ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SAMRUDDHI ISHA

Completed No litigation declared Residential / Group Housing project

SAMRUDDHI ISHA

By SAMRUDDHI ENTERPRISES

RG-MH-10825 · RERA P52100006794 · Last updated on MahaRERA portal: 28 Feb 2024

Source: official MahaRERA filing

Red flags

  • 7 complaints at MahaRERA
  • Completion date moved by 60 months
  • 5 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
4 of 11Construction stages donefurthest along: Internal walls, 90%
7Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

SAMRUDDHI ISHA is a Residential / Group Housing project by SAMRUDDHI ENTERPRISES in Pune, Maharashtra, registered with MahaRERA as P52100006794 on 16 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2023. The completion date has moved by 60 months from the original filing. 7 complaints are on record with the regulator.

At a glance

Project

  • NameSAMRUDDHI ISHA
  • TypeResidential / Group Housing
  • Location
    • KIVALE
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100006794
  • ReraGenie IDRG-MH-10825

Builder

  • NameSAMRUDDHI ENTERPRISES
  • Entity typePartnership
  • PartnerSunil Sudam Bhumkar
  • Other registrations3 more →
  • Completed1 of 4
  • No longer live2 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on16 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Dec 2018)
  • Buildings1 building record
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAMRUDDHI ISHANA90000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 28 Feb 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.

SAMRUDDHI ISHA: 71% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor85%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.60%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities19

As on 28 Feb 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes25%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable
POWER BACKUPYes0%
VIDEO DOOR PHONEYes0%
NANoNot applicable
SOLAR WATER HEATING SYSTEMYes0%

Parking filed50

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots50
Closed/Covered50

Land and ownership3

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,162 sq m
Land owned byThe promoter, with other names on the file
Named landowners3
LandownerVillageDistrict
SAMRUDDHI PROPERTIESKivalePune
MRS NP YADAV MRS ND DALVI THROUGH POAH MR NB BACHEPimpri Chinchawad (M Corp.)Pune
SAMRUDDHI PROPERTEISKivalePune

Approvals and building plan

Permissible FSI2911.89
Proposed, not sanctioned2,912 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSECTOR 26 PRADHIKARAN NIGADI PUNE 411044

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMR SANDEEP DANGE
EngineerCICOM CONSULTANTS Through MR SUBHASH TAYAL
PartnerRole in project
SAMRUDDHI ENTERPRISES-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100003699Dec 2018 → Jun 2020

Reason as filed by the promoter1] Since there is slack in the market from the customers point of view they are not getting there salaries and so the customers are not capable of completing our payments as per the demand letter and so we are facing financial problems due to insufficient funds from the customers. 2] Due to lack of bookings of the flats which is because of slack in the market.

EXT52100005897Dec 2018 → Jun 2020

Reason as filed by the promoterThe reason behind delay of the project is slack in the market. The Customers are having issue of their salary which they are not getting for last 3 to 6 months. The other reason is that the loan of new customers who have booked recently is not getting approved due to their new procedure and also banks are seeking for revised RERA deadline completion certificate., Also revised completion certificate from architect.

EXT52100012674Dec 2018 → Mar 2023

Reason as filed by the promoterrequire extension for last 5-10% stage of work pending, to complete process of OC/completion, also payment disbursement collection from allottees is pending.

EXT52100010601Dec 2018 → Feb 2022

Reason as filed by the promoterDue to COVIS 19 pandemic spread, most labours went back to their hometown and there was a massive shortage of labour, unavailability of materials and other pandemic related hardships, which has a caused the delay and the building could not be completed within the committed date of completion i.e. 30/12/2020 as provided by us in affidavit Form -B for registration. Therefore, we humbly request to allow the further extension for completion of this project till 25.02.2022

EXT52100015290Dec 2018 → Dec 2023

Reason as filed by the promoterIn accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have 16 consents that is 57.14% of the sold units for the Extension of the Project.

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC005000000064739ANIL BABURAO AGALESAMRUDDHI ENTERPRISES12/10/2020
CC005000000064743JAYENDRA AMRUTRAO CHAUDHARISamruddhi Enterprises17/10/2020
CC005000000064755SHRINIVAS NARAYANRAO KADAMSAMRUDDHI ENTERPRISES20/10/2020
CC005000000064779SANGITA R NIKALJESamruddhi Enterprises28/10/2020
CC005000000064820Prashant Prakash GawadeSamruddhi Enterprises10/11/2020
CC005000000064824Vaibhav Kumar KhodkeSamruddhi Enterprises11/11/2020
CC005000000085610Pradnya Rajendra KandekarSudhir Wadekar02/06/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 28 Feb 2024

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan Feb 26, 2024 (3).pdf28 Feb 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Adobe Scan Feb 26, 2024 (3).pdf28 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Isha-Form2A.pdf27 Apr 2023
Disclosure of sold/ booked inventoryFile: Isha-Sold Inventory.pdf27 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Samruddhi Isha - Form 5 (21-22).pdf8 Feb 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declrn for Bank Account.pdf7 Oct 2022
Declaration about Commencement CertificateFile: Circular 32.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 2019.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2A 2021.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 2019.pdf30 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 2020.pdf30 Jul 2021
Disclosure of sold/ booked inventoryFile: Curcular 29.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf30 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf30 Jul 2021
OtherFile: Partnership Deed_compressed.pdf15 Jan 2021
Architect’s Certificate on Completion of Project (Form 4)File: Enterprises.pdf22 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form5 2017-18.pdf8 Dec 2019
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form5 2018-19.pdf8 Dec 2019
Layout approvalFile: Layout Declaration.pdf29 Jul 2017
Copy of the legal title reportFile: Enterprises Advocate-ilovepdf-compressed (1).pdf29 Jul 2017
Details of encumbrancesFile: Encumbrance Declaration.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Declaration.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC ENTERPRISES.pdf29 Jul 2017
Declaration in FORM BFile: Enterprises Form B.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch .pdf29 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Certificate.pdf29 Jul 2017
Certificates of CA (Form 3)File: Enterprises CA Certificate-ilovepdf-compressed.pdf29 Jul 2017
Proforma of Allotment letterFile: ALLOTMENT FOR SAMRUDDHI ISHACopy.pdf29 Jul 2017
Proforma of Allotment letterFile: AGREEMENT TO SALE.pdf29 Jul 2017
Building plan approvalFile: PLAN A.pdf28 Jul 2017
Building plan approvalFile: PLAN B.pdf28 Jul 2017
Building plan approvalFile: PLAN C.pdf28 Jul 2017
PAN CardFile: PAN ENTERPRISES.pdf28 Jul 2017
Building Plan Approval (IOD)File: PLAN A.pdf28 Jul 2017
Building Plan Approval (IOD)File: PLAN B.pdf28 Jul 2017
Building Plan Approval (IOD)File: PLAN C.pdf28 Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 60 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAMRUDDHI ISHA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KIVALE13,700+ in Pune

2 kmSAMRUDDHI ISHACompleted 1Lapsed / revoked 3Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 5 registered projects within 2 km.

Builder: SAMRUDDHI ENTERPRISES

SAMRUDDHI ENTERPRISES has 4 registrations on MahaRERA, including SAMRUDDHI ISHA and SAMRUDDHI ENCLAVE. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SAMRUDDHI ISHA is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAMRUDDHI ISHA?

The registered promoter entity is SAMRUDDHI ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAMRUDDHI ISHA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAMRUDDHI ISHA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAMRUDDHI ISHA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAMRUDDHI ISHA?

The professionals named in the filing: Architect: MR SANDEEP DANGE; Engineer: CICOM CONSULTANTS Through MR SUBHASH TAYAL. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAMRUDDHI ISHA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAMRUDDHI ISHA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAMRUDDHI ISHA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.