Registered No litigation declared Residential / Group Housing project

SHANKAR DARSHAN CHS LTD

By MAJESTIC ROYALE DEVELOPERS

RG-MH-07000 · RERA P51800055178 · Last updated on MahaRERA portal: 27 May 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 9 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
4 of 11Construction stages donefurthest along: Internal walls, 90%
35 of 42Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 68 documents Report an error

SHANKAR DARSHAN CHS LTD is a Residential / Group Housing project by MAJESTIC ROYALE DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800055178 on 11 Mar 2024. Possession is promised by 31 Dec 2026. 7 of the 42 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.

At a glance

Project

  • NameSHANKAR DARSHAN CHS LTD
  • TypeResidential / Group Housing
  • Location
    • 15TH ROAD
    • R.C. MARG
    • CHEMBUR
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800055178
  • ReraGenie IDRG-MH-07000

Builder

  • NameMAJESTIC ROYALE DEVELOPERS
  • Entity typePartnership
  • GSTIN27ABIFM4670P1ZJ
  • PartnersREKHA DILIP KOTHARI, BHAGYAWATI KAILASH PARMAR, LATA KAILASH KOTHARI, AFTAB AYAZ MULANI, SEJAL LOKESH JAIN, VINODKUMAR MISHRIMAL JAIN, RUCHITA JITENDRA CHOUDHARY
  • Other registrations9 more →
  • Completed4 of 10

Key dates

this monthRegisteredMar 2024PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Mar 2024
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed68 files

Current status

17%7 of 42 units booked
67.6%Work done, per cost certificate

Figures as on 27 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SHANKAR DARSHAN CHSLNA141338442

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

SHANKAR DARSHAN CHSL: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises85%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.65%

Progress on shared amenities15

As on 27 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed75

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots75
Closed/Covered75

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,372 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Aug 2025
LandownerVillageDistrict
SHANKAR DARSHAN CHS LTDChemburMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4416.52
Proposed, not sanctioned1,155 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRUNWAL RESIDENCY, NEAR HOTEL MALHAR, D K SANDHU MARG, CHEMBUR EAST MUMBAI- 400071
Estimated costRs 17.00 cr
Cost incurredRs 11.50 cr
Work done67.63%
BuildingWingEstimatedIncurred
SHANKAR DARSHAN CHSLNARs 15.00 crRs 10.23 cr
-NARs 2.00 crRs 1.26 cr

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArvind Mhatre
ArchitectAIMS Consultants
EngineerVINAYAK VIKAS GOKHALE
EngineerAssociated Structural Engineers LLP
Chartered AccountantMEHATA AND ASSOCIATES CHARTERED ACCOUNTANTS
Chartered AccountantP C SURANA & CO
Chartered AccountantNehali & Co.
PartnerRole in project
MAJESTIC ROYALE DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Mar 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 12 May 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 12 May 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 May 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed68

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 March 2026 Shankar Darshan.pdf27 May 2026
Withdrawal Update Form 2File: Form 2 March 2026 Shankar Darshan.pdf27 May 2026
Withdrawal Update Form 3File: Form 3 March 2026 Shankar Darshan.pdf27 May 2026
Withdrawal Update Form 1File: Form 1 Dec 2025.pdf7 Mar 2026
Withdrawal Update Form 1File: Form 1 Dec 2025.pdf7 Mar 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf7 Mar 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf7 Mar 2026
Withdrawal Update Form 3File: Revised Form 3 Dec 2025.pdf7 Mar 2026
Withdrawal Update Form 3File: Revised Form 3 Dec 2025.pdf7 Mar 2026
Withdrawal Update Form 1File: Form 1 Dec 2025.pdf26 Feb 2026
Withdrawal Update Form 2File: Form 2 Dec 2025.pdf26 Feb 2026
Withdrawal Update Form 3File: Form 3 Dec 2025.pdf26 Feb 2026
Withdrawal Update Form 1File: Form 1 Shankar Darshan Sep 2025.pdf15 Nov 2025
Withdrawal Update Form 2File: Form 2 Shankar Darshan Sep 2025.pdf15 Nov 2025
Withdrawal Update Form 3File: CA Form 3 Shankar Darshan September 2025.pdf15 Nov 2025
Layout approvalFile: CC Drawing_compressed.pdf12 May 2025
Building plan approvalFile: CC Drawing_compressed.pdf12 May 2025
Copy of Layout Approval (in case of layout)File: CC Drawing_compressed.pdf12 May 2025
Commencement Certificates / NA Order for plotted developmentFile: Further CC.pdf12 May 2025
Building Plan Approval / NA Order for plotted developmentFile: CC Drawing_compressed.pdf12 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 2025.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2025.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2025.pdf12 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1 December 2024.pdf25 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3 December 2024 (2).pdf25 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 December 2024 SD.pdf25 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 2023-24.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 March 2024 SD.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 June 2024 SD.pdf13 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 September 2024 SD.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 March 2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 June 2024.pdf13 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Setptember 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2024.pdf13 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 September 2024.pdf13 Jan 2025
Copy of the legal title reportFile: Advocate letter 2.pdf6 Mar 2024
Other - LegalFile: Advocate letter 2.pdf6 Mar 2024
Other - TechnicalFile: RERA Order No 50.pdf6 Mar 2024
Other - TechnicalFile: Declaration Sanctioned Units.pdf6 Mar 2024
Copy of the legal title reportFile: Conveyance Deed Index -2.pdf10 Feb 2024
Copy of the legal title reportFile: Conveyance Deed Shankar Darshan.pdf10 Feb 2024
Copy of the legal title reportFile: Rera Title Report VB 02102023.pdf10 Feb 2024
Layout approvalFile: Drawing IOD.pdf25 Jan 2024
Building plan approvalFile: Drawing IOD.pdf25 Jan 2024
Copy of Layout Approval (in case of layout)File: Drawing IOD.pdf25 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: Drawing IOD.pdf25 Jan 2024
Proforma of Agreement for saleFile: Model Rera Agrement Shankar Darshan.pdf25 Jan 2024
Deviation Report with respect to model copy of AgreementFile: Deviation in RERA Agreement.pdf25 Jan 2024
Other - LegalFile: MRD Deed Scan New_compressed (1).pdf21 Dec 2023
Details of encumbrances concerned to FinanceFile: Encumbrances legal.pdf20 Dec 2023
Details of encumbrances concerned to LegalFile: Encumbrances legal.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Ca Certificate 2.pdf20 Dec 2023
Proforma of Allotment letterFile: Rera Allotment.pdf20 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Details Letter.pdf20 Dec 2023
Deviation Report with respect to Allotment letterFile: DEVIATION IN RERA Allotment.pdf20 Dec 2023
Copy of the legal title reportFile: Search Report.pdf13 Nov 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations.pdf9 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Shankar Darshan.pdf3 Nov 2023
CERSAI detailsFile: Cersai Certirficate Undertaking Shankar Dharshan.pdf3 Nov 2023
PAN CardFile: Majestic Royale Developers Pan Card.pdf2 Nov 2023
Details of encumbrances concerned to FinanceFile: Encumbrances Financial.pdf2 Nov 2023
Details of encumbrances concerned to LegalFile: Encumbrances Financial.pdf2 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: Shankar dharshan CC.pdf2 Nov 2023
Declaration about Commencement CertificateFile: CC Declaration Certificate.pdf2 Nov 2023
Declaration in FORM BFile: Form B 3 (4) RERA.pdf2 Nov 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Signed.pdf2 Nov 2023
CERSAI detailsFile: Cersai Search Report.pdf2 Nov 2023

How this compares with Mumbai Suburban

17%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHANKAR DARSHAN CHS LTD on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHEMBUR6,700+ in Mumbai Suburban

2 kmSHANKAR DARSHAN CHS LTDCompleted 164Lapsed / revoked 137Other 174Dot size: filed unitsN

Filed coordinates, straight-line distance. 475 registered projects within 2 km.

Builder: MAJESTIC ROYALE DEVELOPERS

MAJESTIC ROYALE DEVELOPERS has 10 registrations on MahaRERA, including SRINIKETAN and AMARJYOTI CHS LTD. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SHANKAR DARSHAN CHS LTD is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHANKAR DARSHAN CHS LTD?

The registered promoter entity is MAJESTIC ROYALE DEVELOPERS, a partnership as per the filing. Its GSTIN 27ABIFM4670P1ZJ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHANKAR DARSHAN CHS LTD?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SHANKAR DARSHAN CHS LTD?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHANKAR DARSHAN CHS LTD?

The professionals named in the filing: Architect: Arvind Mhatre; Architect: AIMS Consultants; Engineer: VINAYAK VIKAS GOKHALE; Engineer: Associated Structural Engineers LLP; Chartered Accountant: MEHATA AND ASSOCIATES CHARTERED ACCOUNTANTS; Chartered Accountant: P C SURANA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHANKAR DARSHAN CHS LTD?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHANKAR DARSHAN CHS LTD. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHANKAR DARSHAN CHS LTD to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.