ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Shounak CHSL

Completed No litigation declared Residential / Group Housing project

Shounak CHSL

By Kotibhaskar Infrastructures &Developers Pvt.Ltd.

RG-MH-22092 · RERA P52100030056 · Last updated on MahaRERA portal: 10 Jun 2025

Source: official MahaRERA filing

Red flags

  • Completion date moved by 17 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 138 documents Report an error

Shounak CHSL is a Residential / Group Housing project by Kotibhaskar Infrastructures &Developers Pvt.Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100030056 on 29 Jul 2021. The registration is recorded completed; possession was promised by 30 Jun 2025. The completion date has moved by 17 months from the original filing.

At a glance

Project

  • NameShounak CHSL
  • TypeResidential / Group Housing
  • Location
    • Prabhat Road
    • Bhamburda Shivajinagar
    • Pune (M Corp.)
    • Pune City
    • Pune
    • 411004
  • Pincode411004
  • RERA no.P52100030056
  • ReraGenie IDRG-MH-22092

Builder

  • NameKotibhaskar Infrastructures &Developers Pvt.Ltd.
  • Entity typeCompany
  • CINU45209PN2011PTC140254
  • GSTIN27AAQCS2145B1ZG
  • Managing DirectorsDilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar, Dilip Shivanand Kotibhaskar
  • ChairpersonsChidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar, Chidambar Shivanand kotibhaskar
  • Other registrations27 more →
  • Completed15 of 28
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects11 →

Key dates

this monthRegisteredJul 2021First promiseJan 2024Revised toJun 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on29 Jul 2021
  • Promised completion30 Jun 2025
  • Revised completionRevised to 30 Jun 2025 (originally 8 Jan 2024)
  • Buildings1 building record
  • Documents filed138 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ShounakNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Shounak: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 10 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed37

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots37
Closed/Covered37

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,458 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Kotibhaskar Infrastructures and Developers Pvt LtdPune (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI4794.42
Proposed, not sanctioned2,566 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShirole Bhavan PMT Building Jangali Maharaj Road Pune

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAniruddha T Shinde
ArchitectSHINDE JOSHI AND ASSOCIATES
EngineerShridhar M Shet
EngineerSHRIDHAR - SHET
Chartered AccountantOmkar Chandak
PartnerRole in project
Kotibhaskar Infrastructures &Developers Pvt.Ltd.-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100018749Jan 2024 → Apr 2024

Reason as filed by the promoterWE WANT EXTENSION TO COMPLETE THE FINISHING WORK OF THE PROJECT.

EXT52100019750Jan 2024 → Oct 2024

Reason as filed by the promoterConstruction of the Construction of the said project is almost Completed. We have received the Part Occupancy Certificate from Pune Municipal Corporation, Pune, dated - 26/03/2024 bearing no. OCC/1323/23. Hence, we will be requiring additional time to receive Full Completion Certificate for the said project.

EXT52100025089Jan 2024 → Jun 2025

Reason as filed by the promoterConstruction of the said project is 100% Completed. We have received the Part Occupancy Certificate, for 21 flats with parking, from Pune Municipal Corporation, Pune, dated 26/03/2024 bearing no. OCC/1323/23. Occupancy of 3 flats is pending, for which we require Extension for the period of 3 months i.e till 30.06.2024 to obtain Full Occupancy Certificate from Pune Municipal Corporation. We have already handed over the possession of completed flats to Allottees except the flats of which occupancy is in process. We have already applied for full occupancy certificate vide application dated 14.03.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Jul 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jul 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Dec 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Dec 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 13 Mar 2025

Documents filed138

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: Shounak-Completion-All.pdf10 Jun 2025
Form 1File: LG-Shounak Form-1-30062024.pdf4 Jun 2025
Form 2File: LG-Shounak Form-2-30062024.pdf4 Jun 2025
Form 3File: LG-Shounak Form-3-30062024.pdf4 Jun 2025
Disclosure of Sold and Booked InventoryFile: LG-Shounak-sold unsold-30062024.pdf4 Jun 2025
Form 1File: LG-Shounak Form 1-30092024.pdf4 Jun 2025
Form 2File: Shounak Form-2_0002.pdf4 Jun 2025
Form 3File: Shounak Form-3_0001.pdf4 Jun 2025
Disclosure of Sold and Booked InventoryFile: Shounak- Sold-Unsold Inventory_0001.pdf4 Jun 2025
Form 1File: Shounak Form-1-31122024.pdf4 Jun 2025
Form 2File: Shounak Form-2_0003.pdf4 Jun 2025
Form 3File: Shounak Form-3-31122024.pdf4 Jun 2025
Disclosure of Sold and Booked InventoryFile: Shounak- Sold- Unsold Inventory_0001.pdf4 Jun 2025
Form 1File: FORM 1 SHOUNAK.pdf17 May 2025
Form 2File: ENGG CERTIFICATE.pdf17 May 2025
Form 3File: CA CERTIFICATE.pdf17 May 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf17 May 2025
Form 1File: CA CERTIFICATE.pdf17 May 2025
Form 2File: ENGG CERTIFICATE.pdf17 May 2025
Form 3File: Sold Unsold Inventory.pdf17 May 2025
Form 1File: Sold Unsold Inventory.pdf17 May 2025
Form 2File: CA CERTIFICATE.pdf17 May 2025
Form 3File: ENGG CERTIFICATE.pdf17 May 2025
Disclosure of Sold and Booked InventoryFile: FORM 1 SHOUNAK.PDF17 May 2025
Form 3File: Sold Unsold Inventory.pdf17 May 2025
Form 1File: Sold Unsold Inventory.pdf17 May 2025
Form 3File: LG-Shounak-Form 1-310320223.pdf17 May 2025
Form 1File: Sold Unsold Inventory.pdf17 May 2025
Form 2File: LG-Shounak-Form 1-310320223.pdf17 May 2025
Form 3File: LG-Shounakl-Form 1-30062023.pdf17 May 2025
Disclosure of Sold and Booked InventoryFile: LG-Shounak-Form 2-30062023.pdf17 May 2025
Form 1File: Sold Unsold Inventory.pdf17 May 2025
Form 2File: LG-Shounak-Form 2-30062023.pdf17 May 2025
Form 3File: LG-Shounakl-Form 1-30062023.pdf17 May 2025
Disclosure of Sold and Booked InventoryFile: LG-Shounak-Form 1-310320223.pdf17 May 2025
Form 1File: Sold Unsold Inventory.pdf17 May 2025
Form 2File: LG-Shounak-Form 1-310320223.pdf17 May 2025
Form 3File: LG-Shounak-Form 2-30062023.pdf17 May 2025
Disclosure of Sold and Booked InventoryFile: LG-Shounakl-Form 1-30062023.pdf17 May 2025
Form 1File: LG-Shounak-Form 2-30062023.pdf17 May 2025
Form 2File: Sold Unsold Inventory.pdf17 May 2025
Form 3File: LG-Shounak Form 1-310320234.pdf17 May 2025
Disclosure of Sold and Booked InventoryFile: LG-Shounak Form-2-30032024.pdf17 May 2025
Form 1File: FORM 1 SHOUNAK.pdf16 May 2025
Form 2File: ENGG CERTIFICATE.pdf16 May 2025
Form 3File: CA CERTIFICATE.pdf16 May 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold Inventory.pdf16 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shounak Form-1-31032025.pdf12 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shounak-Full Occupancy-11032025.pdf13 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shounak Form-3_0002.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shounak Form-2_0003.pdf1 Feb 2025
Disclosure of sold/ booked inventoryFile: Shounak- Sold- Unsold Inventory_0001.pdf1 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shounak Form-1_0001.pdf17 Jan 2025
PAN CardFile: KIDPL Pan Card.pdf16 Jan 2025
Declaration in FORM BFile: Shounak Form-B.pdf16 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shounak Form-5_0001.pdf13 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shounak Form-3_0001.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shounak Form-2_0002.pdf18 Nov 2024
Disclosure of sold/ booked inventoryFile: Shounak- Sold-Unsold Inventory_0001.pdf18 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LG-Shounak Form 1-30092024.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shounak Form-2_0001.pdf2 Aug 2024
Disclosure of sold/ booked inventoryFile: Shounak_0001.pdf2 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shounak Form-3_0001.pdf2 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shounak Form-1_0001.pdf12 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Shounak Form-2A-23-24.pdf11 May 2024
CERSAI detailsFile: CERSAI_Search_Report_200306300105_For_Asset_Based_Search_10_05_2024_13_10_55_500.pdf10 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: LG_Annexure A-CDK.pdf10 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: LG_Annxure A-SDK.pdf10 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: LG-Annexure A-SCK.pdf10 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shounak Part Completion.pdf9 May 2024
Disclosure of sold/ booked inventoryFile: LG-Shounak-Sold Unsold-31032024.pdf25 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LG-Shounak Form-2-30032024.pdf22 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: LG-Shubhashree Form-2-31032024.pdf22 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shounak Form 3 -30032024.pdf22 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LG-Shounak Form 1-310320234.pdf16 Apr 2024
Disclosure of sold/ booked inventoryFile: 0001_Shounak sold usold_0001.pdf22 Jan 2024
Declaration in FORM BFile: Form B Shounak_0001.pdf12 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Shounak- CHSL Form 1_0001.pdf12 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shounak Form 2_0001.pdf12 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: LG-Shounak CHSL Form- 2A-21-2022.pdf12 Jan 2024

Promoter's earlier projects11

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

8 delivered on promise2 delivered late1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
INDUKIRAN CO-OP HOUSING SOCIETY LIMITEDP52100046237KOTHRUD, Pune1Jun 2022CompletedNov 2025Oct 2024
SARITA CHSLP52100034229KOTHRUD, Pune70Mar 2022CompletedOct 2025May 2025
Purva HeightsP53100034113Warnali, Sangli36Mar 2022CompletedSep 2025Mar 2025
PRABHAKAR CHSLP52100049315Pune, Pune-Feb 2023CompletedJul 2025Apr 2025
Kajal Co operative Housing Society LtdP52100032652Kothrud, Pune67Jan 2022OngoingDec 2024Not delivered
MUKUNDP52100045860MAHARSHI KARVENAGAR, Pune-Jun 2022CompletedMay 2024Late, Jun 2024
SHUBHASHREEP52100045350PUNE, Pune-May 2022CompletedMar 2024Late, Jun 2024
AnnapurnaHingane Budruk Haveli Pune5-CompletedDec 2017Jun 2017
Ankoorshree Co-operative Housing SocietyHappy Colony Lane 3 Kothrud Pune21-CompletedOct 2017May 2017
Snehvardhan Co-operative Housing SocietyPatwardhan Co-operative Housing Society20-CompletedMay 2017Jan 2017
Chinar Co-operative Housing SocietyKothrud Pune24-CompletedMar 2014Mar 2014

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 17 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shounak CHSL on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bhamburda Shivajinagar13,700+ in Pune

Builder: Kotibhaskar Infrastructures &Developers Pvt.Ltd.

Kotibhaskar Infrastructures &Developers Pvt.Ltd. has 28 registrations on MahaRERA, including Sugam Cooperative Housing Society Limited and Vasant Vihar Co-operative Housing Society. Its filings disclose 11 earlier MahaRERA projects: declares 8 of 10 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Shounak CHSL is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shounak CHSL?

The registered promoter entity is Kotibhaskar Infrastructures &Developers Pvt.Ltd., a company as per the filing. Its CIN U45209PN2011PTC140254 and GSTIN 27AAQCS2145B1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shounak CHSL?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shounak CHSL?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shounak CHSL?

The professionals named in the filing: Architect: Aniruddha T Shinde; Architect: SHINDE JOSHI AND ASSOCIATES; Engineer: Shridhar M Shet; Engineer: SHRIDHAR - SHET; Chartered Accountant: Omkar Chandak. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shounak CHSL?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shounak CHSL. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shounak CHSL to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.