf | 19 Nov 2024 |
| Other - LegalFile: 5.pdf | 19 Nov 2024 |
| Other - LegalFile: 4.pdf | 19 Nov 2024 |
| Other - LegalFile: 3.pdf | 19 Nov 2024 |
| Other - LegalFile: 2.pdf | 19 Nov 2024 |
| Other - LegalFile: 10.pdf | 19 Nov 2024 |
| Other - LegalFile: 9.pdf | 19 Nov 2024 |
| Other - LegalFile: 7.pdf | 19 Nov 2024 |
| Other - LegalFile: 6.pdf | 19 Nov 2024 |
| Other - LegalFile: 5.pdf | 19 Nov 2024 |
| Other - LegalFile: 4.pdf | 19 Nov 2024 |
| Other - LegalFile: 3.pdf | 19 Nov 2024 |
| Other - LegalFile: 2.pdf | 19 Nov 2024 |
| Other - LegalFile: 1.pdf | 19 Nov 2024 |
| Other - LegalFile: 1_11zon.pdf | 19 Nov 2024 |
| Details of encumbrances concerned to LegalFile: NO ENCUMBRANCE FINANCE.PDF | 19 Nov 2024 |
| Other - TechnicalFile: declaration ORDER NO 50.pdf | 7 Nov 2024 |
| Proforma of Allotment letterFile: MODEL DRAFT RERA ALLOTMENT LETTER_compressed.pdf | 24 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: spaxe ca.pdf | 24 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A- NEW BANK LETTERHEAD OF PROMOTER.PDF | 24 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: FORMAT B.pdf | 24 Oct 2024 |
| Layout approvalFile: 1.pdf | 23 Oct 2024 |
| Building plan approvalFile: IOD.pdf | 23 Oct 2024 |
| Building plan approvalFile: 2.pdf | 23 Oct 2024 |
| Building plan approvalFile: 3.pdf | 23 Oct 2024 |
| Building plan approvalFile: 4.pdf | 23 Oct 2024 |
| Building plan approvalFile: 5.pdf | 23 Oct 2024 |
| Building plan approvalFile: 6.pdf | 23 Oct 2024 |
| PAN CardFile: Space Infra Pan card.pdf | 23 Oct 2024 |
| Copy of the legal title reportFile: Legal Title Report (1).pdf | 23 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: 1.pdf | 23 Oct 2024 |
| Declaration in FORM BFile: SPACE FORM B (1).pdf | 23 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: shreeji serenity form 1.pdf | 23 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: shreeji serenity form 2.pdf | 23 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Space CC.pdf | 23 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 2.pdf | 23 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 6.pdf | 23 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 5.pdf | 23 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 4.pdf | 23 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 3.pdf | 23 Oct 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf | 23 Oct 2024 |
| Proforma of Agreement for saleFile: space rera afs.pdf | 23 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: no enc merged.pdf | 22 Oct 2024 |
| Declaration about Commencement CertificateFile: CC declaration.pdf | 22 Oct 2024 |
| Deviation Report with respect to Allotment letterFile: NO DEV ALOTMENT.pdf | 22 Oct 2024 |
| Details of encumbrances concerned to LegalFile: no enc merged.pdf | 22 Oct 2024 |
| Deviation Report with respect to model copy of AgreementFile: deviation[1].pdf | 22 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: annexure a final.pdf | 22 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: output (8).pdf | 22 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 79 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHREEJI SERENITY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NAIGAON, DADAR WEST780+ in Mumbai City
Filed coordinates, straight-line distance. 191 registered projects within 2 km.
Monopoli
Mathuresh Infrapro Private Ltd
The Baya Sunrise
RENAISSANCE SPACES
RA RESIDENCES
R A ASSOCIATES
PANCHRATNA-NX
SUDHIR KISHOR DESAI
Ratan Infinia
Shree Shankheshwar Enterprises
EL MEJOR
ARTH REALTECH SPACES PVT LTD
See every Mumbai City project, with the district possession charts
Builder: SPACE INFRA
SPACE INFRA has 2 registrations on MahaRERA, including SPACE CITY-1 and SHREEJI SERENITY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if SHREEJI SERENITY is delayed beyond 31 Mar 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREEJI SERENITY?
The registered promoter entity is SPACE INFRA, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREEJI SERENITY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SHREEJI SERENITY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREEJI SERENITY?
The professionals named in the filing: Architect: S G DALVI & ASSOCIATES; Engineer: STRUCT BOMBAY CONSULTANTA; Engineer: SUNNYRAJ SHINDE; Engineer: SACHIN SHASHIKANT SHIRKE; Chartered Accountant: VAYEDA AND ASSOCIATES; Chartered Accountant: KOTHHARI AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREEJI SERENITY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback