Completed No litigation declared Residential / Group Housing project

Shantai

By WINSTAR INFRA

RG-MH-31748 · RERA P52100080083 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 2 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedregistration recorded completed
5 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 90%
7 of 16Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 39 documents Report an error

Shantai is a Residential / Group Housing project by WINSTAR INFRA in Pune, Maharashtra, registered with MahaRERA as P52100080083 on 23 Apr 2025. The registration is recorded completed; possession was promised by 31 Mar 2028. 9 of the 16 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameShantai
  • TypeResidential / Group Housing
  • Location
    • Gat No. 58 Plot No. 13 & Plot No. 14
    • Pabal Road
    • Near Kasturi Collage
    • Shikrapur
    • Shirur
    • Pune
    • 412208
  • Pincode412208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100080083
  • ReraGenie IDRG-MH-31748

Builder

  • NameWINSTAR INFRA
  • Entity typePartnership
  • GSTIN27AADFW2068D1Z9
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersSaurabh Ashok Dhamdhere, Jayant Hemant Dhamdhere
  • Other registrations2 more →
  • Completed2 of 3

Key dates

this monthRegisteredApr 2025PromisedMar 2028Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Apr 2025
  • Promised completion31 Mar 2028
  • Revised completionNone
  • Buildings1 building record
  • Documents filed39 files

Current status

56%9 of 16 units booked
94.7%Work done, per cost certificate

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA4416016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 90%.

A: 69% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes50%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes60%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes40%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed32

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots32
Closed/Covered2
Open Space30

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area502 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on10 Jul 2025
LandownerVillageDistrict
Mr. Vilas Padmakar KulkarniPimpri Chinchawad (M Corp.)Pune

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority (PMRDA)
Permissible FSI654.98
Proposed, not sanctioned655 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchCOMMERCIAL BUILDING HIRA BAUG TILAK ROAD DISTT PUNE MAHARASHTRA 411002
Estimated costRs 3.03 cr
Cost incurredRs 2.87 cr
Work done94.74%
BuildingWingEstimatedIncurred
ANARs 1.52 crRs 1.44 cr
-NARs 1.52 crRs 1.44 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArchitect Ajit V Thakur
ArchitectAjit Thakur And Associates
EngineerMr Santosh Chavan
EngineerSantosh Ramesh Chavan
Chartered AccountantSatish B Raut and Associates Chartered Accountant
Chartered AccountantSatish B. Raut & Associates
PartnerRole in project
WINSTAR INFRA-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 13 Mar 2025
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Mar 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed39

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupational CertificateFile: PMRDA_OC_Shantai.pdf23 Jun 2026
Withdrawal Update Form 1File: Form1_Architecht Certificate_Shantai_2025-26_Q4.pdf3 Apr 2026
Withdrawal Update Form 2File: Form2 CE Certificate_Shantai_2025-26_Q4.pdf3 Apr 2026
Withdrawal Update Form 3File: From3 CA certificate_Shantai_2025-26_Q4.pdf3 Apr 2026
Withdrawal Update Form 1File: Withdrawal Application Form1_Shantai_202512.pdf12 Jan 2026
Withdrawal Update Form 2File: Withdrawal Application Form2_Shantai_202512.pdf12 Jan 2026
Withdrawal Update Form 3File: Withdrawal Application Form3_Shantai_202512.pdf12 Jan 2026
Withdrawal Update Form 1File: Form1_Shantai.pdf11 Oct 2025
Withdrawal Update Form 2File: Form2_Shantai.pdf11 Oct 2025
Withdrawal Update Form 3File: Form3_Shantai.pdf11 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3_CA_Plot No 13 14.pdf8 Apr 2025
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate_Shantai.pdf8 Apr 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: RERA_Bank Letter.pdf8 Apr 2025
Deviation Report with respect to model copy of AgreementFile: Deviation to model copy of Agreement_Shantai.pdf7 Apr 2025
CERSAI detailsFile: CERSAI_Search_Report_20250323.pdf23 Mar 2025
Proforma of Agreement for saleFile: Proforma of Agreement for sale_compressed (1).pdf23 Mar 2025
Details of encumbrances concerned to FinanceFile: Encumbrances Letter-Finance_Shantai.pdf20 Mar 2025
Details of encumbrances concerned to FinanceFile: Encumbrances Letter-Legal_Shantai.pdf20 Mar 2025
Proforma of Allotment letterFile: Proforma of Allotment letter.pdf20 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: PMRDA_Building Permision.pdf20 Mar 2025
Commencement Certificates / NA Order for plotted developmentFile: PMRDA_Plinth Completion_P 1314.pdf20 Mar 2025
Deviation Report with respect to Allotment letterFile: Deviation to allotment letter_Shantai.pdf20 Mar 2025
Details of encumbrances concerned to LegalFile: Encumbrances Letter-Finance_Shantai.pdf20 Mar 2025
Details of encumbrances concerned to LegalFile: Encumbrances Letter-Legal_Shantai.pdf20 Mar 2025
Other - FinanceFile: Declaration cum Undertaking_Landowner.pdf20 Mar 2025
Other - TechnicalFile: Declaration Annexure A.pdf20 Mar 2025
Copy of the legal title reportFile: Legal Report_Shantai.pdf13 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_Engineer Certificate.pdf13 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration Separate Bank Account Details.pdf13 Mar 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: Declaration cum Undertaking.pdf13 Mar 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations_Shantai.pdf13 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of secured unsecured loan_Shantai.pdf13 Mar 2025
Layout approvalFile: PMRDA_SanctionDWG.pdf12 Mar 2025
Building plan approvalFile: NA_Order.pdf12 Mar 2025
PAN CardFile: WinStar Infra_Pan Card.pdf12 Mar 2025
Copy of Layout Approval (in case of layout)File: PMRDA_SanctionDWG.pdf12 Mar 2025
Declaration in FORM BFile: From B_Plot No 1314_Promoter.pdf12 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1_Architects Certificate_Shantai.pdf12 Mar 2025
Building Plan Approval / NA Order for plotted developmentFile: NA_Order.pdf12 Mar 2025

How this compares with Pune

56%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shantai on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Pabal Road, Near Kasturi Collage13,700+ in Pune

2 kmShantaiCompleted 8Lapsed / revoked 19Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 39 registered projects within 2 km.

Builder: WINSTAR INFRA

WINSTAR INFRA has 3 registrations on MahaRERA, including Nandan and Dnyaneshwar. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Shantai is delayed beyond 31 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shantai?

The registered promoter entity is WINSTAR INFRA, a partnership as per the filing. Its GSTIN 27AADFW2068D1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shantai?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shantai?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shantai?

The professionals named in the filing: Architect: Architect Ajit V Thakur; Architect: Ajit Thakur And Associates; Engineer: Mr Santosh Chavan; Engineer: Santosh Ramesh Chavan; Chartered Accountant: Satish B Raut and Associates Chartered Accountant; Chartered Accountant: Satish B. Raut & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shantai?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shantai. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shantai to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.