Registered No litigation declared Others project

RA RESIDENCES

By R A ASSOCIATES

RG-MH-20886 · RERA P51900001634 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 102 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2027Possession promisedmoved 102 months from the original
19 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 95%
20 of 194Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 61 documents Report an error

RA RESIDENCES is a Others project by R A ASSOCIATES in 400014, registered with MahaRERA as P51900001634 on 29 Jul 2017. Possession is promised by 31 Dec 2027. The completion date has moved by 102 months from the original filing. 174 of the 194 units on this registration are recorded sold or booked, and 19 of 33 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameRA RESIDENCES
  • TypeOthers
  • Location
    • Dr Babasaheb Ambedkar Rd
    • 400014
  • Pincode400014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900001634
  • ReraGenie IDRG-MH-20886

Builder

  • NameR A ASSOCIATES
  • Entity typePartnership
  • PartnersRAJENDRA KHEMCHAND KOTHARI, ASHOK KHEMCHAND KOTHARI, VINAY KHEMCHAND KOTHARI, VIVEK KAMALCHAND KOTHARI, VARUN ASHOK KOTHARI, SUSHIL RAJENDRA KOTHARI, CHANDRAPRAKASH SIROYA

Key dates

this monthRegisteredJul 2017First promiseJun 2019Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on29 Jul 2017
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Jun 2019)
  • Buildings3 building records
  • Documents filed61 files

Current status

90%174 of 194 units booked
96.6%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RA RESIDENCES WING ANA554674074
RA BUSINESS PARKNA5504646
RA RESIDENCES WING BNA554674074

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

19 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 95%.

RA RESIDENCES WING A90%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
RA BUSINESS PARK45%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth90%
Stilt Floor80%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.10%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
RA RESIDENCES WING B90%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes80%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed492

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots492
Closed/Covered492
BuildingClosed/CoveredTotal
RA RESIDENCES WING A209209
RA BUSINESS PARK7474
RA RESIDENCES WING B209209

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area12,751 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 Sep 2025

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI33772.4
Proposed, not sanctioned33,772 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTULSIANI CHAMBERS, NARIMAN POINT, MUMBAI - 400021
Estimated costRs 307.35 cr
Cost incurredRs 296.85 cr
Work done96.59%
BuildingWingEstimatedIncurred
RA RESIDENCES WING ANARs 112.41 crRs 108.57 cr
RA RESIDENCES WING BNARs 112.41 crRs 108.57 cr
RA BUSINESS PARKNARs 67.16 crRs 64.86 cr
-NARs 15.37 crRs 14.84 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSKYLINE ARCHITECTS
ArchitectSPACE AGE CONSULTANTS
EngineerSTERLING ENGINEERING CONSULTANCY SERVICES PVT LTD
EngineerSK Consultants & Engineers
EngineerPankaj Shah
Chartered AccountantBiren Lukka
Chartered AccountantCA Rutuja Narsingh and Associates
Chartered AccountantNusrat Banu Sayed
PartnerRole in project
R A ASSOCIATES-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900001858Jun 2019 → Jun 2020

Reason as filed by the promoterDue to certain technicalities regarding the installation of the lift in the building there was a delay in completion of the project. However, the technicalities have been resolved and we shall be able to complete the entire project swiftly.

EXT51900008771Jun 2019 → May 2021

Reason as filed by the promoter(b) We say that due to situation created by COVID-19 pandemic (Force Majeure) and nationwide lockdown, the construction work of on-going project was halted leading to reverse migration of labourers to their native place. Further, there was large scale disruption in the supply chain of construction materials which also adversely impacted the construction activity of the Project. It took so much time and hardships for labourers to return to work from their native place resulting into further delay in construction activities to restart.

EXT51900015182Jun 2019 → Mar 2025

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project under Section 7(3). We seek for the extension till 31st March 2025.

EA22092502660Jun 2019 → Dec 2027

Reason as filed by the promoterWe sincerely apologize for the delay in completion of the project and in submission of this request. The delay has occurred due to unforeseen and uncontrollable circumstances, including procurement issues and site challenges. Despite these setbacks, we are making all efforts to resolve the issues and complete the balance work. Additionally, a major reason for the delay has been the series of judicial and regulatory developments regarding provision of RG. The timeline is as under: • 13.09.2022 - NGT passed an order stating RG has to be provided on ground (mother earth) to enable plantation. • 2

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000197392Laxmi JainRA Associates24/06/2021
CC006000000303514SUVIRA PROPERTIES PVT LTDR A ASSOCIATES01/12/2022
CC006000000303513GU MERCHANDISE PVT LTDR A ASSOCIATES01/12/2022
CC006000000395936RA RESIDENCIES CHS LTDRA ASSOCIATES LLP30/05/2023
CC006000000396253Ashok Suresh DeshmukhAshok Kothari20/06/2023
CC006000000397857Gaurav Satyapal JainRA Associates14/10/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 11 Apr 2023

Documents filed61

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2017-2018)File: Form 2A FY 2019-20.pdf24 Apr 2026
Form 2A (FY 2018-2019)File: Form 2A FY 2020-21.pdf24 Apr 2026
Form 2A (FY 2019-2020)File: Form 2A FY 2019-20.pdf24 Apr 2026
Form 2A (FY 2020-2021)File: Form 2A FY 2019-20.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1- Jun 2025.pdf16 Oct 2025
Withdrawal Update Form 2File: Form 2 -Jun 2025.pdf16 Oct 2025
Withdrawal Update Form 3File: Form 3 -Jun 2025.pdf16 Oct 2025
Certificates of CA (Form 3)File: FORM 3 - CA Certificate.pdf11 Apr 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society registration certificate.pdf11 Apr 2024
Certificates of CA (Form 3)File: Form 3Chartered Account_compressed.pdf1 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate.pdf29 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 for 2022-23.pdf20 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Annexure B form 2.pdf14 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Annexure C form 2A.pdf14 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate FY 2019-20.pdf12 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance Certificate FY 2020-21.pdf12 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate FY 2021-22.pdf12 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC till 32 floors-Part 1.pdf11 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC for 33 to 42 flrs- Part 2.pdf11 Apr 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC for 43 to 46th floor - Part 3.pdf11 Apr 2023
Declaration about Commencement CertificateFile: FORMAT D.pdf28 Mar 2023
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 Wing C Inventory.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5_201819.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5_201920.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5_202021.pdf28 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5_202122.pdf28 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Mar 2019.pdf11 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Mar 2019.pdf11 May 2019
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Dec18.PDF20 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 Dec18.pdf29 Jan 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2 Dec18.pdf29 Jan 2019
Certificates of CA (Form 3)File: Form - 3 (CA Certificate).PDF5 Jan 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Sept 2018.pdf11 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Sept 2018.pdf11 Dec 2018
Certificates of CA (Form 5)File: Form 5 - Annual Report on Statement of Accounts.PDF12 Oct 2018
Certificates of CA (Form 3)File: CA Certificate Form 3 - Jun'18.PDF9 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1 - Jun'18.pdf20 Sep 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 - Jun'18.pdf20 Sep 2018
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf26 Jul 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 - Mar'18 - Signed.pdf13 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1- Mar'18.pdf15 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Form 2 - Mar'18.pdf15 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects Certificate - Compressed.pdf13 Feb 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer's certificate .pdf12 Feb 2018
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Compressed.PDF12 Feb 2018
Certificates of CA (Form 3)File: Form 3 - CA Certificate - Compressed.pdf12 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate Form 1.pdf30 Oct 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.pdf30 Oct 2017
Layout approvalFile: LAYOUT_993 KB.pdf25 Jul 2017
Building plan approvalFile: IOD_DATE-23_11_2009 (1)_981 KB.pdf25 Jul 2017
PAN CardFile: PAN Card.pdf25 Jul 2017
Copy of the legal title reportFile: Title Report.pdf25 Jul 2017
Details of encumbrancesFile: Details of encumbrances.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT_993 KB.pdf25 Jul 2017
Building Plan Approval (IOD)File: IOD_DATE-23_11_2009 (1)_981 KB.pdf25 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf25 Jul 2017
Declaration in FORM BFile: Promoter Declaration.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Form 1.pdf25 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineers Certificate Form 2.pdf25 Jul 2017
Certificates of CA (Form 3)File: Certificate of CA.pdf25 Jul 2017
Proforma of Allotment letterFile: Agreement for sale and allotment letter.pdf25 Jul 2017

Keep RA RESIDENCES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

2 kmRA RESIDENCESCompleted 17Lapsed / revoked 6Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 48 registered projects within 2 km.

Builder: R A ASSOCIATES

R A ASSOCIATES has 1 registration on MahaRERA, including RA RESIDENCES. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if RA RESIDENCES is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RA RESIDENCES?

The registered promoter entity is R A ASSOCIATES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RA RESIDENCES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RA RESIDENCES?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RA RESIDENCES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RA RESIDENCES?

The professionals named in the filing: Architect: SKYLINE ARCHITECTS; Architect: SPACE AGE CONSULTANTS; Engineer: STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD; Engineer: SK Consultants & Engineers; Engineer: Pankaj Shah; Chartered Accountant: Biren Lukka. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RA RESIDENCES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RA RESIDENCES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RA RESIDENCES to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.