Home / Browse projects / Pune, Maharashtra / Shree Ganesh Gracia Phase II

Registered No litigation declared Others project

Shree Ganesh Gracia Phase II

By Ganesh Realty

RG-MH-05727 · RERA P52100056395 · Last updated on MahaRERA portal: 20 Apr 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
10 of 22Construction stages doneacross 2 buildings; furthest along: Internal walls, 75%
13 of 138Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

Shree Ganesh Gracia Phase II is a Others project by Ganesh Realty in Pune, Maharashtra, registered with MahaRERA as P52100056395 on 31 May 2024. Possession is promised by 31 Dec 2027. 125 of the 138 units on this registration are recorded sold or booked, and 10 of 22 construction stages are filed complete.

At a glance

Project

  • NameShree Ganesh Gracia Phase II
  • TypeOthers
  • Location
    • Survey No. 67/2B/1/1 Kiwale
    • Kiwale
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100056395
  • ReraGenie IDRG-MH-05727

Builder

  • NameGanesh Realty
  • Entity typePartnership
  • PartnersSameer Rajkumar Jhamtani, Harsh Ishwar Jhamtani, Pritpal Charansingh Jhamtani

Key dates

this monthRegisteredMay 2024PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on31 May 2024
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings2 building records
  • Documents filed82 files

Current status

91%125 of 138 units booked
50.9%Work done, per cost certificate

Figures as on 20 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing ANA121265873
Wing BNA121265065

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Internal walls, at 75%.

Wing A57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing B57%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed225

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots225
Closed/Covered225
BuildingClosed/CoveredTotal
Wing A113113
Wing B112112

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area3,475 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on27 May 2025

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Muncipal Corporation
Permissible FSI12534.62
Proposed, not sanctioned12,535 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSai Platinum Society Block J, Pimple Saudagar ,Pimpri Chinchwad Pune - 411027
Estimated costRs 33.40 cr
Cost incurredRs 16.99 cr
Work done50.87%
BuildingWingEstimatedIncurred
Wing ANARs 15.46 crRs 8.50 cr
Wing BNARs 15.46 crRs 8.50 cr
-NARs 2.49 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectYojana Architects
EngineerOmkar Constructions
Chartered AccountantA N J K & Co LLP
Chartered AccountantYashkumar Santosh Soni
Chartered AccountantR V Nevatia & CO
PartnerRole in project
Ganesh Realty-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 30 Apr 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 30 Apr 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Withdrawal Application Form 1.pdf20 Apr 2026
Withdrawal Update Form 2File: Withdrawal Application Form 2.pdf20 Apr 2026
Withdrawal Update Form 3File: Withdrawal Application Form 3.pdf20 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A Quality Assurance Certificate.pdf20 Apr 2026
Withdrawal Update Form 1File: Withdrawal Application Form1.pdf13 Feb 2026
Withdrawal Update Form 2File: Withdrawal Application Form2.pdf13 Feb 2026
Withdrawal Update Form 3File: Withdrawal Application Form3.pdf13 Feb 2026
Form 2A (FY 2024-2025)File: Form 2A Quality Assurance Certificate FY 2024-25_Phase II_Signed.pdf24 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate_June 2025.pdf21 Nov 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate_September 2025.pdf21 Nov 2025
Withdrawal Update Form 2File: Withdrawal Application Form2_June 2025_Gracia Phase II.pdf21 Nov 2025
Withdrawal Update Form 2File: Withdrawal Application Form2_September 2025_Gracia Phase II.pdf21 Nov 2025
Withdrawal Update Form 3File: Withdrawal Application Form3_June 2025_Signed.pdf21 Nov 2025
Withdrawal Update Form 3File: Withdrawal Application Form3_September 2025_Signed.pdf21 Nov 2025
Form 5 (FY 2024-2025)File: CA Form 5_Shree Ganesh Gracia Phase II_FY 2024-25_Signed.pdf19 Nov 2025
Form 1File: Form 1 Architect Certificate - March 2025.pdf2 Jul 2025
Form 2File: Form 2 Engineer Certificate - March 2025.pdf2 Jul 2025
Form 3File: CA Certificate March 2025 - Sign.pdf2 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - March 2025.pdf2 Jul 2025
Withdrawal Update Form 1File: Form 1 Architect Certificate - March 2025.pdf2 Jul 2025
Withdrawal Update Form 2File: Form 2 Engineer Certificate - March 2025.pdf2 Jul 2025
Withdrawal Update Form 3File: CA Certificate March 2025 - Sign.pdf2 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - Sept 2024.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate - Dec 2024.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate September 2024 - Signed.pdf17 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate December 2024 - Signed.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - Sept 2024.pdf17 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate - Dec 2024.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - September 2024.pdf17 Feb 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory - December 2024.pdf17 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Inventory.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June 2024 - Sign_11zon.pdf20 Jul 2024
Other - LegalFile: 1 Legal Title Report Latest.pdf25 May 2024
Details of encumbrances concerned to FinanceFile: encumbrance-scan.pdf23 May 2024
Details of encumbrances concerned to LegalFile: encumbrance-scan.pdf23 May 2024
Other - LegalFile: Declaration relating to Other Real Estate HJ-scan.pdf23 May 2024
Other - LegalFile: Declaration relating to Other Real Estate PA-scan.pdf23 May 2024
Other - LegalFile: Declaration relating to Other Real Estate PJ-scan.pdf23 May 2024
Other - LegalFile: Declaration relating to Other Real Estate SJ-scan.pdf23 May 2024
CERSAI detailsFile: Cersai Asset Based Search Report 17052024.pdf16 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Signed_compressed.pdf2 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration relating to Other Real Estate HJ.pdf1 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration relating to Other Real Estate PJ.pdf1 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Declaration relating to Other Real Estate SJ.pdf1 May 2024
Layout approvalFile: Layout Plan_compressed Coloured.pdf30 Apr 2024
Building plan approvalFile: 2 Parking Ground 8th Floor Plan_compressed.pdf30 Apr 2024
Building plan approvalFile: 3 A Wing 1st to 11th flr Plan_compressed.pdf30 Apr 2024
Building plan approvalFile: 4 A B Wing 9th Floor Plan_compressed.pdf30 Apr 2024
Building plan approvalFile: 5 B Wing Parking 8th Flr Plan_compressed.pdf30 Apr 2024
Building plan approvalFile: 6 B Wing 1st to 11th Flr Plan_compressed.pdf30 Apr 2024
Building plan approvalFile: 7 A B Wing Basement Parking plan_compressed.pdf30 Apr 2024
Building plan approvalFile: 8 A B Wing Terrace Ramp Plan_compressed.pdf30 Apr 2024
Building plan approvalFile: 9 A Wing Elevation_compressed.pdf30 Apr 2024
Building plan approvalFile: 10 B Wing Elevation_compressed.pdf30 Apr 2024
PAN CardFile: GANESH REALTY PAN CARD.pdf30 Apr 2024
Copy of the legal title reportFile: Search Title Report Merged.pdf30 Apr 2024
Details of encumbrances concerned to FinanceFile: Encumbrance_merged.pdf30 Apr 2024
Details of encumbrances concerned to LegalFile: Encumbrance_merged.pdf30 Apr 2024
Copy of Layout Approval (in case of layout)File: Layout Plan_compressed Coloured.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 2 Parking Ground 8th Floor Plan_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 3 A Wing 1st to 11th flr Plan_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 4 A B Wing 9th Floor Plan_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 5 B Wing Parking 8th Flr Plan_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 6 B Wing 1st to 11th Flr Plan_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 7 A B Wing Basement Parking plan_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 8 A B Wing Terrace Ramp Plan_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 9 A Wing Elevation_compressed.pdf30 Apr 2024
Building Plan Approval / NA Order for plotted developmentFile: 10 B Wing Elevation_compressed.pdf30 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_compressed.pdf30 Apr 2024
Declaration about Commencement CertificateFile: Commencement Certificate Declaration.pdf30 Apr 2024
Declaration in FORM BFile: Form B Affidavit_0001.pdf30 Apr 2024
CERSAI detailsFile: CERSAI Undertaking.pdf30 Apr 2024
CERSAI detailsFile: CERSAI_Search_Report_200305406648_For_Asset_Based_Search_01_05_2024_01_18_02_158.pdf30 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Int in other Org PLA.pdf30 Apr 2024
Proforma of Agreement for saleFile: Master Draft RERA - KIWALE-GANESH REALTY- 67 - Ganesh Gracia Phase 2 23052024.pdf30 Apr 2024
Proforma of Allotment letterFile: RERA Allotment Letter Ganesh Gracia Phase 2.pdf30 Apr 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration on Seperate bank account-scan.pdf30 Apr 2024
Deviation Report with respect to Allotment letterFile: Allotment Letter.pdf30 Apr 2024

How this compares with Pune

91%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shree Ganesh Gracia Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kiwale13,700+ in Pune

2 kmShree Ganesh Gracia PhasCompleted 75Lapsed / revoked 45Other 82Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: Ganesh Realty

Ganesh Realty has 1 registration on MahaRERA, including Shree Ganesh Gracia Phase II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Shree Ganesh Gracia Phase II is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shree Ganesh Gracia Phase II?

The registered promoter entity is Ganesh Realty, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shree Ganesh Gracia Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shree Ganesh Gracia Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shree Ganesh Gracia Phase II?

The professionals named in the filing: Architect: Yojana Architects; Engineer: Omkar Constructions; Chartered Accountant: A N J K & Co LLP; Chartered Accountant: Yashkumar Santosh Soni; Chartered Accountant: R V Nevatia & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shree Ganesh Gracia Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shree Ganesh Gracia Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shree Ganesh Gracia Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.