Home / Browse projects / Pune, Maharashtra / SHIVAM PRIDE

Registration lapsed No litigation declared Residential / Group Housing project

SHIVAM PRIDE

By GULABRAO SUKLAL DHANGAR

RG-MH-22426 · RERA P52100032049 · Last updated on MahaRERA portal: 27 Jun 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 6%
10 of 20Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

SHIVAM PRIDE is a Residential / Group Housing project by GULABRAO SUKLAL DHANGAR in Pune, Maharashtra, registered with MahaRERA as P52100032049 on 3 Dec 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 12 months from the original filing. 10 of the 20 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHIVAM PRIDE
  • TypeResidential / Group Housing
  • Location
    • REGULAR TRACK ROAD
    • KIWALE
    • Kivale
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100032049
  • ReraGenie IDRG-MH-22426

Builder

  • NameGULABRAO SUKLAL DHANGAR
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live2 lapsed, de-registered or revoked

Key dates

10 months past promisethis monthRegisteredDec 2021First promiseDec 2024Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 Dec 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2024)
  • Buildings1 building record
  • Documents filed58 files

Current status

50%10 of 20 units booked

Figures as on 27 Jun 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shivam PrideNA6520020

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Jun 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 6%.

Shivam Pride: 37% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)1%
Plinth100%
Stilt Floor0%
Slabs of Super Structure6%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Jun 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area624 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
BHORU DULAGI DHAWALEKivalePune
RAMCHANDRA PANDURANG DEVARDEKARPimpri Chinchawad (M Corp.)Pune
SHIVRAM MARUTI LANGHIPune (M Corp.)Pune
SANTOSH RAJARAM JOSHIPune (CB)Pune
OMPRAKASH PANDURANG JOSHIPune (CB)Pune
VANDANA NITIN DHANGARDhule (M Corp.)Dhule

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI973.88
Proposed, not sanctioned974 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDEHU ROAD, KIWALE, PUNE

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr Sachin Balawant Barawade
EngineerBA PATIL
Chartered AccountantDSD assosiates
PartnerRole in project
GULABRAO SUKLAL DHANGAR-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100027815Dec 2024 → Dec 2025

Reason as filed by the promoterFire NOC delayed revised commencement certificate, RCC and internal works have been completed.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Sep 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1-JAN-23 SP.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1-JAN-24 SP.pdf27 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F 1-APR-25 SP.pdf27 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA F3 JAN 25-MAR 25 SP_11zon.pdf27 Jun 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F 2-APR-25 SP.pdf27 Jun 2025
Other - LegalFile: FORM B 1.pdf27 Jun 2025
Other - LegalFile: FORM B 2.pdf27 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Quality Assurance Certificate 20219-20.pdf27 Jun 2025
Disclosure of sold/ booked inventoryFile: SOLD 2025 SP.pdf27 Jun 2025
Other - TechnicalFile: PERT Chart Creative.pdf27 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Quality Assurance Certificate 2021-22.pdf27 Jun 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: CA F5 2024-25 SP.pdf27 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: F 2A-2022-23 SP.pdf23 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F 2A-2022-23 SP.pdf23 Jun 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: F 2A-2023-24 SP.pdf23 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_25.pdf26 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_APR SEP 23.pdf26 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_APR SEP 24.pdf26 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_25.pdf26 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_25.pdf26 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_25.pdf26 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_25.pdf26 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5_23 24.pdf26 Apr 2025
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf26 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5_22 23.pdf26 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5_23 24.pdf26 Apr 2025
Building plan approvalFile: scan 516.pdf8 Mar 2025
Building plan approvalFile: scan 515_11zon.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_25.pdf8 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_APR SEP 23.pdf8 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_APR SEP 24.pdf8 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_JAN MAR 23.pdf8 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_OCT DEC 24.pdf8 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3_OCT MAR 24.pdf8 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2_25.pdf8 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf8 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: scan 516.pdf8 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: scan 515_11zon.pdf8 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5_22 23.pdf8 Mar 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5_23 24.pdf8 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_10012023.pdf24 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf24 Feb 2023
Declaration about Commencement CertificateFile: Declaration of commencecement cert.pdf27 Nov 2021
CERSAI detailsFile: talati_compressed.pdf26 Nov 2021
Proforma of Allotment letterFile: shivam pride Rent Agreement.pdf10 Nov 2021
Details of encumbrancesFile: encumberence.pdf29 Sep 2021
Layout approvalFile: typical floor plan_compressed.pdf28 Sep 2021
Building plan approvalFile: Terrace floor plan_compressed.pdf28 Sep 2021
PAN CardFile: PAN Card.pdf28 Sep 2021
Copy of the legal title reportFile: search and title report_compressed.pdf28 Sep 2021
Copy of Layout Approval (in case of layout)File: typical floor plan_compressed.pdf28 Sep 2021
Building Plan Approval / NA Order for plotted developmentFile: Terrace floor plan_compressed.pdf28 Sep 2021
Commencement Certificates / NA Order for plotted developmentFile: talati_compressed.pdf28 Sep 2021
Declaration in FORM BFile: form b_compressed.pdf28 Sep 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ar cert.pdf28 Sep 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng cert.pdf28 Sep 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate.pdf28 Sep 2021

How this compares with Pune

50%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 12 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHIVAM PRIDE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KIWALE13,700+ in Pune

2 kmSHIVAM PRIDECompleted 101Lapsed / revoked 51Other 111Dot size: filed unitsN

Filed coordinates, straight-line distance. 263 registered projects within 2 km.

Builder: GULABRAO SUKLAL DHANGAR

GULABRAO SUKLAL DHANGAR has 2 registrations on MahaRERA, including SHIVAM PRIDE and VENKATESH PRIDE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that SHIVAM PRIDE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if SHIVAM PRIDE is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHIVAM PRIDE?

The registered promoter entity is GULABRAO SUKLAL DHANGAR, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHIVAM PRIDE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHIVAM PRIDE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHIVAM PRIDE?

The professionals named in the filing: Architect: Ar Sachin Balawant Barawade; Engineer: BA PATIL; Chartered Accountant: DSD assosiates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHIVAM PRIDE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHIVAM PRIDE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHIVAM PRIDE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.