Home / Browse projects / Monopoli
Monopoli
By Mathuresh Infrapro Private Ltd
RG-MH-35208 · RERA P51900049902 · Last updated on MahaRERA portal: 16 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 4 cases
- Completion date moved by 27 months
- 1 extension taken
- Rs 100.00 crore secured on the land, in favour of State Bank of India
Clear
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: .Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Monopoli is a Residential / Group Housing project by Mathuresh Infrapro Private Ltd in Naigaon, Dadar East, 400014, registered with MahaRERA as P51900049902 on 6 Mar 2023. Possession is promised by 31 Dec 2029. The completion date has moved by 27 months from the original filing. 86 of the 256 units on this registration are recorded sold or booked, and 39 of 55 construction stages are filed complete.
At a glance
Project
- NameMonopoli
- TypeResidential / Group Housing
- Location
- Dr. Babasaheb Ambedkar Road
- Naigaon
- Dadar East
- 400014
- Pincode400014
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900049902
- ReraGenie IDRG-MH-35208
Builder
- NameMathuresh Infrapro Private Ltd
- Entity typeCompany
- DirectorsYASH MUTHA, ANIL MUTHA, Nagraj Mutha
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Mar 2023
- Promised completion31 Dec 2029
- Revised completionRevised to 31 Dec 2029 (originally 27 Sep 2027)
- Buildings5 building records
- Documents filed137 files
Current status
Figures as on 16 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Wing- A | NA | 46 | 36 | 128 | 0 | 128 |
| Wing- B | NA | 46 | 36 | 128 | 0 | 128 |
| Wing- D | NA | 20 | 18 | 0 | 0 | 0 |
| Wing- E | NA | 20 | 18 | 0 | 0 | 0 |
| Wing- C | NA | 24 | 20 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 16 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
39 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Podiums (if any), at 50%.
Wing- A34%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing- B34%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 50% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 20% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Wing- D100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing- E100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Wing- C100%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 16 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 40% |
| Water Supply | Yes | 10% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 75% |
| Solid Waste Management And Disposal | Yes | 50% |
| Water conservation /Rain water harvesting | Yes | 70% |
| Energy managemcnt | Yes | 50% |
| Fire protection and fire safety requirements | Yes | 60% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | Yes | 30% |
| Open Parking | No | Not applicable |
Parking filed392
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Wing- A | 148 | 148 |
| Wing- B | 148 | 148 |
| Wing- D | 12 | 12 |
| Wing- E | 12 | 12 |
| Wing- C | 72 | 72 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Wing- A | NA | Rs 79.70 cr | Rs 20.00 cr |
| Wing- B | NA | Rs 79.70 cr | Rs 20.00 cr |
| Wing- C | NA | Rs 45.38 cr | Rs 35.92 cr |
| - | NA | Rs 40.81 cr | Rs 24.96 cr |
| Wing- D | NA | Rs 20.93 cr | Rs 18.28 cr |
| Wing- E | NA | Rs 20.93 cr | Rs 18.28 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | B.N.Shah & Associates |
| Architect | Skyline Architects |
| Architect | Sharaddha Salvi |
| Engineer | Chandrashekhar Gadgil |
| Engineer | Chandrapratap Singh |
| Engineer | Ratan Kharatmol |
| Chartered Accountant | KALPESH AGARWAL AND CO |
| Chartered Accountant | kalpesh |
| Chartered Accountant | Raj jain & Associates |
| Partner | Role in project |
|---|---|
| Mathuresh Infrapro Private Ltd | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Promoter has earlier received approval for development of project from MCGM under regulation 33(7) of DCPR 2034 Thereafter, Promoter has revised the proposal in June 2024 from earlier regulation 33(7) to regulation 33(9) and got revised approved plans from MCGM. This has resulted delay in proposed completion date.
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 316/2017/2017 | Small Causes Court | Closed |
| 60/2022/2022 | Small Causes Court | Closed |
| 1446/2018/2018 | Bombay High Court | Ongoing |
| 1721/2024 | Bombay High Court | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 13 Feb 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 11 Jul 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 18 Jul 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Jul 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed137
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 137 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Commencement certificateFile: CC 38 floors dated 291025.pdf | 16 Jul 2026 |
| Commencement certificateFile: CC revalidation letter till 061126.pdf | 16 Jul 2026 |
| Withdrawal Update Form 1File: Monopoli - Architect Certificate.pdf | 16 Jul 2026 |
| Withdrawal Update Form 2File: Monopoli - Engineer Certificate.pdf | 16 Jul 2026 |
| Withdrawal Update Form 3File: Monopoli Form - 3.pdf | 16 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A Monopoli 25-26.pdf | 27 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate-Monopoli Mar 26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 2File: Form -2 March 26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Monopoli-Mar 26.pdf | 18 Apr 2026 |
| Form 5 (FY 2025-2026)File: Form 5 FY 25-26.pdf | 18 Apr 2026 |
| Withdrawal Update Form 1File: Architect Certificate-Monopoli Dec 25.pdf | 19 Jan 2026 |
| Withdrawal Update Form 2File: Form -2 Dec 25.pdf | 19 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 Monopoli-Dec 25.pdf | 19 Jan 2026 |
| Withdrawal Update Form 1File: Architect Certificate-Monopoli Sep 25.pdf | 25 Oct 2025 |
| Withdrawal Update Form 2File: Engineers Certficate mathuresh Sep 2025.pdf | 25 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Monopoli-Sep25_signed.pdf | 25 Oct 2025 |
| Withdrawal Update Form 1File: Architect Certificate-Monopoli Sep 25.pdf | 24 Oct 2025 |
| Withdrawal Update Form 2File: Engineers Certficate mathuresh Sep 2025.pdf | 24 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Monopoli-Sep25_signed.pdf | 24 Oct 2025 |
| Withdrawal Update Form 1File: Architect Certificate-Monopoli June 25.pdf | 2 Aug 2025 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate June 25.pdf | 2 Aug 2025 |
| Withdrawal Update Form 3File: Withdrawal Application Form3 June 25.pdf | 2 Aug 2025 |
| Withdrawal Update Form 1File: Architect Certificate-Monopoli Mar25.pdf | 30 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 June 2024.pdf | 30 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Monopoli-March 2025.pdf | 30 Jul 2025 |
| Withdrawal Update Form 1File: Architect Certificate-Monopoli Mar25.pdf | 29 Jul 2025 |
| Withdrawal Update Form 2File: Form 2 June 2024.pdf | 29 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Monopoli-March 2025.pdf | 29 Jul 2025 |
| Form 5 (FY 2024-2025)File: Form 5 FY 24-25.pdf | 23 Jul 2025 |
| Building plan approvalFile: Drawing 44 floors- Uploaded.pdf | 18 Jul 2025 |
| Building plan approvalFile: Amended Plan Approval Letter.pdf | 14 Jul 2025 |
| Building plan approvalFile: Amended Plan Approval Letter.pdf | 14 Jul 2025 |
| Building plan approvalFile: Drawing 44 floors.pdf | 14 Jul 2025 |
| Form 1File: Architect Certificate-Monopoli Mar25.pdf | 5 Jul 2025 |
| Form 2File: Engineer Certificate March 2025.pdf | 5 Jul 2025 |
| Form 3File: Form 3 Monopoli-March 2025.pdf | 5 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold details March 25.pdf | 5 Jul 2025 |
| Form 2A (FY 2024-2025)File: MIPL- Site Supervisors Certificate Mar 25.pdf | 5 Jul 2025 |
| Form 2A (FY 2022-2023)File: Site Supervisor Certificate 2A FY 22-23- Fortuna Blue.pdf | 5 Jul 2025 |
| Form 2A (FY 2023-2024)File: MIPL- Site Supervisors Certificate Mar 24.pdf | 5 Jul 2025 |
| Form 5 (FY 2022-2023)File: Mathuresh Form-5.pdf | 5 Jul 2025 |
| Form 5 (FY 2023-2024)File: Form 5 FY 23-24.pdf | 5 Jul 2025 |
| Proforma of Allotment letterFile: Allotment letter.pdf | 13 May 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report.pdf | 13 May 2025 |
| Proforma of Agreement for saleFile: Agreement for Sale_RERA_Monopoli.pdf | 13 May 2025 |
| Disclosure of sold/ booked inventoryFile: Sold details March 25.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Monopoli Mar25.pdf | 21 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Monopoli-March 2025.pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate March 2025.pdf | 21 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Monopoli-Dec 2024.pdf | 15 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Dec 24.pdf | 15 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Sold details Dec 24.pdf | 15 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Monopoli Dec 24.pdf | 13 Jan 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank letter - RERA Bank accounts.pdf | 13 Jan 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC revalidation dated 221224.pdf | 20 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 2437649_FurtherCC_signed.pdf | 28 Nov 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: 2437649_FurtherCC_signed upto 4th Floor Sale.pdf | 28 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sep 24.pdf | 19 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Monopoli Sep 24.pdf | 17 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Monopoli-Sep2024.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Sold details Sep 24.pdf | 11 Oct 2024 |
| Declaration in FORM BFile: Form B Declaration Revised.pdf | 12 Aug 2024 |
| Declaration about Commencement CertificateFile: Form D - Mathuresh Infrapro.pdf | 19 Jul 2024 |
| Layout approvalFile: IOD Drawing revised.pdf | 11 Jul 2024 |
| Building plan approvalFile: IOD Drawing revised.pdf | 11 Jul 2024 |
| Copy of Layout Approval (in case of layout)File: IOD Drawing revised.pdf | 11 Jul 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: IOD Drawing revised.pdf | 11 Jul 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC dated 14 june 2024.pdf | 11 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 24.pdf | 11 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2024.pdf | 11 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Sold and unsold Inventory as on 30 june 2024.pdf | 11 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2024.pdf | 11 Jul 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 FY 23-24.pdf | 14 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: MIPL- Site Supervisors Certificate Mar 24.pdf | 3 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Monopoli- Form 3 Mar 24.pdf | 3 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Monopoli Mar24.pdf | 22 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Mar 24.pdf | 22 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate-Monopoli Dec 23.pdf | 19 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: MIPL Engi certificate.pdf | 12 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: MIPL- Form 3.pdf | 12 Jan 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against every project registered within 2 km, which the RERA portal never shows together
- All 137 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Monopoli on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Naigaon, Dadar East
Filed coordinates, straight-line distance. 55 registered projects within 2 km.
The Baya Sunrise
RENAISSANCE SPACES
RA RESIDENCES
R A ASSOCIATES
PANCHRATNA-NX
SUDHIR KISHOR DESAI
Ratan Infinia
Shree Shankheshwar Enterprises
EL MEJOR
ARTH REALTECH SPACES PVT LTD
THREE ICC-A WING
The Bombay Dyeing and Manufacturing Compan
Builder: Mathuresh Infrapro Private Ltd
Mathuresh Infrapro Private Ltd has 1 registration on MahaRERA, including Monopoli. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.
Frequently asked questions
What are my rights if Monopoli is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Monopoli?
The registered promoter entity is Mathuresh Infrapro Private Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Monopoli?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Monopoli?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Monopoli?
The professionals named in the filing: Architect: B.N.Shah & Associates; Architect: Skyline Architects; Architect: Sharaddha Salvi; Engineer: Chandrashekhar Gadgil; Engineer: Chandrapratap Singh; Engineer: Ratan Kharatmol. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Monopoli?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback