Home / Browse projects / Palghar, Maharashtra / SHREE SALASAR ROW VILLAS

Registered No litigation declared Residential / Group Housing project

SHREE SALASAR ROW VILLAS

By RADHA KRISHNA REALTY

RG-MH-32733 · RERA P99000080420 · Last updated on MahaRERA portal: 28 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 1 other registration and every project registered within 2 km.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Jan 2028Possession promisedno revision filed
5 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 50%
12 of 15Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 65 documents Report an error

SHREE SALASAR ROW VILLAS is a Residential / Group Housing project by RADHA KRISHNA REALTY in Palghar, Maharashtra, registered with MahaRERA as P99000080420 on 3 Jun 2025. Possession is promised by 31 Jan 2028. 3 of the 15 units on this registration are recorded sold or booked, and 5 of 33 construction stages are filed complete.

At a glance

Project

  • NameSHREE SALASAR ROW VILLAS
  • TypeResidential / Group Housing
  • Location
    • -
    • DHANSAR
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000080420
  • ReraGenie IDRG-MH-32733

Builder

  • NameRADHA KRISHNA REALTY
  • Entity typePartnership
  • GSTIN27AAYFR8167K1Z2
  • PartnersRAMASHANKAR K YADAV, RAMSAKAL YADAV, SHIVDEV SHUKLA, DIPESH S MISHRA, SHYAMSUNDER PANDHARI YADAV
  • Other registrations1 more →

Key dates

this monthRegisteredJun 2025PromisedJan 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 Jun 2025
  • Promised completion31 Jan 2028
  • Revised completionNone
  • Buildings3 building records
  • Documents filed65 files

Current status

20%3 of 15 units booked
31.4%Work done, per cost certificate

Figures as on 28 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 1NA22909
BUILDING NO 3NA22404
BUILDING NO 6NA22202

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 28 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 50%.

BUILDING NO 141%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 318%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING NO 60%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 28 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes20%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsYes30%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Open Space15
BuildingOpen SpaceTotal
BUILDING NO 199
BUILDING NO 344
BUILDING NO 622

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area2,105 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Feb 2026
LandownerVillageDistrict
MAYANK GREEN CITYDahisar Taraphe ManorPalghar

Approvals and building plan

Sanctioning authorityVasai Virar City Municipal Corporation
Permissible FSI1328.59
Proposed, not sanctioned1,329 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1ST FLOOR, SAILEELA, ABOVE VIJAYA BANK, ANANDNAGAR, DAHISAR [E], PINCODE - 400068
Estimated costRs 4.54 cr
Cost incurredRs 1.42 cr
Work done31.38%
BuildingWingEstimatedIncurred
BUILDING NO 1NARs 2.39 crRs 1.32 cr
BUILDING NO 3NARs 1.07 crRs 10.69 lakh
BUILDING NO 6NARs 82.48 lakh-
-NARs 25.00 lakh-

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShree Ketan Gopal Sawant
EngineerYogesh Jain
Chartered AccountantJ VIPUL AND ASSOCIATES
PartnerRole in project
RADHA KRISHNA REALTY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jan 2028

Documents filed65

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 shree Salasar qtr 4.pdf28 Apr 2026
Withdrawal Update Form 2File: Form 2 QTR 4 shree Salasar.pdf28 Apr 2026
Withdrawal Update Form 3File: Form 3 qtr 4 shree Salasar.pdf28 Apr 2026
Withdrawal Update Form 1File: FORM 1 QTR 2 SALASAR.pdf12 Feb 2026
Withdrawal Update Form 1File: FORM 1 QTR 3 SALASAR.pdf12 Feb 2026
Withdrawal Update Form 2File: FORM 2 QTR 2 SALASAR.pdf12 Feb 2026
Withdrawal Update Form 2File: FORM 2 QTR 3 SHREE SALASAR.pdf12 Feb 2026
Withdrawal Update Form 3File: FORM 3 QTR 2 SALASAR n.pdf12 Feb 2026
Withdrawal Update Form 3File: FORM 3 QTR 3 SALASAR.pdf12 Feb 2026
Declaration and undertaking (Annexure A)File: Annexure A ORDER NO 50.pdf25 Aug 2025
Other - LegalFile: RERA Queries.pdf8 May 2025
Proforma of Agreement for saleFile: RERA Queries.pdf8 May 2025
Other - LegalFile: RERA QUERIES.pdf25 Apr 2025
Proforma of Agreement for saleFile: RERA QUERIES.pdf25 Apr 2025
Other - LegalFile: Form B.pdf24 Apr 2025
Other - LegalFile: NOC.pdf24 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: fORMAT B LANDOWNER.pdf24 Apr 2025
Other - TechnicalFile: EMAIL FROM AUTHORITY.pdf8 Apr 2025
Other - LegalFile: LEGAL QUERY.pdf5 Apr 2025
Layout approvalFile: LAYOUT COMPRESSED.pdf30 Mar 2025
Layout approvalFile: HIGHLIGHTED PLAN.pdf30 Mar 2025
Building plan approvalFile: BLDG PLANS COMPRESSED.pdf30 Mar 2025
PAN CardFile: PAN Card.pdf30 Mar 2025
Copy of the legal title reportFile: Title Report.pdf30 Mar 2025
Details of encumbrances concerned to FinanceFile: Encumberance Finance.pdf30 Mar 2025
Details of encumbrances concerned to FinanceFile: Encumbrance Legal.pdf30 Mar 2025
Copy of Layout Approval (in case of layout)File: LAYOUT COMPRESSED.pdf30 Mar 2025
Copy of Layout Approval (in case of layout)File: HIGHLIGHTED PLAN.pdf30 Mar 2025
Proforma of Allotment letterFile: Allotment Letter.pdf30 Mar 2025
Declaration in FORM BFile: FORM B.pdf30 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SHREE SALASAR SIGNED.pdf30 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 UPDATED.pdf30 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SHREE SALASAR SIGNED.pdf30 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: BLDG PLANS COMPRESSED.pdf30 Mar 2025
Other - LegalFile: Power of Attorney Dhansar.pdf30 Mar 2025
Other - LegalFile: PARTNERSHIP DEED.pdf30 Mar 2025
Other - LegalFile: conveyance deed_compressed-35-58.pdf30 Mar 2025
Other - LegalFile: conveyance deed_compressed-59-83.pdf30 Mar 2025
Other - LegalFile: SUMMARY OF UNDERSTANDING.pdf30 Mar 2025
Other - LegalFile: 7 12.pdf30 Mar 2025
Other - LegalFile: Authority Letter.pdf30 Mar 2025
Other - LegalFile: Development Agreement Dhansar.pdf30 Mar 2025
Other - LegalFile: conveyance deed_compressed-01-16.pdf30 Mar 2025
Other - LegalFile: conveyance deed_compressed-17-34.pdf30 Mar 2025
Declaration about Commencement CertificateFile: Declaration About Commencement.pdf30 Mar 2025
CERSAI detailsFile: CERSAI.pdf30 Mar 2025
CERSAI detailsFile: CERSAI 1.pdf30 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A DECLARATION ABOUT ACCOUNT RKR.pdf30 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation Allotment.pdf30 Mar 2025
Deviation Report with respect to Allotment letterFile: Allotment Letter Track Changes.pdf30 Mar 2025
Details of encumbrances concerned to LegalFile: Encumberance Finance.pdf30 Mar 2025
Details of encumbrances concerned to LegalFile: Encumbrance Legal.pdf30 Mar 2025
Other - FinanceFile: SUMMARY OF UNDERSTANDING.pdf30 Mar 2025
Other - TechnicalFile: SUMMARY OF UNDERSTANDING.pdf30 Mar 2025
Other - TechnicalFile: Encumbrance others.pdf30 Mar 2025
Other - TechnicalFile: Annexure A ORDER NO 50.pdf30 Mar 2025
Deviation Report with respect to model copy of AgreementFile: AGREEMENT DEVIATION.pdf30 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Agreement Track Changes part 1.pdf30 Mar 2025
Deviation Report with respect to model copy of AgreementFile: Agreement Track Changes part 2.pdf30 Mar 2025
Proforma of Agreement for saleFile: Agreement For Sale.pdf30 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Discl of int in other Organisations.pdf30 Mar 2025
Home Buyer /Allottee Grievance Redressal CellFile: Greivance Redersal.pdf30 Mar 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: format B new.pdf30 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Secured Unsecured Finance.pdf30 Mar 2025

How this compares with Palghar

20%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one has not
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE SALASAR ROW VILLAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHANSAR3,200+ in Palghar

2 kmSHREE SALASAR ROW VILLASCompleted 18Lapsed / revoked 10Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: RADHA KRISHNA REALTY

RADHA KRISHNA REALTY has 2 registrations on MahaRERA, including RADHA KRISHNA RESIDENCY and SHREE SALASAR ROW VILLAS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SHREE SALASAR ROW VILLAS is delayed beyond 31 Jan 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE SALASAR ROW VILLAS?

The registered promoter entity is RADHA KRISHNA REALTY, a partnership as per the filing. Its GSTIN 27AAYFR8167K1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE SALASAR ROW VILLAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE SALASAR ROW VILLAS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE SALASAR ROW VILLAS?

The professionals named in the filing: Architect: Shree Ketan Gopal Sawant; Engineer: Yogesh Jain; Chartered Accountant: J VIPUL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SALASAR ROW VILLAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SALASAR ROW VILLAS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SALASAR ROW VILLAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.