Home / Browse projects / Pune, Maharashtra / SHREE SADGURU HEIGHTS

Registration lapsed No litigation declared Others project

SHREE SADGURU HEIGHTS

By Shree Sadguru Builders and Developers

RG-MH-43147 · RERA P52100048416 · Last updated on MahaRERA portal: 17 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 9 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jan 2026Possession promised9 months past this date
3 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 43 documents Report an error

SHREE SADGURU HEIGHTS is a Others project by Shree Sadguru Builders and Developers in Pune, Maharashtra, registered with MahaRERA as P52100048416 on 3 Jan 2023. Possession was promised by 27 Jan 2026 and is now 9 months past that date. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameSHREE SADGURU HEIGHTS
  • TypeOthers
  • Location
    • PURANDAR COLONY
    • ADARSH NAGAR
    • Kivale
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100048416
  • ReraGenie IDRG-MH-43147

Builder

  • NameShree Sadguru Builders and Developers
  • Entity typePartnership

Key dates

9 months past promisethis monthRegisteredJan 2023First promiseJan 2025Revised toJan 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Jan 2023
  • Promised completion27 Jan 2026
  • Revised completionRevised to 27 Jan 2026 (originally 27 Jan 2025)
  • Buildings1 building record
  • Documents filed43 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE SADGURU HEIGHTSNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 17 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SHREE SADGURU HEIGHTS: 27% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 17 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed18

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots18
Closed/Covered6
Open Space12

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area500 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Arjun TarasDehu Road (CB)Pune

Approvals and building plan

Permissible FSI847.23
Proposed, not sanctioned847 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNIGDI PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAtul Temghare
EngineerSadashiv Harpale
Chartered AccountantVIKAS AGRAWAL
PartnerRole in project
Shree Sadguru Builders and Developers-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100025868Jan 2025 → Jan 2026

Reason as filed by the promoter(1) Due to Global pandemic labours at site were not also material was not available due to that construction work was very slow. (2) Due to Global Pandemic Covid-19 sales of flat was very slow that also affected speed of construction (3) Due to lockdown 2 in year 2021 our construction completion got delayed and due to that we were unable to get Pune Municipal corporation completion certificate

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Jul 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Aug 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jul 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed43

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March 2025 Form 2 Shree Sadguru Heights.pdf17 Jun 2025
Disclosure of sold/ booked inventoryFile: March 25 Disclosure of sold and unsold inventory.pdf17 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 upto march 2025.pdf10 May 2025
Declaration in FORM BFile: Form B Self declarationcompressed.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate upto March 2025 compressedpage0001.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Latest upto 31 march 2025compressed.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate upto june 2024_compressed.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate upto sept 2024_compressed.pdf9 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate upto dec 2024_compressed.pdf9 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a 23 to 24.pdf9 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2a upto 24to25.pdf9 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate uto sept 2024_compressed.pdf3 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch certificate upto dec 2024_compressed.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclsure of sold unsold upto march 2023_compressed.pdf3 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of sold unsold inventory upto 2024_compressed.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a upto june 2024_compressed.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a upto sept 2024_compressed.pdf3 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: form 2a upto dec2024_compressed.pdf3 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5 2023 to 2024_compressed.pdf3 Apr 2025
Proforma of Allotment letterFile: 1mb Model Form of Allotment Letter Sadguru Heights.pdf22 Dec 2022
Proforma of Agreement for saleFile: 1mb Sadguru Model agreement as per RERA.pdf22 Dec 2022
Details of encumbrances concerned to FinanceFile: Encumbrances finance.pdf20 Dec 2022
Details of encumbrances concerned to LegalFile: Encumbrances finance.pdf20 Dec 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants1mb.pdf20 Dec 2022
Deviation Report with respect to Allotment letterFile: Deviation allotment.pdf20 Dec 2022
Deviation Report with respect to model copy of AgreementFile: Deviation agreement.pdf20 Dec 2022
Details of encumbrances concerned to FinanceFile: FINANCE ENCUMBRANCES.pdf13 Oct 2022
Details of encumbrances concerned to LegalFile: ENCUMBRANCES LETTER.pdf26 Sep 2022
Layout approvalFile: Sanction Plan_compressed.pdf16 Aug 2022
Copy of Layout Approval (in case of layout)File: Sanction Plan_compressed.pdf16 Aug 2022
CERSAI detailsFile: CERSAI.pdf16 Aug 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Seprate Bank Account details.pdf16 Aug 2022
Layout approvalFile: Layout Copy.pdf16 Jul 2022
Building plan approvalFile: NA ORDER.pdf16 Jul 2022
PAN CardFile: Sadguru Pancard.pdf16 Jul 2022
Copy of the legal title reportFile: TITEL REPORT.pdf16 Jul 2022
Copy of Layout Approval (in case of layout)File: Layout Copy.pdf16 Jul 2022
Building Plan Approval / NA Order for plotted developmentFile: NA ORDER.pdf16 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: compecment letter.pdf16 Jul 2022
Declaration about Commencement CertificateFile: DECLERATION.pdf16 Jul 2022
Declaration in FORM BFile: SELF DECLERATIO0N.pdf16 Jul 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTURE CERTIFICATE.pdf16 Jul 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERING CERTIFICATE.pdf16 Jul 2022

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE SADGURU HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ADARSH NAGAR13,700+ in Pune

2 kmSHREE SADGURU HEIGHTSCompleted 94Lapsed / revoked 51Other 111Dot size: filed unitsN

Filed coordinates, straight-line distance. 256 registered projects within 2 km.

Builder: Shree Sadguru Builders and Developers

Shree Sadguru Builders and Developers has 1 registration on MahaRERA, including SHREE SADGURU HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SHREE SADGURU HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHREE SADGURU HEIGHTS is delayed beyond 27 Jan 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE SADGURU HEIGHTS?

The registered promoter entity is Shree Sadguru Builders and Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE SADGURU HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE SADGURU HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE SADGURU HEIGHTS?

The professionals named in the filing: Architect: Atul Temghare; Engineer: Sadashiv Harpale; Chartered Accountant: VIKAS AGRAWAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE SADGURU HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE SADGURU HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE SADGURU HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.