Home / Browse projects / Mumbai Suburban, Maharashtra / SATRA HARMONY

Completed No litigation declared Residential / Group Housing project

SATRA HARMONY

By RRB REALTORS PVT LTD.

RG-MH-07935 · RERA P51800000726 · Last updated on MahaRERA portal: 27 Dec 2023

Source: official MahaRERA filing

Red flags

  • 7 complaints at MahaRERA
  • Completion date moved by 47 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Nov 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
7Complaints at MahaRERAon this registration
Jump to the 127 documents Report an error

SATRA HARMONY is a Residential / Group Housing project by RRB REALTORS PVT LTD. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000726 on 23 Jul 2017. The registration is recorded completed; possession was promised by 6 Nov 2023. The completion date has moved by 47 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameSATRA HARMONY
  • TypeResidential / Group Housing
  • Location
    • Irla society road
    • Vile parle (west)
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000726
  • ReraGenie IDRG-MH-07935

Builder

  • NameRRB REALTORS PVT LTD.
  • Entity typeCompany
  • DirectorAnuj Ajay Bansal

Key dates

this monthRegisteredJul 2017First promiseDec 2019Revised toNov 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on23 Jul 2017
  • Promised completion6 Nov 2023
  • Revised completionRevised to 6 Nov 2023 (originally 31 Dec 2019)
  • Buildings1 building record
  • Documents filed127 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SATRA HARMONYNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 27 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

SATRA HARMONY: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 27 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes99%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes99%
Water conservation /Rain water harvestingYes99%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes99%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes100%
FITNESS CENTREYes0%

Parking filed91

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots91
Closed/Covered75
Open Space16

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,557 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
SUBHASH NAGAR RAJESHWARI CHS LTDKurlaMumbai Suburban

Approvals and building plan

Permissible FSI7352.83
Proposed, not sanctioned4,264 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUNIT NO 501 5TH FLOOR TOWER B PENINSULA BUSINESS PARK LOWER PAREL MUMBAI 400013

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSMT DHRUTI A BHAGALIA
EngineerMR C B PATEL
Chartered AccountantKAMAL DHANUKA & CO
Chartered AccountantJAIN ANIL AND ASSOCIATES
PartnerRole in project
RRB REALTORS PVT LTD.-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800003716Dec 2019 → Dec 2020

Reason as filed by the promoterC.C is re endorsed up to top of 7th floor for wing A and up to top of 5th floor for wing B by the approval authorities , further C.C to be obtained to complete 15th floor in both the wing hence extension is required to complete the project till 30th Dec 2020.

EXT51800009534Dec 2019 → Dec 2022

Reason as filed by the promoterThe projects needs extension dues to various reasons which affected the project completion timelines such as change in MHADA policies from that of area sharing to being allowed on payment of premium for utilization of FSI followed by change in premium policy of the State Government and delay in implementation of the said policies by the authorities, etc. Further, not only managing with these reforms was first-hand for the developer but lately the challenging time of the widespread pandemic of Covid-19 led to standstill operations not only at site but also office/s and migration of labourers as

EXT51800017032Dec 2019 → Nov 2023

Reason as filed by the promoteroc has been received and accordingly we want to extend the project and get it completed under Maharera

Litigation declared1

CaseCourtStatus
2434/2023HIGH COURTclosed

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000196050SUNIL ANANDERISHBH PRAFUL SATRA26/03/2021
CC006000000196522M/s. Nagindas Kasturchand and Bros through its partner Jignesh Dinkerbhai ShahRRB Realtors Pvt. Ltd. and Praful Nanji Satra23/04/2021
CC006000000196860Vikrant Shewale and Deepa ShewaleRRB REALTORS PVT LTD03/05/2021
CC006000000198751RRB REALTORS PRIVATE LIMITEDASHISH S BHSARI AND BHARATI A BHUSARI20/10/2021
CC006000000429307GIRISH RAGHUNATH PATILRRB Realtors Private Limited17/02/2024
CC12400134Shreyans ShahRRB REALTORS PVT LTD.17/09/2024
CC12400140Shrayans Jashwantlal ShahRRB REALTORS PVT LTD.18/09/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jun 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Jun 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 19 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Nov 2023

Documents filed127

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: form 4 satra harmony.pdf27 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SEPT 23.pdf24 Nov 2023
Certificates of CA (Form 3)File: form 3 sept 23.pdf23 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 dated 21 SEPTEMBER 2023.pdf20 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 june 23.pdf8 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: form 2a sept 23.pdf8 Nov 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: full oc.pdf8 Nov 2023
Certificates of CA (Form 3)File: form 3 juen 23.pdf6 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 sept 23.pdf21 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 march 23.pdf17 Oct 2023
Certificates of CA (Form 3)File: Form 3 march 23.pdf10 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A FOR MARCH 23.pdf27 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A FOR JUNE 23.pdf27 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: 180205 TO 190204_PLINTH CC.pdf19 Jul 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 230620_OC_ISSUED LETTER ONLY_WING -A.pdf19 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 for march 23.pdf17 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 for june 23.pdf17 Jul 2023
Foreclosure of the ProjectFile: Satra Harmony Wing A - OC.pdf25 Jun 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1_dec 22.pdf1 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_dec 22.pdf1 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A)File: form 2a_dec 22.pdf1 Apr 2023
Certificates of CA (Form 3)File: form 3_dec 22.pdf24 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RRB REALTORS PVT LTD - Sign Certificate.pdf8 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_ SEPT 22.pdf4 Mar 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_spet 22.pdf4 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A)File: form 2a_sept 22.pdf4 Mar 2023
Certificates of CA (Form 3)File: rrb form 3_sept 22.pdf29 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2_june 22.pdf30 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A)File: form 2a_june 22.pdf30 Sep 2022
Certificates of CA (Form 3)File: form 3 _june 22.pdf30 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1_JUNE 22.pdf21 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form I of RERA.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate RRB Realtors.pdf5 Jul 2022
Commencement Certificates / NA Order for plotted developmentFile: 220511_Updated CC_.pdf24 May 2022
Certificates of CA (Form 3)File: RERA FORM 3 DEC 2021.pdf31 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RRB FORM 2 SEPT 21.pdf22 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: satra harmony form 1 Dec 2021.pdf16 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: satra harmony FORM 1 sept21.pdf9 Feb 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 OF MARCH 2021 SATRA HARMONY.pdf31 Jan 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A RRB June 2021 Quality Assurance Certificate_SEP.pdf24 Dec 2021
Disclosure of sold/ booked inventoryFile: disclosure of sold inventory.pdf24 Dec 2021
Certificates of CA (Form 3)File: FORM 3 SEPT 21 SATRA HARMONY.pdf17 Dec 2021
Certificates of CA (Form 3)File: RRB FORM 3 JUNE 21.pdf19 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate RRB Realtors 30 JUNE 21_SEP.pdf18 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A RRB June 2021 Quality Assurance Certificate_SEP.pdf18 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 RRB JUNE 21.pdf9 Sep 2021
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A RRB june 2021 Quality Assurance Certificate_R1.pdf9 Sep 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRB FORM 1 MARCH 21.pdf20 Aug 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRB FORM 1 JUNE 21.pdf20 Aug 2021
Certificates of CA (Form 3)File: SATRA HARMONY FORM 3 MARCH 21.pdf20 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SEPT 20.pdf1 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 DEC 20.pdf1 Jul 2021
Disclosure of sold/ booked inventoryFile: HARMONY_APARTMENT DETAILS.pdf12 Jun 2021
Certificates of CA (Form 5)File: RRB FORM 5 MARCH 20.pdf12 Apr 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RRB FORM 5 MARCH 20.pdf12 Apr 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 RRB DEC 20.pdf10 Mar 2021
Engineers Certificate on Quality Assurance (Form 2A)File: form 2 A RRB DEC 20.pdf10 Mar 2021
Certificates of CA (Form 3)File: RRB HARMONY FORM 3 DEC20.pdf3 Mar 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 sept 20 RRB.pdf30 Jan 2021
Engineers Certificate on Quality Assurance (Form 2A)File: FORM 2A RRB sept 20.pdf30 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRB FORM 1 JUNE 20.pdf9 Jan 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RRB FORM 1 MARCH 20.pdf9 Jan 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate RRB Realtors 31 MARCH 20.pdf22 Dec 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate RRB Realtors 30 JUNE 20.pdf22 Dec 2020
Certificates of CA (Form 3)File: RRB FORM 3 SEPT 2020.pdf22 Dec 2020
Certificates of CA (Form 3)File: RRB FORM 3 MARCH 20.pdf7 Sep 2020
Certificates of CA (Form 3)File: RRB FORM 3 JUNE 20.pdf7 Sep 2020
Engineers Certificate on Quality Assurance (Form 2A)File: RRB FORM 2 A MARCH 20.pdf19 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 RRB sept 2019.pdf10 Aug 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RRB FORM 2 DEC 19.pdf10 Aug 2020
Engineers Certificate on Quality Assurance (Form 2A)File: RRB FORM 2A DEC 19.pdf10 Aug 2020
Certificates of CA (Form 3)File: RRB form 3 dec 19.pdf10 Aug 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA form 1 Dec 2019.pdf13 Jul 2020
Certificates of CA (Form 3)File: RRB form 3 dec 19.pdf5 Jun 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: satra harmony Sept 19 form 1.pdf14 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 RRB sept 2019.pdf24 Dec 2019
Engineers Certificate on Quality Assurance (Form 2A)File: form 2 A rrb sept 2019.pdf24 Dec 2019
Certificates of CA (Form 3)File: FORM 3 RRB SEPT 19.pdf21 Dec 2019

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 47 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SATRA HARMONY on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Vile parle (west)6,700+ in Mumbai Suburban

2 kmSATRA HARMONYCompleted 138Lapsed / revoked 111Other 134Dot size: filed unitsN

Filed coordinates, straight-line distance. 383 registered projects within 2 km.

Builder: RRB REALTORS PVT LTD.

RRB REALTORS PVT LTD. has 1 registration on MahaRERA, including SATRA HARMONY. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SATRA HARMONY is delayed beyond 6 Nov 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SATRA HARMONY?

The registered promoter entity is RRB REALTORS PVT LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SATRA HARMONY?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SATRA HARMONY?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SATRA HARMONY?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SATRA HARMONY?

The professionals named in the filing: Architect: SMT DHRUTI A BHAGALIA; Engineer: MR C B PATEL; Chartered Accountant: KAMAL DHANUKA & CO; Chartered Accountant: JAIN ANIL AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SATRA HARMONY?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SATRA HARMONY. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SATRA HARMONY to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.