Home / Browse projects / Thane, Maharashtra / SHREE KRISHNA HEIGHTS

Registered No litigation declared Residential / Group Housing project

SHREE KRISHNA HEIGHTS

By NANDINI BUILDERS & DEVELOPERS

RG-MH-72818 · RERA P51700048322 · Last updated on MahaRERA portal: 1 Sep 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 15 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 15 months from the original
9 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
18 of 50Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 113 documents Report an error

SHREE KRISHNA HEIGHTS is a Residential / Group Housing project by NANDINI BUILDERS & DEVELOPERS in Thane, Maharashtra, registered with MahaRERA as P51700048322 on 26 Dec 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 32 of the 50 units on this registration are recorded sold or booked, and 9 of 22 construction stages are filed complete.

At a glance

Project

  • NameSHREE KRISHNA HEIGHTS
  • TypeResidential / Group Housing
  • Location
    • NILJE STATION ROAD
    • DOMBIVALI (E)
    • nelje
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700048322
  • ReraGenie IDRG-MH-72818

Builder

  • NameNANDINI BUILDERS & DEVELOPERS
  • Entity typePartnership
  • PartnerNIKITA SUDHIR PATIL

Key dates

this monthRegisteredDec 2022First promiseDec 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on26 Dec 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
  • Buildings2 building records
  • Documents filed113 files

Current status

64%32 of 50 units booked
99.7%Work done, per cost certificate

Figures as on 1 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHREE KRISHNA HEIGHTSNA32101
SHREE KRISHNA HEIGHTSNA8749049

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 1 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

SHREE KRISHNA HEIGHTS0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
SHREE KRISHNA HEIGHTS90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 1 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes60%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes85%
Energy managemcntYes60%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes70%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed43

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots43
Closed/Covered43
BuildingClosed/CoveredTotal
SHREE KRISHNA HEIGHTS33
SHREE KRISHNA HEIGHTS4040

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,800 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Sep 2026
LandownerVillageDistrict
GANESH GOPAL KHANDALEDOMBIVLIThane
JAYWANTI BALIRAM PATILPendharRaigarh
KASHINATH GOPAL KHANDALEDOMBIVLIThane
BHAGWAN KUNDLIK BHANDARIneljeThane
CHANGUNABAI GOPAL KHANDALEneljeThane
SHARDA YASHWANT GAIKWADTisgaonThane
BALIRAM KUNDALIK BHANDARIneljeThane
KASHINATH KUNDALIK BHANDARIDOMBIVLIThane
JOMUBAI SAVALARAM BHOIRKalyanThane

Approvals and building plan

Sanctioning authorityKALYAN DOMBIVALI MUNICIPAL CORPORATION
Permissible FSI3094.32
Proposed, not sanctioned3,094 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 8, HISSA NO 10, SURVEY NO 328, NEHRU ROAD, THANE 421201
Estimated costRs 7.50 cr
Cost incurredRs 7.47 cr
Work done99.67%
BuildingWingEstimatedIncurred
SHREE KRISHNA HEIGHTSNARs 7.25 crRs 7.25 cr
-NARs 25.00 lakhRs 22.50 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJEEV TAYSHETE AND ASSOCIATES
EngineerDEV AND ASSOCIATES
Chartered AccountantRAVI MALVIYA & ASSOCIATES
Chartered AccountantRAJESH TIWARI
Chartered AccountantYOGESH THOMBRE
PartnerRole in project
NANDINI BUILDERS & DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA14082622138Dec 2025 → Mar 2027

Reason as filed by the promoterThe delay in completion of the project was due to financial constraints, supply chain disruptions and slowdown in customer booking which were beyond our reasonable control. However, the project is now back on track, Despite these challenges, We have taken all necessary steps to expedite remaining construction work and committed to completing the project within the extended period sought

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Nov 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed113

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 113 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1_March_2026.pdf1 Sep 2026
Withdrawal Update Form 1File: Form-1_30_06_2026.pdf1 Sep 2026
Withdrawal Update Form 2File: Form-2 Mar-2026.pdf1 Sep 2026
Withdrawal Update Form 2File: Form-2 Jun-2026.pdf1 Sep 2026
Withdrawal Update Form 3File: Form-3 Mar-2026.pdf1 Sep 2026
Withdrawal Update Form 3File: Form-1_30_06_2026.pdf1 Sep 2026
Form 1File: Form-1 March-2023.pdf14 Aug 2026
Form 2File: Form-2 March-2023.pdf14 Aug 2026
Form 3File: Form-3 Signed.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory March-23.pdf14 Aug 2026
Form 1File: Form-1 March-2023.pdf14 Aug 2026
Form 2File: Form-2 March-2023.pdf14 Aug 2026
Form 3File: Form-3 Signed.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory March-23.pdf14 Aug 2026
Form 1File: Form-1 Jun-2023.pdf14 Aug 2026
Form 2File: Form-2 Jun-2023.pdf14 Aug 2026
Form 3File: Form-3 Jun-2023.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Jun-23.pdf14 Aug 2026
Form 1File: Form-1 Sep-2023.pdf14 Aug 2026
Form 2File: Form-2 Sep-2023.pdf14 Aug 2026
Form 3File: Form-3 Sep-2023.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Sep-23.pdf14 Aug 2026
Form 1File: Form-1 Dec-2023.pdf14 Aug 2026
Form 2File: Form-2 Dec-2023.pdf14 Aug 2026
Form 3File: Form-3 Dec-2023.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Dec-23.pdf14 Aug 2026
Form 1File: Form-1 Mar-2024.pdf14 Aug 2026
Form 2File: Form-2 Mar-2024.pdf14 Aug 2026
Form 3File: Form-3 Mar-2024.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Mar-24.pdf14 Aug 2026
Form 1File: Form-1 Jun-2024.pdf14 Aug 2026
Form 2File: Form-2 Jun-2024.pdf14 Aug 2026
Form 3File: Form-3 Jun-2024.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Jun-24.pdf14 Aug 2026
Form 1File: Form-1 Sep-2024.pdf14 Aug 2026
Form 2File: Form-2 Sep-2024.pdf14 Aug 2026
Form 3File: Form-3 Sep-2024.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Sep-24.pdf14 Aug 2026
Form 1File: Form-1 Dec-2024.pdf14 Aug 2026
Form 2File: Form-2 Dec-2024.pdf14 Aug 2026
Form 3File: Form-3 Dec-2024.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Dec-24.pdf14 Aug 2026
Form 1File: Form-1 Mar-2025.pdf14 Aug 2026
Form 2File: Form-2 Mar-2025.pdf14 Aug 2026
Form 3File: Form-3 Mar-2025.pdf14 Aug 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold or Booked Inventory Mar-25.pdf14 Aug 2026
Withdrawal Update Form 1File: Form-1 Jun-2026.pdf14 Aug 2026
Withdrawal Update Form 1File: Form-1 Jun-2025.pdf14 Aug 2026
Withdrawal Update Form 1File: Form-1 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 1File: Form-1 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 1File: Form-1 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 2File: Form-2 Jun-2026.pdf14 Aug 2026
Withdrawal Update Form 2File: Form-2 Jun-2025.pdf14 Aug 2026
Withdrawal Update Form 2File: Form-2 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 2File: Form-2 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 2File: Form-2 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 3File: Form-3 Jun-2026.pdf14 Aug 2026
Withdrawal Update Form 3File: Form-3 Jun-2025.pdf14 Aug 2026
Withdrawal Update Form 3File: Form-3 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 3File: Form-3 Sep-2025.pdf14 Aug 2026
Withdrawal Update Form 3File: Form-3 Jun-2026.pdf14 Aug 2026
Form 2A (FY 2025-2026)File: Form-2A Mar-2026.pdf14 Aug 2026
Form 2A (FY 2024-2025)File: Form-2A Mar-2025.pdf14 Aug 2026
Form 2A (FY 2023-2024)File: Form-2A Mar-2024.pdf14 Aug 2026
Form 2A (FY 2022-2023)File: Form-2A March-2023.pdf14 Aug 2026
Form 5 (FY 2025-2026)File: Form-5 Mar-2026.pdf14 Aug 2026
Form 5 (FY 2024-2025)File: Form-5 Mar-2025.pdf14 Aug 2026
Form 5 (FY 2023-2024)File: Form-5 Mar-2024.pdf14 Aug 2026
Form 5 (FY 2022-2023)File: Form 5 March-2023.pdf14 Aug 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: DocScanner Dec 19, 2024 5-39 PM.pdf6 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5-2023_compressed.pdf6 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5-2023_compressed.pdf6 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form5-2024_compressed.pdf6 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31032024.pdf16 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31062024.pdf16 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2 Date--31-03-2023 -1.pdf16 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 Date--30-06-2023 -2.pdf16 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 Date--30-09-2023 -3.pdf16 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 Date-- 31-12-2023 -4.pdf16 Aug 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2 Date--31-03-2024 -5.pdf16 Aug 2024

How this compares with Thane

64%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 15 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHREE KRISHNA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DOMBIVALI (E)7,600+ in Thane

2 kmSHREE KRISHNA HEIGHTSCompleted 26Lapsed / revoked 10Other 25Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: NANDINI BUILDERS & DEVELOPERS

NANDINI BUILDERS & DEVELOPERS has 1 registration on MahaRERA, including SHREE KRISHNA HEIGHTS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if SHREE KRISHNA HEIGHTS is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHREE KRISHNA HEIGHTS?

The registered promoter entity is NANDINI BUILDERS & DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHREE KRISHNA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHREE KRISHNA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHREE KRISHNA HEIGHTS?

The professionals named in the filing: Architect: RAJEEV TAYSHETE AND ASSOCIATES; Engineer: DEV AND ASSOCIATES; Chartered Accountant: RAVI MALVIYA & ASSOCIATES; Chartered Accountant: RAJESH TIWARI; Chartered Accountant: YOGESH THOMBRE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHREE KRISHNA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHREE KRISHNA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHREE KRISHNA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.