SERENO

By TRIO INFRASTRUCTURE PRIVATE LIMITED

RG-MH-06424 · RERA P99000053269 · Last updated on MahaRERA portal: 25 Sep 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 16 months
  • 2 extensions taken
  • Rs 40.00 crore secured on the land, in favour of state bank of india

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Apr 2028Possession promisedmoved 16 months from the original
5 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 74%
228 of 449Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 73 documents Report an error

SERENO is a Residential / Group Housing project by TRIO INFRASTRUCTURE PRIVATE LIMITED in Palghar, Maharashtra, registered with MahaRERA as P99000053269 on 23 Oct 2023. Possession is promised by 30 Apr 2028. The completion date has moved by 16 months from the original filing. 221 of the 449 units on this registration are recorded sold or booked, and 5 of 22 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSERENO
  • TypeResidential / Group Housing
  • Location
    • Gokhiware
    • VASAI
    • Vasai-Virar City (M Corp)
    • Palghar
    • 401208
  • Pincode401208
  • RERA no.P99000053269
  • ReraGenie IDRG-MH-06424

Builder

  • NameTRIO INFRASTRUCTURE PRIVATE LIMITED
  • Entity typeCompany
  • DirectorsBALAJI RAGHAVAN, MANOJSHANKAR AMBIKAPRASAD TRIPATHI

Key dates

this monthRegisteredOct 2023First promiseDec 2026Revised toApr 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Oct 2023
  • Promised completion30 Apr 2028
  • Revised completionRevised to 30 Apr 2028 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed73 files

Current status

49%221 of 449 units booked
32.2%Work done, per cost certificate

Figures as on 25 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
E WINGNA25222160216
H WINGNA252321617233

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 25 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 74%.

E WING14%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth50%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
H WING50%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure74%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises27%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks51%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 25 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed729

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots729
Closed/Covered715
Open Space14
BuildingClosed/CoveredOpen SpaceTotal
E WING38514399
H WING3300330

Land and ownership3

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,462 sq m
Land owned byNot the promoter
Named landowners3
Encumbrance on the landDeclared present
Charge in favour ofstate bank of india
Secured amountRs 40.00 crore
CERSAI search filedYes
Declared on27 Nov 2025
LandownerVillageDistrict
Anil Ramchandra GuptaVasai-Virar City (M Corp)Palghar
Devendra Rajanikant LadhaniVasai-Virar City (M Corp)Palghar
Mukesh Shivdas SonarVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityVASAI VIRAL CITY MUNCIPAL CORARATION
Permissible FSI26031.67
Proposed, not sanctioned26,032 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSTATE BANK OF INDIA, 1ST FLOOR, LANDMARK BUILDING, S.V.ROAD BORIVALI WEST BRANCH MUMBAI 400092
Estimated costRs 152.85 cr
Cost incurredRs 49.26 cr
Work done32.23%
BuildingWingEstimatedIncurred
E WINGNARs 70.10 crRs 9.11 cr
H WINGNARs 64.75 crRs 40.15 cr
-NARs 18.00 cr-

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANAT MEHTA & ASSOCIATES
EngineerMUKESH KUMAR
EngineerOmkesh Umesh Chaurasia
Chartered AccountantS C SHAH & COMPANY
Chartered AccountantA SACHDEV & CO
PartnerRole in project
TRIO INFRASTRUCTURE PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000019198Dec 2026 → Dec 2027

Reason as filed by the promoterWe are not able to complete project on time due to delay in commencement of the construction work, delayed sales and shortage of materials and manpower. We would like to request you to please grant us an additional 12 months extension until 30/12/2027.

P99000053269/WarDec 2026 → Apr 2028

Reason as filed by the promoterNA

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500336Deepika Anil SoniTRIO INFRASTRUCTURE PRIVATE LIMITED31/01/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 2 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 2 Mar 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Apr 2028

Documents filed73

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: ANNEXURE F FORM 5 .pdf25 Sep 2026
Form 2A (FY 2025-2026)File: FORM 2A -FY 25-26sd.pdf19 Sep 2026
Withdrawal Update Form 1File: FORM-1.pdf7 Sep 2026
Withdrawal Update Form 2File: FORM-2.pdf7 Sep 2026
Withdrawal Update Form 3File: FORM-3.pdf7 Sep 2026
Withdrawal Update Form 1File: FROM 1 Q4.pdf6 Jun 2026
Withdrawal Update Form 2File: FORM 2 Q4.pdf6 Jun 2026
Withdrawal Update Form 3File: FORM 3 Q4_11zon.pdf6 Jun 2026
Withdrawal Update Form 1File: Form 1 (1).pdf5 Jun 2026
Withdrawal Update Form 2File: FORM-2 Q-3.pdf5 Jun 2026
Withdrawal Update Form 3File: form 3 Q3_11zon.pdf5 Jun 2026
Layout approvalFile: plans 1 and 2.pdf2 Mar 2026
Building plan approvalFile: 3.pdf2 Mar 2026
Building plan approvalFile: Plans 4 and 5.pdf2 Mar 2026
Building plan approvalFile: layout.pdf2 Mar 2026
Withdrawal Update Form 1File: FORM-1 (1).pdf5 Dec 2025
Withdrawal Update Form 2File: FORM-2 (1).pdf5 Dec 2025
Withdrawal Update Form 3File: FORM 3 Q2 1_11zon.pdf5 Dec 2025
Withdrawal Update Form 1File: FORM 1 (5).pdf2 Dec 2025
Withdrawal Update Form 2File: FORM 2 (3).pdf2 Dec 2025
Withdrawal Update Form 3File: FORM 3 Q1_11zon.pdf2 Dec 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: TRIO FROM-5 2023-2024.pdf19 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)File: TRIO FROM-5 2024-2025.pdf19 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form- I.pdf30 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q3 (1).pdf30 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Q4 (2).pdf30 Apr 2025
Copy of Layout Approval (in case of layout)File: Plans_1-1.pdf25 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Plans_2-3.pdf25 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Plans_4-4.pdf25 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Plans_5-end.pdf25 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form 3.pdf3 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3.pdf26 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate 23 Q4.pdf28 Feb 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineer Certificate 23 Q4.pdf28 Feb 2024
Disclosure of sold/ booked inventoryFile: inventory disclosure.pdf28 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate 23 Q4.pdf28 Feb 2024
Commencement Certificates / NA Order for plotted developmentFile: RDP Order 31-03-2023 copy.pdf12 Oct 2023
Copy of the legal title reportFile: title report part 1.pdf30 Aug 2023
Copy of the legal title reportFile: Legal Title Report Sereno (1)_9-end (1).pdf30 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca certificate final.pdf23 Aug 2023
Layout approvalFile: layout plan highlighted.pdf17 Aug 2023
Building plan approvalFile: E wing Approved Plan_11-end_1-1.pdf17 Aug 2023
Building plan approvalFile: E wing Approved Plan_11-end_2-2.pdf17 Aug 2023
Building plan approvalFile: E wing Approved Plan_11-end_3-end highlighted.pdf17 Aug 2023
Building plan approvalFile: H wing Approved Plan_11-end_1-1.pdf17 Aug 2023
Building plan approvalFile: H wing Approved Plan_11-end_2-2.pdf17 Aug 2023
Building plan approvalFile: H wing Approved Plan_11-end_3-end highlighted.pdf17 Aug 2023
Copy of Layout Approval (in case of layout)File: layout plan highlighted.pdf17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: E wing Approved Plan_11-end_1-1.pdf17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: E wing Approved Plan_11-end_2-2.pdf17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: E wing Approved Plan_11-end_3-end highlighted.pdf17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: H wing Approved Plan_11-end_1-1.pdf17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: H wing Approved Plan_11-end_2-2.pdf17 Aug 2023
Building Plan Approval / NA Order for plotted developmentFile: H wing Approved Plan_11-end_3-end highlighted.pdf17 Aug 2023
Deviation Report with respect to Allotment letterFile: allotment deviation.pdf17 Aug 2023
Declaration about Commencement CertificateFile: CC declaration.pdf14 Aug 2023
Declaration in FORM BFile: FROM B PROMOTERScan.pdf14 Aug 2023
Proforma of Agreement for saleFile: Draft Agreement vijay tripathi.pdf14 Aug 2023
Proforma of Allotment letterFile: ALLOTMENT LETTER FINAL.pdf14 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank details letter.pdf14 Aug 2023
Deviation Report with respect to model copy of AgreementFile: deviation of agreement.pdf14 Aug 2023
Details of encumbrances concerned to FinanceFile: No encumbrance self declaration.pdf11 Aug 2023
Details of encumbrances concerned to LegalFile: No encumbrance self declaration.pdf11 Aug 2023
CERSAI detailsFile: CERSAI DECLARATION.pdf11 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: ANNAXURE A.pdf11 Aug 2023
Details of encumbrances concerned to FinanceFile: encumbrances concerned to Finance.pdf2 Aug 2023
Details of encumbrances concerned to FinanceFile: encumbrances concerned to Legal.pdf2 Aug 2023
Details of encumbrances concerned to LegalFile: encumbrances concerned to Finance.pdf2 Aug 2023
Details of encumbrances concerned to LegalFile: encumbrances concerned to Legal.pdf2 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FROM-1.pdf2 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf2 Aug 2023
PAN CardFile: TRIO-Pan Card.pdf1 Aug 2023

How this compares with Palghar

49%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 16 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SERENO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near VASAI3,200+ in Palghar

Builder: TRIO INFRASTRUCTURE PRIVATE LIMITED

TRIO INFRASTRUCTURE PRIVATE LIMITED has 1 registration on MahaRERA, including SERENO. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if SERENO is delayed beyond 30 Apr 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SERENO?

The registered promoter entity is TRIO INFRASTRUCTURE PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SERENO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SERENO?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SERENO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SERENO?

The professionals named in the filing: Architect: SANAT MEHTA & ASSOCIATES; Engineer: MUKESH KUMAR; Engineer: Omkesh Umesh Chaurasia; Chartered Accountant: S C SHAH & COMPANY; Chartered Accountant: A SACHDEV & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SERENO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SERENO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SERENO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.