Shanti Luxuria

By RDP Realtores

RG-MH-45548 · RERA P51700012995 · Last updated on MahaRERA portal: 26 Aug 2026

Source: official MahaRERA filing

Red flags

  • 66 complaints at MahaRERA
  • Completion date moved by 58 months
  • 5 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2027Possession promisedmoved 58 months from the original
5 of 11Construction stages donefurthest along: Internal walls, 78%
120 of 315Units unsoldnot recorded sold or booked
66Complaints at MahaRERAon this registration
Jump to the 155 documents Report an error

Shanti Luxuria is a Others project by RDP Realtores in Thane, Maharashtra, registered with MahaRERA as P51700012995 on 11 Sep 2017. Possession is promised by 30 Apr 2027. The completion date has moved by 58 months from the original filing. 195 of the 315 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 66 complaints are on record with the regulator.

At a glance

Project

  • NameShanti Luxuria
  • TypeOthers
  • Location
    • Kalyan Shil Road
    • Village Padle
    • Thane (M Corp.)
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700012995
  • ReraGenie IDRG-MH-45548

Builder

  • NameRDP Realtores
  • Entity typePartnership
  • PartnersDilip Yadav, Premkumar Gangwani, Jitesh Mange, Mitesh Vedprakash Sugla, RDP MERA GHAR LUXURIA PRIVATE LIMITED through its Director Mitesh Vedprakash Sugla, RDP MERA GHAR LUXURIA PRIVATE LIMITED through its Director Raunak Rajan Bandelkar

Key dates

this monthRegisteredSep 2017First promiseJun 2022Revised toApr 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2017
  • Promised completion30 Apr 2027
  • Revised completionRevised to 30 Apr 2027 (originally 30 Jun 2022)
  • Buildings1 building record
  • Documents filed155 files

Current status

62%195 of 315 units booked
89.3%Work done, per cost certificate

Figures as on 26 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shanti LuxuriaNA32323078315

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 26 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 78%.

Shanti Luxuria: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises78%
Sanitary Fittings within the flats / premises2%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks60%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities15

As on 26 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes20%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes10%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed231

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots231
Open Space231

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area7,900 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on12 Dec 2025
LandownerVillageDistrict
Ramdas MhatreThane (M Corp.)Thane
Swapnil MhatreThane (M Corp.)Thane
Indira MhatreThane (M Corp.)Thane
Nitin MhatreThane (M Corp.)Thane

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI12927.76
Proposed, not sanctioned9,019 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUnite No 1 Town Center, Andheri Kurla Road Near Kobe Mumbai Maharashtra
Estimated costRs 66.66 cr
Cost incurredRs 59.55 cr
Work done89.33%
BuildingWingEstimatedIncurred
Shanti LuxuriaNARs 57.91 crRs 57.18 cr
-NARs 8.75 crRs 2.37 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectThe Firm
EngineerMERCURY DESIGNS AND SOLUTIONS PVT LTD
EngineerGopal Rathi
EngineerRAJAN TIPNIS
Chartered AccountantKETAN KATARIA AND ASSOCIATES
Chartered AccountantSSRV & ASSOCIATES
Chartered AccountantPulkit Porwal
Chartered AccountantChirag Surana
Chartered AccountantANKIT GOYANKA
PartnerRole in project
RDP Realtores-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700010768Jun 2022 → Dec 2022

Reason as filed by the promoterWe hereby apply for extension u/s 7 (3) of the registered project bearing vide no P51700012995. As prescribed under circulation no 07/2019 dated 8th Feb 2019, the consent of 51% of the allottees is enclosed herewith.

EXT51700015118Jun 2022 → Dec 2024

Reason as filed by the promoterRespected Sir/Madam, This is in reference to Real Estate Project “Shanti Luxuria” with MahaRERA Project Registration No: P51700012995, whose registration is ending on 30th June 2023. I am writing herewith to kindly request you to grant extension for this project by 18 months thereby extending the registration till December 2024. The aforesaid project was initiated Pre-RERA and had gone into financial difficulties. We partnered with this promoter to revive this lapsed project. In order to ensure financial viability of the project, adjacent land was taken and accordingly, FSI area was increased

EXT51700024959Jun 2022 → Dec 2025

Reason as filed by the promoterAs per the Urban Development Control and Promotion Regulations (UDCPR) guidelines, we supposed to provide adequate number of parking to the flat purchasers. We intend to construct tower parking and for that we have already acquired the land for construction of tower parking. The Corporation granted Commencement Certificate for construction of Tower Parking on 19th September, 2024. However, due to unusually heavy monsoon season, it was not feasible to commence the work. Hence, the Construction work could not be started. Now the monsoon has ended, we are prepared to prioritize the parking work.

EA12122518660Jun 2022 → Dec 2026

Reason as filed by the promoter1) Delay Due to Obstruction of Access Road by Adjacent Land Owner 2) High-tension electrical cables and extensions were laid across the common access route. i) Construction vehicles were unable to enter or exit the project site; ii) Transportation of materials, concrete, machinery, and essential equipment became impossible; iii) Labour movement and access for emergency service vehicles was entirely prevented; and iv) All construction activities from November 2024 to September 2025 were brought to a complete standstill.

P51700012995/WarJun 2022 → Apr 2027

Reason as filed by the promoterNA

Complaints filed with MahaRERA66

Case no.ComplainantRespondentFiled
CC006000000196238Mr. Saumya Kanti GoswamiM/s RDP Realtors03/03/2021
CC006000000210142VIVEK UPADHYAYRDP RELATORS24/03/2023
CC006000000292704Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292708Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292709Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292711Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292713Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292716Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292722Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292724Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292725Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292727Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000292731Mr. Radheshyam Awadhraj YadavM/s. RDP Realtors10/11/2022
CC006000000396705Nilesh Shivaji LendeRDP Realtores18/07/2023
CC006000000396876Alok MukherjeeRDP REALTORES02/08/2023
CC006000000396958Vijay Hiraman KakadeRDP Realtores30/08/2023
CC006000000397038Praveen JoshiRDP Realtors11/08/2023
CC006000000397026Kalpesh ParmarRDP Realtores11/08/2023
CC006000000397042Mangesh RautRDP Realtors11/08/2023
CC006000000397121Vinod SorathiaRDP Realtores17/08/2023
CC006000000397223Dhananjay VarmaRDP Realtores23/08/2023
CC006000000397440Ravindra TiwariRDP Realtores09/09/2023
CC006000000397442Shrikant DubeRDP Realtores09/09/2023
CC006000000397595Jagannath NayakRDP Realtores25/09/2023
CC006000000397844Preetha Balakrishna ShettyRDP Realtores14/10/2023
CC006000000398039Piyush ThakkarRDP Realtores01/11/2023
CC006000000591315RDP REALTORS PRIVATE LIMITEDMr. Jitendra Bharti25/07/2024
CC006000000591316RDP REALTORS PRIVATE LIMITEDMr. Subir Indrajeet Mukherjee25/07/2024
CC006000000591317RDP REALTORS PRIVATE LIMITEDMr. Ramprasad M. Pasi25/07/2024
CC006000000591329RDP REALTORS PRIVATE LIMITEDMR. NAVIN SONCHANDRA SHIGWAN26/07/2024
CC006000000591407RDP REALTORS PRIVATE LIMITEDRAKESHKUMAR B SAROJ02/08/2024
CC006000000591408RDP REALTORS PRIVATE LIMITEDMr. Arvind Kumar Yadav02/08/2024
CC006000000591409RDP REALTORS PRIVATE LIMITEDMrs. Laxmi Shivaji Vanjare02/08/2024
CC006000000591458RDP REALTORS PRIVATE LIMITEDAshok Motilal Gupta08/08/2024
CC006000000591497RDP REALTORS PRIVATE LIMITEDSITARAM SUGREEM PRAJAPATI10/08/2024
CC12500103Gayatri Anirudha RaimaneRDP Realtores11/01/2025
CC12501832RDP PRIVATE LIMITEDNAJISH YUSUF SAYYED04/06/2025
CC12600029SHANMUGARAJAN VELAYUTHAMRDP REALTORS PRIVATE LIMITED03/01/2026
CC12600528Purushottam SinghRDP Realtores30/01/2026
CC12600524Vimal SinghRDP Realtores30/01/2026
CC12600538Puja ChandraRDP Realtores31/01/2026
CC12600541Archana SinghRDP Realtores31/01/2026
CC12600542Soni SinghRDP Realtores31/01/2026
CC12600543Ajay MahajaniRDP Realtores31/01/2026
CC12600546Abhishek KambleRDP Realtores31/01/2026
CC12600573Akash KambleRDP Realtores02/02/2026
CC12600544Shivaji SharmaRDP Realtores31/01/2026
CC12600545Gunjan SinghRDP Realtores31/01/2026
CC12600575Megha ChaurasiaRDP Realtores02/02/2026
CC12600579Ashish PunkarRDP Realtores02/02/2026
CC12600740Anoop SenRDP Realtores09/02/2026
CC12600799Danish SayyedRDP Realtores12/02/2026
CC12600907Sugnaram MistryRDP Realtores19/02/2026
CC12600908Arvind DubeyRDP Realtores19/02/2026
CC12600950RDP PRIVATE LIMITEDMRS SARIKA SUHAS PARAB21/02/2026
CC12600951RDP PRIVATE LIMITEDJASNEET KAUR21/02/2026
CC12601063Pooja MathpatiRDP Realtores26/02/2026
CC12601096Piyush Shankar BhirudRDP Realtores28/02/2026
CC12602323Shahadat Ali MullaRDP Realtores20/04/2026
CC12603341Ravindra PathadeRDP Realtores01/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 21 Jan 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Aug 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 21 Jan 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2027

Documents filed155

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 155 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Shanti Luxuria June 2026.pdf26 Aug 2026
Withdrawal Update Form 2File: Form 2 Engineer Certificate Shanti Luxuria June 2026.pdf26 Aug 2026
Withdrawal Update Form 3File: CA Shanti Luxuria RDP June 2026.pdf26 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A Shanti Luxuria RDP.pdf19 Jun 2026
Withdrawal Update Form 1File: Form 1 Shanti Luxuria Dec 25.pdf13 May 2026
Withdrawal Update Form 1File: Form 1 Shanti Luxuria March 26.pdf13 May 2026
Withdrawal Update Form 2File: Form 2 Shanti Luxuria Dec 25.pdf13 May 2026
Withdrawal Update Form 2File: Form 2 Shanti Luxuria March 26.pdf13 May 2026
Withdrawal Update Form 3File: Form 3 Shanti Luxuria Dec 25.pdf13 May 2026
Withdrawal Update Form 3File: Form 3 Shanti Luxuria March 26.pdf13 May 2026
Form 2A (FY 2024-2025)File: Form 2A Shanti Luxuria.pdf9 Dec 2025
Form 5 (FY 2024-2025)File: Form 5 Shanti Luxuria 31032025.pdf8 Dec 2025
Disclosure of Sold and Booked InventoryFile: Details of Sold Booked March 25.pdf1 Dec 2025
Form 1File: Form 1 Architect Certificate Shanti Luxuria 310325.pdf1 Dec 2025
Form 2File: Form 2 Engineer Certificate Shanti Luxuria 310325.pdf1 Dec 2025
Form 3File: Form 3 Shanti Luxuria 31032025.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: Details of Sold Booked June 25 03092025.pdf1 Dec 2025
Form 1File: Form 1 Shanti June 2025.pdf1 Dec 2025
Form 2File: Form 2 Shanti June 25.pdf1 Dec 2025
Form 3File: Form 3 Shanti Luxuria June 25.pdf1 Dec 2025
Disclosure of Sold and Booked InventoryFile: Details of Sold Booked Sept 25.pdf1 Dec 2025
Form 1File: Architect's Certificate Form 1 Shanti Luxuria Bldg A for RERA dt 300925.pdf1 Dec 2025
Form 2File: Form 2 Engineer Certificate Shanti Luxuria 300925.pdf1 Dec 2025
Form 3File: RERA Certificate RDP Realtors 30092025.pdf1 Dec 2025
Declaration about Commencement CertificateFile: 3 Declaration about Commencement Certificate (1).pdf23 Jan 2025
Declaration about Commencement CertificateFile: 250123122401_0001_250123_122834.pdf23 Jan 2025
Disclosure of sold/ booked inventoryFile: JUNE 2024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: MARCH 2024.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: DEC 2023.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: SEPT 2023.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: JUNE 2023.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: MARCH 2023.pdf22 Jan 2025
Layout approvalFile: 1 Layout Plan 19092024.pdf21 Jan 2025
Copy of Layout Approval (in case of layout)File: 1 Layout Plan 19092024.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Sept 2023.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Dec 2023.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Mar 2024.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate june 2024.pdf21 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate June 2023.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 CA Certificate for Sept 2023.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 30062024.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 31032024.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 31122023.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 30062023.pdf21 Jan 2025
Certificates of CA (Form 3)File: Form 3 31032023.pdf21 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 1-7-24.pdf21 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 1-4-24.pdf21 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form -2 1-1 -24.pdf21 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form-2 1-7-23.pdf21 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form-2 1-4-23_sign.pdf21 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer's Certificate- Sept 2023.pdf21 Jan 2025
Commencement Certificates / NA Order for plotted developmentFile: FORTUNA CC Dt 19092024.pdf21 Jan 2025
Declaration about Commencement CertificateFile: Format D Shanti Luxuria Ph 1.pdf21 Jan 2025
Declaration in FORM BFile: Form B-Affidavit Cum Declaration.pdf22 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate sept 2024.pdf28 Oct 2024
Certificates of CA (Form 3)File: Form 3 Shanti Luxuria Sept 24.pdf28 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate Sept 24.pdf28 Oct 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold inventory.pdf28 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shanti Luxuria - FY 2022-23 (1) (1).pdf25 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shanti Luxuria - FY 2023-24 (1) (1).pdf25 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Shanti Luxuria - FY 2022-23 (1).pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Shanti Luxuria - FY 2023-24 (1).pdf21 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 30_Form-2A-Shanti Luxuria.pdf3 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Shanti Luxuria Form 2A 2023.pdf4 Oct 2023
Other - TechnicalFile: Shanti luxuria schedule sept2024.pdf17 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE1.pdf29 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Dec 2022.pdf2 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Mar 2021.pdf2 Feb 2023
Disclosure of sold/ booked inventoryFile: Sales MIS Dec 2022.pdf2 Feb 2023
Details of encumbrances concerned to FinanceFile: Encrumbance Certificate Legal.pdf12 Jan 2023
Details of encumbrances concerned to LegalFile: Encrumbance Certificate Legal.pdf12 Jan 2023
Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf12 Jan 2023
CERSAI detailsFile: Cersai Report.pdf12 Jan 2023
PAN CardFile: Pan Card.pdf22 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SEP 2022.pdf22 Nov 2022
CERSAI detailsFile: Cersai print with sign and stamp.pdf21 Nov 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE FORM 1.pdf28 Oct 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: form 2A.pdf28 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM -5 QTRJUNE.pdf28 Oct 2022
Details of encumbrancesFile: ENCRUMBANCE CERTIFICATE MORTAGE09.pdf23 Sep 2022

How this compares with Thane

62%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 58 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shanti Luxuria on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Village Padle7,600+ in Thane

2 kmShanti LuxuriaCompleted 41Lapsed / revoked 15Other 48Dot size: filed unitsN

Filed coordinates, straight-line distance. 104 registered projects within 2 km.

Builder: RDP Realtores

RDP Realtores has 1 registration on MahaRERA, including Shanti Luxuria. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Shanti Luxuria is delayed beyond 30 Apr 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shanti Luxuria?

The registered promoter entity is RDP Realtores, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shanti Luxuria?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Shanti Luxuria?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Shanti Luxuria?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shanti Luxuria?

The professionals named in the filing: Architect: The Firm; Engineer: MERCURY DESIGNS AND SOLUTIONS PVT LTD; Engineer: Gopal Rathi; Engineer: RAJAN TIPNIS; Chartered Accountant: KETAN KATARIA AND ASSOCIATES; Chartered Accountant: SSRV & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shanti Luxuria?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shanti Luxuria. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shanti Luxuria to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.