Home / Browse projects / Mumbai Suburban, Maharashtra / SHREE SARASWATI CHS LTD PLOT 8B
SHREE SARASWATI CHS LTD PLOT 8B
By NAV DURGA CONSTRUCTION COMPANY
RG-MH-72294 · RERA P51800017436 · Last updated on MahaRERA portal: 21 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 10 complaints at MahaRERA
- Completion date moved by 35 months
- 6 extensions taken
- Rs 11.00 crore secured on the land, in favour of ANAND RATHI GLOBAL FINANCE LTD
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SHREE SARASWATI CHS LTD PLOT 8B is a Residential / Group Housing project by NAV DURGA CONSTRUCTION COMPANY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800017436 on 13 Aug 2018. Possession is promised by 30 Nov 2026. The completion date has moved by 35 months from the original filing. 73 of the 79 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete. 10 complaints are on record with the regulator.
At a glance
Project
- NameSHREE SARASWATI CHS LTD PLOT 8B
- TypeResidential / Group Housing
- Location
- N.G.ACHARYA MARG
- CHEMBUR
- MUMBAI
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- RERA no.P51800017436
- ReraGenie IDRG-MH-72294
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on13 Aug 2018
- Promised completion30 Nov 2026
- Revised completionRevised to 30 Nov 2026 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed126 files
Current status
Figures as on 21 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SHREE SARASWATI CHS LTD BLDG B6 AND A1 | NA | 16 | 14 | 79 | 0 | 79 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 21 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
9 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 90%.
SHREE SARASWATI CHS LTD BLDG B6 AND A1: 92% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 20% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 90% |
Progress on shared amenities15
As on 21 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 5% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed75
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SHREE SARASWATI CHS LTD BLDG B6 AND A1 | NA | Rs 40.00 cr | Rs 38.75 cr |
| - | NA | Rs 14.00 cr | Rs 6.00 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | B H WADHWA & CO |
| Architect | B.H.WADHWA & CO. |
| Engineer | B H WADHWA |
| Engineer | VIJAY NARANG |
| Chartered Accountant | BANWAT & CO |
| Chartered Accountant | BANWAT & CO. |
| Chartered Accountant | P.C.DHOLAKIA & CO |
| Partner | Role in project |
|---|---|
| NAV DURGA CONSTRUCTION COMPANY | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTHE LOCKDOWNS LED TO CONSTRUCTIN ACTIVITIES COMING TO A STANDSTILL DUE TO NON AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW DEVELOPER HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS.
Reason as filed by the promoterDUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS STILL NOT COMPLETED THEREFORE REQUEST TO GIVE EXTENSION UTPTO 31ST MARCH 2025.
Reason as filed by the promoterDUE TO UNRESOLVED FINANCIAL ISSUES THAT HAVE IMPACTED PROGRESS OF THE PROJECT.DESPITE OF OUR BEST EFFORTS THE REQUIRED FIANANCIAL RESORCES ARE NO YET FULL SECURED.WE THEREFORE REQUEST EXTENSION UPTO 31ST DECEMBER 2025
Reason as filed by the promoterDue to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resources deployed at site. We assure you that the interests of the allottees / customers are fully secured, and the project shall be completed within the extended period.
Reason as filed by the promoterNA
Reason as filed by the promoterThe flats are ready for soft possession, and construction is at an advanced stage. The extension is required primarily to facilitate pending bank disbursements, new registrations, completion of necessary documentation and other formalities needed to obtain the Occupation Certificate. Therefore requesting for extension upto November 2026
Complaints filed with MahaRERA10
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12501609 | Dinesh Mahadevan | NAV DURGA CONSTRUCTION COMPANY | 16/05/2025 |
| CC12501615 | Shivaday Dayashankar Shetty | NAV DURGA CONSTRUCTION COMPANY | 16/05/2025 |
| CC12501614 | Hasit Vaishnav | NAV DURGA CONSTRUCTION COMPANY | 16/05/2025 |
| CC12501797 | Praveen Gopinathan | NAV DURGA CONSTRUCTION COMPANY | 31/05/2025 |
| CC12501796 | Praveen Gopinathan | NAV DURGA CONSTRUCTION COMPANY | 31/05/2025 |
| CC12501798 | Lakhminderjeet Singh | NAV DURGA CONSTRUCTION COMPANY | 31/05/2025 |
| CC12501812 | Pankaj Shinde | NAV DURGA CONSTRUCTION COMPANY | 02/06/2025 |
| CC12501811 | Vikas Nirmal | NAV DURGA CONSTRUCTION COMPANY | 02/06/2025 |
| CC12501826 | Kartik Kumar | NAV DURGA CONSTRUCTION COMPANY | 03/06/2025 |
| CC12502006 | Kodanda rama Shetty | NAV DURGA CONSTRUCTION COMPANY | 19/06/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Mar 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Aug 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Feb 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Jan 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Nov 2026
Documents filed126
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 126 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: SRS Form 2A SRS 25 26.pdf | 21 Sep 2026 |
| Form 5 (FY 2025-2026)File: SRS Form 5 SRS 25 26.pdf | 21 Sep 2026 |
| Withdrawal Update Form 1File: FORM 1 SRS MAR 2026.pdf | 19 Sep 2026 |
| Withdrawal Update Form 1File: FORM 1 SRS JUNE 2026.pdf | 19 Sep 2026 |
| Withdrawal Update Form 2File: SRS Form 2MAR 2026.pdf | 19 Sep 2026 |
| Withdrawal Update Form 2File: SRS Form 2 JUNE 2026.pdf | 19 Sep 2026 |
| Withdrawal Update Form 3File: SRS FORM 3 MAR 2026.pdf | 19 Sep 2026 |
| Withdrawal Update Form 3File: SRS FROM 3 JUNE 2026.pdf | 19 Sep 2026 |
| Building plan approvalFile: Approved_Drawing_Saraswati_CHS .pdf | 17 Feb 2026 |
| Building plan approvalFile: SRS 8B- Approved Letter.pdf | 17 Feb 2026 |
| Commencement certificateFile: SRS 8B CC.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 SRS APR TO JUNE 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: FROM 1 SRS JULY TO SEPT 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: FORM 1 SRS OCT TO DEC 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 SRS APR TO JUNE 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 SRS JULY TO SEPT 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 SRS OCT TO DEC 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: SRS FORM 3 APR TO JUNE 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: SRS FORM 3 JULY TO SEPT 2025.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: SRS FORM 3 OCT TO DEC 2025.pdf | 17 Jan 2026 |
| Certificates of CA (Form 3)File: FORM 3.pdf | 2 May 2025 |
| Declaration in FORM BFile: FORM B.pdf | 30 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MARCH 2025.pdf | 30 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 SRS.pdf | 30 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MARCH 2025.pdf | 30 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY SRS DEC 2024.pdf | 30 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY SRSMAR 2025.pdf | 30 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 30 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 30 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SRS Form 1 DEC 2024.pdf | 1 Feb 2025 |
| Certificates of CA (Form 3)File: FORM 3 SRS DEC 2024.pdf | 1 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SRS Form 2 DEC 2024.pdf | 1 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SRS SEPT 2024.pdf | 9 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 SRS SEPT 2024.pdf | 9 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SRS FORM 2 SEPT 2024.pdf | 9 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SRS Form 2 A WITH SIGN.pdf | 17 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SRS Form 2 A WITH SIGN.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: SRS Form 5 WITH SIGN.pdf | 17 Oct 2024 |
| Building plan approvalFile: Approved Letter.pdf | 16 Oct 2024 |
| Building plan approvalFile: Approved_Drawing SRS.pdf | 16 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: SRS 8B CC.pdf | 16 Oct 2024 |
| Building Plan Approval (IOD)File: Approved Letter.pdf | 16 Oct 2024 |
| Building Plan Approval (IOD)File: Approved_Drawing SRS.pdf | 16 Oct 2024 |
| Declaration about Commencement CertificateFile: FORMAT D DECLARATION CC SRS.pdf | 16 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: SRS FORMAT A DESIGNATED BANK AC.pdf | 16 Oct 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: SRS PLOT B DISCLOSURE OF INTEREST.pdf | 16 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SRS FORM 2A 23-24.pdf | 16 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form-5 SRS 23-24.pdf | 16 Oct 2024 |
| Declaration in FORM BFile: FORM B ( SRS).pdf | 9 Oct 2024 |
| Details of encumbrancesFile: SRS ENCUMBRANCE.pdf | 8 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MARCH 2024.pdf | 8 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE 2024.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: FORM 3 MARCH 2024.pdf | 8 Oct 2024 |
| Certificates of CA (Form 3)File: FORM 3 JUNE 2024 SRS.pdf | 8 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MARCH 2024.pdf | 8 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE 2024.pdf | 8 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: SARASWATI INVENTORY 31ST MARCH 2024.pdf | 8 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF INVENTORY JUNE 2024.pdf | 8 Oct 2024 |
| CERSAI detailsFile: CERSAI SRS.pdf | 8 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SRS 31ST DEC 2023.pdf | 28 Mar 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SRS DEC 2023.pdf | 28 Mar 2024 |
| Certificates of CA (Form 3)File: form 3 srs 31st dec 2023.pdf | 28 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MAR 2023.pdf | 21 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 JUNE'23.pdf | 21 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SEPT 2023.pdf | 21 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MARCH 2023.pdf | 21 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 JUNE'23.pdf | 21 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SEPT 2023.pdf | 21 Dec 2023 |
| Certificates of CA (Form 3)File: FORM 3 MARCH 2023.pdf | 21 Dec 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: SRS CC.pdf | 20 Dec 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: REVALID CC SRS.pdf | 20 Dec 2023 |
| Declaration in FORM BFile: NDC FORM B.pdf | 20 Dec 2023 |
| Declaration in FORM BFile: NDC FORM B.pdf | 19 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE TM 2021-22.pdf | 19 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: ENGINEER’S CERTIFICATE FOR QUALITY ASSURANCE TM 2022-23.pdf | 19 Dec 2023 |
| Disclosure of sold/ booked inventoryFile: SRS DISCLOSURE OF IN VENTORY SEPT 2023.pdf | 19 Dec 2023 |
| Certificates of CA (Form 3)File: FORM 3 AS ON 30-06-23.pdf | 26 Oct 2023 |
| Certificates of CA (Form 3)File: FORM 3 AS ON 30-09-23.pdf | 26 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 1-4-2021TO 31-3-2022.pdf | 26 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 1-4-2021TO 31-3-2022.pdf | 26 Oct 2023 |
Promoter's earlier projects3
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| NAV PARMANU CHS LTD | WT PATIL MARG VILLAGE BORLA CHEMBUR MUMBAI 400071 | 60 | Completed | Mar 2016 | Late, Jul 2016 |
| GANGA LAXMI SADAN CHS LTD | HEMU KALANI MARG CHEMBUR MUMBAI 400071 | 36 | Completed | Mar 2016 | Late, Jul 2018 |
| SHREE SARASWATI CHS LTD | N G ACHARYA MARG VILLAGE BORLA CHEMBUR CTS NO 8B MUMBAI 400071 | 193 | Completed | Mar 2015 | Late, Apr 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations, which the RERA portal never shows together
- All 126 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SHREE SARASWATI CHS LTD PLOT 8B on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHEMBUR,MUMBAI6,700+ in Mumbai Suburban
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: NAV DURGA CONSTRUCTION COMPANY
Nav Durga Construction Company has 3 registrations on MahaRERA, including SHREE SARASWATI CHSL PLOT 8 A and JAI GOPI KRISHNA CHSL. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SHREE SARASWATI CHS LTD PLOT 8B is delayed beyond 30 Nov 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SHREE SARASWATI CHS LTD PLOT 8B?
The registered promoter entity is NAV DURGA CONSTRUCTION COMPANY, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SHREE SARASWATI CHS LTD PLOT 8B?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SHREE SARASWATI CHS LTD PLOT 8B?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SHREE SARASWATI CHS LTD PLOT 8B?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SHREE SARASWATI CHS LTD PLOT 8B?
The professionals named in the filing: Architect: B H WADHWA & CO; Architect: B.H.WADHWA & CO.; Engineer: B H WADHWA; Engineer: VIJAY NARANG; Chartered Accountant: BANWAT & CO; Chartered Accountant: BANWAT & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SHREE SARASWATI CHS LTD PLOT 8B?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback