Registration lapsed No litigation declared Others project

Shankar Bhavan Premises Co-operative Society Limited

By Mishal Construction Private Limited

RG-MH-24405 · RERA P51900009596 · Last updated on MahaRERA portal: 3 Jan 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Completion date moved by 78 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
5 of 11Construction stages donefurthest along: Internal walls, 7%
18 of 28Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 41 documents Report an error

Shankar Bhavan Premises Co-operative Society Limited is a Others project by Mishal Construction Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51900009596 on 22 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 78 months from the original filing. 10 of the 28 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete.

At a glance

Project

  • NameShankar Bhavan Premises Co-operative Society Limited
  • TypeOthers
  • Location
    • D K Sandhu Marg & 11th Road
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900009596
  • ReraGenie IDRG-MH-24405

Builder

  • NameMishal Construction Private Limited
  • Entity typeCompany
  • ChairpersonNaveenkumar Mishrimal Jain
  • Other registrations10 more →
  • No longer live9 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseDec 2019Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on22 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed41 files

Current status

36%10 of 28 units booked

Figures as on 3 Jan 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shankar Bhavan Premises Co-operative Society LimitedNA151527128

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jan 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 7%.

Shankar Bhavan Premises Co-operative Society Limited: 46% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises7%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 3 Jan 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Closed/Covered26
Open Space2

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area791 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on13 Jan 2026

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI2082.41
Proposed, not sanctioned1,230 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop No 16, Ground Flr, Kanakia Zillion, LBS CST Rd Junction, BKC, Kurla W, Mumbai-400070

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIKKON Architects
ArchitectNasa Architectural Consultant Pvt Ltd
ArchitectMS Nambarch
EngineerAssociated Consultants
Chartered AccountantR.B Ashar
PartnerRole in project
Mishal Construction Private Limited-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800005520Dec 2019 → Dec 2020

Reason as filed by the promoterDue to change in Approval authority, draft development plan has come into force effecting from September 2018 and implementation on the same has been clarified by certain circulars during the process latest in September 2019, the proposal need to be approved in accordance with the new DCR-2034 for the above floors. The revised plans are now approved by the Hon. Municipal Commissioner and now we are in process of obtaining further approvals in accordance with the provisions of new DCR. As the same was delayed beyond our control due to implementation of new DCR and amendments thereafter.

EXT51800010434Dec 2019 → Dec 2022

Reason as filed by the promoterDue to Change in Policy & Pandemics

EXT51800013272Dec 2019 → Dec 2023

Reason as filed by the promoterCovid

EA16012619467Dec 2019 → Jun 2026

Reason as filed by the promoterFirstly, during the period of execution, the outbreak of the COVID-19 pandemic severely disrupted construction activities, availability of labour, supply chains, and functioning of government offices. The lockdowns and subsequent restrictions resulted in unavoidable delays in processing approvals as well as execution of work. Secondly, there was a significant change in the approval regime. The Draft Development Plan came into force with effect from September 2018, and its implementation was clarified through various circulars issued from time to time, the latest being in September 2019. Pursua

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 20 Feb 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed41

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: SB-Form-1-31 March 2023.pdf3 Jan 2026
Form 2File: SB-Form-2- March- 2023.pdf3 Jan 2026
Form 3File: SB - Form 3- March 2023.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Booked inventory.pdf3 Jan 2026
Form 1File: SB- Form -1-30 june 2023.pdf3 Jan 2026
Form 2File: SB-Form-2- June- 2023.pdf3 Jan 2026
Form 3File: SB - Form 3- June 2023.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Booked inventory.pdf3 Jan 2026
Form 1File: SB- Form -1-30 sept 2023.pdf3 Jan 2026
Form 2File: SB-Form-2- Sept- 2023.pdf3 Jan 2026
Form 3File: SB - Form 3- Sept 2023.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Booked inventory.pdf3 Jan 2026
Form 1File: SB-Form-1-31 - Dec 2023.pdf3 Jan 2026
Form 2File: SB-Form-2- Dec- 2023.pdf3 Jan 2026
Form 3File: SB - Form 3-Dec 2023.pdf3 Jan 2026
Disclosure of Sold and Booked InventoryFile: Booked inventory.pdf3 Jan 2026
Declaration about Commencement CertificateFile: FORMAT D.pdf7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2 SB.pdf7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2 SB.pdf7 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_Shankar Bhavan.pdf7 Apr 2022
Disclosure of sold/ booked inventoryFile: CIRCULAR 29 Sold Unsold.pdf7 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Shankar Bhavan 18-19.pdf7 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: SB 19-20.pdf7 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: SB 20-21.pdf7 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: FurtherCC_signed.pdf20 Feb 2021
Details of encumbrancesFile: Encumbarance Certificate Shankar Bhavan_compressed.pdf31 Oct 2019
Annual Audit Report of Statutory CA (Form 5)File: FORM 5 SHANKAR BHAVAN CHS.pdf11 Sep 2019
Proforma of Allotment letterFile: AGREEMENTFORSALE - SHANKAR BHAVAN.pdf31 Oct 2017
Building plan approvalFile: IOD_Shankar Bhavan.pdf28 Jul 2017
Details of encumbrancesFile: Shankar Bhawan _Encumbrance certificate.pdf28 Jul 2017
Building Plan Approval (IOD)File: IOD_Shankar Bhavan.pdf28 Jul 2017
Declaration in FORM BFile: form b shankar bhavan.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Shankar Bhavan_Architect Certificate.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Shankar Bhawan Engg Certificate.pdf28 Jul 2017
Certificates of CA (Form 3)File: Form 3_Shankar Bhavan.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment Letter Draft Shankar Bhavan.pdf28 Jul 2017
Layout approvalFile: Layout Plan.pdf27 Jul 2017
PAN CardFile: Mishal Construction Private Limited PAN card.pdf27 Jul 2017
Copy of the legal title reportFile: TITLE CERTIFICATE.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.PDF27 Jul 2017

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Mahesh Villa Ghatkopar Cooperative Housing Society LtdPlot No 12 Vallabhaug Lane Garodia Nagar Ghatkopar East Mumbai - 40007716CompletedDec 2015Late, Jun 2017
Mohan Sadan Co-Operative Housing Society LtdPlot No 2A of TPS III CTS No 5991 MG Road Ghatkopar East Mumbai 40007726CompletedJun 2015Late, Sep 2015

How this compares with Mumbai Suburban

36%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 78 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Shankar Bhavan Premises Co-operative Society on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur6,700+ in Mumbai Suburban

2 kmShankar Bhavan Premises Completed 158Lapsed / revoked 129Other 160Dot size: filed unitsN

Filed coordinates, straight-line distance. 447 registered projects within 2 km.

Builder: Mishal Construction Private Limited

Mishal Construction Private Limited has 11 registrations on MahaRERA, including Gagan Vihar Co-operative Housing Society Limited and Gulistan Manzil Co-operative Housing Society Limited. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that Shankar Bhavan Premises Co-operative Society Limited shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Shankar Bhavan Premises Co-operative Society Limited is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Shankar Bhavan Premises Co-operative Society Limited?

The registered promoter entity is Mishal Construction Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Shankar Bhavan Premises Co-operative Society Limited?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Shankar Bhavan Premises Co-operative Society Limited?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Shankar Bhavan Premises Co-operative Society Limited?

The professionals named in the filing: Architect: IKKON Architects; Architect: Nasa Architectural Consultant Pvt Ltd; Architect: MS Nambarch; Engineer: Associated Consultants; Chartered Accountant: R.B Ashar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Shankar Bhavan Premises Co-operative Society Limited?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Shankar Bhavan Premises Co-operative Society Limited. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Shankar Bhavan Premises Co-operative Society to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.