ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SHREEJA SERENE

Registered No litigation declared Residential / Group Housing project

SHREEJA SERENE

By Yogiraj Krishna Lohokare

RG-MH-30835 · RERA P52100079173 · Last updated on MahaRERA portal: 13 Jun 2026

Source: official MahaRERA filing

Red flags

  • Rs 4.90 crore secured on the land, in favour of INDIAN OVERSEAS BANK

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2028Possession promisedno revision filed
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 50%
68 of 70Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 55 documents Report an error

SHREEJA SERENE is a Residential / Group Housing project by Yogiraj Krishna Lohokare in Pune, Maharashtra, registered with MahaRERA as P52100079173 on 12 Feb 2025. Possession is promised by 30 Jun 2028. 2 of the 70 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHREEJA SERENE
  • TypeResidential / Group Housing
  • Location
    • Pune
    • Undri
    • Haveli
    • 411060
  • Pincode411060
  • RERA no.P52100079173
  • ReraGenie IDRG-MH-30835

Builder

  • NameYogiraj Krishna Lohokare
  • Entity typeIndividual
  • Declared earlier projects1 →

Key dates

this monthRegisteredFeb 2025PromisedJun 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on12 Feb 2025
  • Promised completion30 Jun 2028
  • Revised completionNone
  • Buildings2 building records
  • Documents filed55 files

Current status

3%2 of 70 units booked
20.1%Work done, per cost certificate

Figures as on 13 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLDG ANA9728028
BLDG BNA9742042

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 13 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 50%.

BLDG A31%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure40%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BLDG B32%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure50%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 13 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed110

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots110
Closed/Covered110
BuildingClosed/CoveredTotal
BLDG A4444
BLDG B6666

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area3,100 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofINDIAN OVERSEAS BANK
Secured amountRs 4.90 crore
CERSAI search filedYes
Declared on14 Nov 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI5434.1
Proposed, not sanctioned5,434 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 7, WONDER LAND, MAHATMA GANDHI ROAD, CANTONMENT, PUNE - 411001
Estimated costRs 18.00 cr
Cost incurredRs 3.61 cr
Work done20.07%
BuildingWingEstimatedIncurred
BLDG BNARs 10.80 crRs 2.17 cr
BLDG ANARs 7.20 crRs 1.45 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAkansh Aeram Architects
EngineerMr. Yogiraj Krishna Lohokare
Chartered AccountantPhule Wagh & Associates LLP
Chartered AccountantK L Rajput
PartnerRole in project
Yogiraj Krishna Lohokare-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jan 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Dec 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2028

Documents filed55

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Architect Cartificate Q4 FY 2025-26.pdf13 Jun 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Q4 FY 2025-26.pdf13 Jun 2026
Withdrawal Update Form 3File: Q4 FY 2025-26 Shreeja Serene FORM 3 Chartered Accountant Certificate.pdf13 Jun 2026
Withdrawal Update Form 1File: HC Q3 Form 1 Architect Certificate.pdf28 Mar 2026
Withdrawal Update Form 2File: HC Q3 Form 2 Engineers Certificate.pdf28 Mar 2026
Withdrawal Update Form 3File: Q3 Shreeja Serene FORM 3 Chartered Accountant Certificate 31122025.pdf28 Mar 2026
Form 2A (FY 2024-2025)File: HC Form 2A.pdf2 Jan 2026
Form 5 (FY 2024-2025)File: HC FORM 5.pdf2 Jan 2026
Withdrawal Update Form 1File: HC RERA Form 1 Architect Certificate.pdf5 Nov 2025
Withdrawal Update Form 1File: HC RERA Form 1 Architect Certificate.pdf5 Nov 2025
Withdrawal Update Form 2File: HC RERA Form 2 Engineers Certificate.pdf5 Nov 2025
Withdrawal Update Form 2File: HC RERA Form 2 Engineers Certificate.pdf5 Nov 2025
Withdrawal Update Form 3File: HC RERA Form 3 CA Certificate.pdf5 Nov 2025
Withdrawal Update Form 3File: HC RERA Form 3 CA Certificate.pdf5 Nov 2025
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf22 Aug 2025
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf22 Aug 2025
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf22 Aug 2025
Form 1File: HC Form 1 Architect Certificate.pdf19 May 2025
Form 2File: HC Form 2 Engineers Certificate.pdf19 May 2025
Form 3File: HC Form 3.pdf19 May 2025
Disclosure of Sold and Booked InventoryFile: HC Inventory Sold Unsold Q4.pdf19 May 2025
Commencement Certificates / NA Order for plotted developmentFile: Shuddhi patrak.pdf29 Jan 2025
Declaration about Commencement CertificateFile: Shuddhi patrak.pdf29 Jan 2025
Other - TechnicalFile: Shuddhi patrak.pdf29 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Format A.pdf13 Jan 2025
Proforma of Agreement for saleFile: RERA Model Agreement Format_V1.pdf13 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf13 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: CC-2581-24 DT 02-12-2024.pdf10 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: Letter.pdf10 Jan 2025
Other - TechnicalFile: Letter.pdf10 Jan 2025
Copy of the legal title reportFile: GetUserDocumentFileContent.pdf7 Jan 2025
Details of encumbrances concerned to FinanceFile: Self Declaration Finance.pdf31 Dec 2024
Details of encumbrances concerned to FinanceFile: Self Declaration Legal.pdf31 Dec 2024
Proforma of Allotment letterFile: Allotment letter as per order 60.pdf31 Dec 2024
Declaration in FORM BFile: Promoter Affidavit.pdf31 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FINAL Shreeja Serene FORM 3 Chartered Accountant Certificate 27122024.pdf31 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf31 Dec 2024
Other - LegalFile: 712 UPLOAD.pdf31 Dec 2024
Declaration about Commencement CertificateFile: Declaration About CC.pdf31 Dec 2024
CERSAI detailsFile: Undertaking.pdf31 Dec 2024
Deviation Report with respect to Allotment letterFile: Deviation Report Allotment.pdf31 Dec 2024
Details of encumbrances concerned to LegalFile: Self Declaration Finance.pdf31 Dec 2024
Details of encumbrances concerned to LegalFile: Self Declaration Legal.pdf31 Dec 2024
Other - TechnicalFile: Declaration-Cum-Undertaking.pdf31 Dec 2024
Deviation Report with respect to model copy of AgreementFile: RERA Model Agreement Format.pdf31 Dec 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure for Interest.pdf31 Dec 2024
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secured.pdf31 Dec 2024
Layout approvalFile: layout upload.pdf30 Dec 2024
Building plan approvalFile: bldg plan 1.pdf30 Dec 2024
Building plan approvalFile: PLAN-03-03.pdf30 Dec 2024
Copy of Layout Approval (in case of layout)File: layout upload.pdf30 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf30 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: bldg plan 1.pdf30 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: PLAN-03-03.pdf30 Dec 2024
PAN CardFile: pan.pdf21 Dec 2024

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationRegisteredStatusPromisedDelivered
SAI VILLAGE PHASE 1P52100004944Yawat, PuneAug 2017OngoingDec 2026Registered original: Dec 2021Not due yet

How this compares with Pune

3%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREEJA SERENE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Undri13,700+ in Pune

Builder: Yogiraj Krishna Lohokare

Yogiraj Krishna Lohokare has 1 registration on MahaRERA, including SHREEJA SERENE. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SHREEJA SERENE is delayed beyond 30 Jun 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREEJA SERENE?

The registered promoter entity is Yogiraj Krishna Lohokare, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREEJA SERENE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREEJA SERENE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREEJA SERENE?

The professionals named in the filing: Architect: Akansh Aeram Architects; Engineer: Mr. Yogiraj Krishna Lohokare; Chartered Accountant: Phule Wagh & Associates LLP; Chartered Accountant: K L Rajput. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREEJA SERENE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREEJA SERENE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREEJA SERENE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.