ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SHIVAM RESIDENCY

Registered No litigation declared Residential / Group Housing project

SHIVAM RESIDENCY

By PREET PROMOTER

RG-MH-65333 · RERA P52100052323 · Last updated on MahaRERA portal: 6 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
May 2027Possession promisedno revision filed
4 of 32Construction stages doneacross 3 buildings; furthest along: Stilt Floor, 95%
123 of 220Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 196 documents Report an error

SHIVAM RESIDENCY is a Residential / Group Housing project by PREET PROMOTER in Pune, Maharashtra, registered with MahaRERA as P52100052323 on 10 Aug 2023. Possession is promised by 31 May 2027. 97 of the 220 units on this registration are recorded sold or booked, and 4 of 32 construction stages are filed complete.

At a glance

Project

  • NameSHIVAM RESIDENCY
  • TypeResidential / Group Housing
  • Location
    • S B PATIL SCHOOL ROAD
    • RAVET
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • RERA no.P52100052323
  • ReraGenie IDRG-MH-65333

Builder

  • NamePREET PROMOTER
  • Entity typePartnership
  • PartnersPRAVIN GANGARAMBHAI PATEL, DEEPAK DHANVANT PATEL, PARESH HARIBHAI PATEL, RAMANBHAI RAVJIBHAI PATEL, DINESHBHAI LAXMANBHAI PATEL, SHRIKANT GUNVANT DARADE

Key dates

this monthRegisteredAug 2023PromisedMay 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Aug 2023
  • Promised completion31 May 2027
  • Revised completionNone
  • Buildings3 building records
  • Documents filed196 files

Current status

44%97 of 220 units booked
43.5%Work done, per cost certificate

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C-WINGC Wing16141100110
B-WINGB Wing16141100110
A-WINGA-WING20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 32 construction stages are filed complete across 3 buildings. The stage furthest along is Stilt Floor, at 95%.

C-WING · wing C Wing57%
ActivityProgress
Excavation100%
Basement (if any)45%
Podiums (if any)0%
Plinth45%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises65%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.75%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-WING · wing B Wing40%
ActivityProgress
Excavation100%
Basement (if any)45%
Podiums (if any)0%
Plinth45%
Stilt Floor95%
Slabs of Super Structure75%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A-WING · wing A-WING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)Not applicable
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed350

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots350
Closed/Covered90
Open Space171
Stilt / Ground24
Basement65
BuildingClosed/CoveredOpen SpaceStilt / GroundBasementTotal
C-WING C Wing455600101
B-WING B Wing4511500160
A-WING A-WING00246589

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,065 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on23 Jul 2025
LandownerVillageDistrict
SANJAY DNYNESHWAR TAPKIRPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI21446.86
Proposed, not sanctioned21,447 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTELCO ROAD, MIDC, BHOSARI, PUNE - 411026
Estimated costRs 77.00 cr
Cost incurredRs 33.51 cr
Work done43.52%
BuildingWingEstimatedIncurred
C-WINGC WingRs 28.00 crRs 18.76 cr
B-WINGB WingRs 25.00 crRs 13.75 cr
A-WINGA-WINGRs 20.00 cr-
-NARs 4.00 crRs 1.00 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectNTINBHAI PATEL R PATEL
EngineerSHUBHAM SANDEEP KUTE SANDEEP KUTE
EngineerGAURAV PATEL
Chartered AccountantVaishali Rohidas Gole ROHIDAS GOLE
Chartered Accountantviren pokar
Chartered AccountantPrasant Patel
PartnerRole in project
PREET PROMOTER-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 10 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Nov 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Nov 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 26 Nov 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 May 2027

Documents filed196

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 196 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Withdrawal Application Form1 2025-26 Q-4.pdf6 May 2026
Withdrawal Update Form 2File: Withdrawal Application Form2 2025-26 Q4.pdf6 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (1).pdf6 May 2026
Withdrawal Update Form 1File: FORM-1 2025-26 Q3.pdf5 May 2026
Withdrawal Update Form 2File: FORM-2 2025-26 Q3.pdf5 May 2026
Withdrawal Update Form 3File: Withdrawal Application Form3 (1).pdf5 May 2026
Layout approvalFile: 1 LAYOUT PLAN 16-9-2025.pdf26 Nov 2025
Building plan approvalFile: 2 SECTION PLAN -16-9-2025.pdf26 Nov 2025
Building plan approvalFile: 3 A WING GROUND AND TERRACE FLOOR PLAN 16-9-2025.pdf26 Nov 2025
Building plan approvalFile: 4 B WING 1ST FLOOR AND GROUND FLOOR 16-09-2025.pdf26 Nov 2025
Building plan approvalFile: 5 B WING 2 to 14TH FLOOR PLAN 16-09-2025.pdf26 Nov 2025
Building plan approvalFile: 6 B WING SECTION PLAN 16-09-2025.pdf26 Nov 2025
Building plan approvalFile: 7 B WING ELIVATION PLAN 16-09-2025.pdf26 Nov 2025
Building plan approvalFile: 8 C WING 1st to 12th FLOOR.pdf26 Nov 2025
Building plan approvalFile: 9 C WING 8TH and 13 FLOOR PLAN 16-09-2025.pdf26 Nov 2025
Building plan approvalFile: 10 C WING 14TH FLOOR PLAN 16-09-2025.pdf26 Nov 2025
Building plan approvalFile: 11 C WING ELIVATION PLAN 16-09-2025.pdf26 Nov 2025
Building plan approvalFile: 12 C WING ELIVATION PLAN 16-09-2025.pdf26 Nov 2025
Commencement certificateFile: CC 16-09-2025.pdf26 Nov 2025
Withdrawal Update Form 1File: FORM-1 2025-26 Q2.pdf26 Nov 2025
Withdrawal Update Form 2File: FORM-2 2025-26 Q2.pdf26 Nov 2025
Withdrawal Update Form 3File: FORM-3 2025-26 Q2.pdf26 Nov 2025
Layout approvalFile: 1 LAYOUT PLAN 16-9-2025.pdf17 Nov 2025
Building plan approvalFile: 2 SECTION PLAN -16-9-2025.pdf17 Nov 2025
Building plan approvalFile: 3 A WING GROUND AND TERRACE FLOOR PLAN 16-9-2025.pdf17 Nov 2025
Building plan approvalFile: 4 B WING 1ST FLOOR AND GROUND FLOOR 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 5 B WING 2 to 14TH FLOOR PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 6 B WING SECTION PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 6 B WING SECTION PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 7 B WING ELIVATION PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 8 C WING 1st to 12th FLOOR.pdf17 Nov 2025
Building plan approvalFile: 9 C WING 8TH and 13 FLOOR PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 10 C WING 14TH FLOOR PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 11 C WING ELIVATION PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 11 C WING ELIVATION PLAN 16-09-2025.pdf17 Nov 2025
Building plan approvalFile: 12 C WING ELIVATION PLAN 16-09-2025.pdf17 Nov 2025
Withdrawal Update Form 1File: FORM-1-2025-26-Q1.pdf20 Aug 2025
Withdrawal Update Form 2File: FORM-2 2025-26-Q1.pdf20 Aug 2025
Withdrawal Update Form 3File: FORM-3 2025-26 Q1 - revised.pdf20 Aug 2025
Withdrawal Update Form 1File: FORM-1-2025-26-Q1.pdf8 Aug 2025
Withdrawal Update Form 2File: FORM-2 2025-26-Q1.pdf8 Aug 2025
Withdrawal Update Form 3File: FORM-3 2025-26 Q1 - revised.pdf8 Aug 2025
Withdrawal Update Form 1File: FORM-1-2025-26-Q1.pdf4 Aug 2025
Withdrawal Update Form 2File: FORM-2 2025-26-Q1.pdf4 Aug 2025
Withdrawal Update Form 3File: FORM-3- 2025-26-Q1.pdf4 Aug 2025
Layout approvalFile: 1 LAYOUT - 26-03-2025_1_11zon.pdf23 Jul 2025
Building plan approvalFile: 2 SECTION PALN - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 3 A Wing SECTION PLAN - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 4 B Wing Floor Plan 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 5 B Wing 2 to 9 th Floor and Terrace Plan.pdf23 Jul 2025
Building plan approvalFile: 6 B Wing 8th Floor Plan - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 7 B Wing Elevation Plan - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 8 C Wing - ground and 1st to 12th Floor Plan - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 9 C Wing 8 to 13th Floor Plan and terrace - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 10 C Wing 14th Floor Plan (MHADA) - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 11 SECTION PLAN-26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 12 C Wing ELEVATION - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 1 LAYOUT - 26-03-2025_1_11zon.pdf23 Jul 2025
Building plan approvalFile: 2 SECTION PALN - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 3 A Wing SECTION PLAN - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 4 B Wing Floor Plan 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 5 B Wing 2 to 9 th Floor and Terrace Plan.pdf23 Jul 2025
Building plan approvalFile: 6 B Wing 8th Floor Plan - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 7 B Wing Elevation Plan - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 8 C Wing - ground and 1st to 12th Floor Plan - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 9 C Wing 8 to 13th Floor Plan and terrace - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 10 C Wing 14th Floor Plan (MHADA) - 26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 11 SECTION PLAN-26-03-2025.pdf23 Jul 2025
Building plan approvalFile: 12 C Wing ELEVATION - 26-03-2025.pdf23 Jul 2025
Withdrawal Update Form 1File: FORM-1-2025-26-Q1.pdf23 Jul 2025
Withdrawal Update Form 2File: FORM-2 2025-26-Q1.pdf23 Jul 2025
Withdrawal Update Form 3File: FORM-3- 2025-26-Q1.pdf23 Jul 2025
Form 2A (FY 2023-2024)File: Form-2A 2023-24.pdf23 Jul 2025
Form 2A (FY 2024-2025)File: Form-2A 2024-25.pdf23 Jul 2025
Form 5 (FY 2023-2024)File: FORM-5-2023-24.pdf23 Jul 2025
Form 5 (FY 2024-2025)File: FORM-5-2024-25.pdf23 Jul 2025
Layout approvalFile: 1 LAYOUT - 26-03-2025_1_11zon.pdf21 Jul 2025
Building plan approvalFile: 2 SECTION PALN - 26-03-2025.pdf21 Jul 2025
Building plan approvalFile: 3 A Wing SECTION PLAN - 26-03-2025.pdf21 Jul 2025
Building plan approvalFile: 4 B Wing Floor Plan 26-03-2025.pdf21 Jul 2025

How this compares with Pune

44%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVAM RESIDENCY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near RAVET13,700+ in Pune

Builder: PREET PROMOTER

PREET PROMOTER has 1 registration on MahaRERA, including SHIVAM RESIDENCY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SHIVAM RESIDENCY is delayed beyond 31 May 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVAM RESIDENCY?

The registered promoter entity is PREET PROMOTER, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVAM RESIDENCY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVAM RESIDENCY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVAM RESIDENCY?

The professionals named in the filing: Architect: NTINBHAI PATEL R PATEL; Engineer: SHUBHAM SANDEEP KUTE SANDEEP KUTE; Engineer: GAURAV PATEL; Chartered Accountant: Vaishali Rohidas Gole ROHIDAS GOLE; Chartered Accountant: viren pokar; Chartered Accountant: Prasant Patel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVAM RESIDENCY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVAM RESIDENCY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVAM RESIDENCY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.