Home / Browse projects / Pune, Maharashtra / SAMARTH COUNTY
SAMARTH COUNTY
RG-MH-21449 · RERA P52100029698 · Last updated on MahaRERA portal: 18 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 10 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAMARTH COUNTY is a Others project by D A BORADE AND SONS in Pune, Maharashtra, registered with MahaRERA as P52100029698 on 26 Jun 2021. Possession is promised by 31 Oct 2026. The completion date has moved by 10 months from the original filing. 117 of the 176 units on this registration are recorded sold or booked, and 27 of 33 construction stages are filed complete.
At a glance
Project
- NameSAMARTH COUNTY
- TypeOthers
- Location
- Sr No 61/1
- 61/2/1
- Ravet
- Haveli
- Pune
- 412101
- Pincode412101
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100029698
- ReraGenie IDRG-MH-21449
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on26 Jun 2021
- Promised completion31 Oct 2026
- Revised completionRevised to 31 Oct 2026 (originally 31 Dec 2025)
- Buildings3 building records
- Documents filed119 files
Current status
Figures as on 18 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A WING | NA | 25 | 22 | 83 | 0 | 83 |
| B WING | NA | 25 | 22 | 83 | 0 | 83 |
| C WING | NA | 4 | 4 | 0 | 10 | 10 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
27 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 25%.
A WING84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
B WING84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
C WING84%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 25% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 100% |
Parking filed420
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A WING | 181 | 0 | 181 |
| B WING | 182 | 0 | 182 |
| C WING | 1 | 56 | 57 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A WING | NA | Rs 31.23 cr | Rs 31.23 cr |
| B WING | NA | Rs 31.23 cr | Rs 31.23 cr |
| C WING | NA | Rs 31.23 cr | Rs 31.23 cr |
| - | NA | Rs 4.00 cr | Rs 3.92 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AJINKYA BORADE ARCHITECTS |
| Engineer | RITESH S CHAVAN |
| Engineer | GANESH B PATIL |
| Chartered Accountant | INDAPURKAR & MUNDADA CHARTERED ACCOUNTANTS |
| Partner | Role in project |
|---|---|
| D A BORADE AND SONS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterRespected Sir/Madam, We, the promoters of Samarth County (Reg. No. P52100029698), humbly request an extension of the project registration, currently valid till 31/12/2025, up to 30/06/2026, to complete the remaining work and obtain the Occupancy Certificate. I. Grounds for Seeking Extension Extended Monsoon Affecting External Plastering The unusually prolonged monsoon in Maharashtra during 2025, with intermittent rains continuing into October-November, delayed external plastering and waterproofing. Internal finishing works could not commence without sealing the building envelope, causing an un
Reason as filed by the promoterRespected Sir/Madam, We, the promoters of SAMARTH COUNTY, registered with the Authority under Registration No. P52100029698, humbly submit this application seeking extension of project registration up to 31/10/2026 for completion of the balance construction work and procurement of the Occupancy Certificate. The present completion date is 30/06/2026. Considering unavoidable circumstances affecting construction activities, we request an extension of four months. The registered Agreement for Sale executed with the allottees also provides that in the event of reasonable circumstances beyond the co
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 Oct 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Nov 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 10 Aug 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 10 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Oct 2026
Documents filed119
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 119 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: Form 2A 25-26.pdf | 18 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 Q1 26-27 SAMARTH COUNTY.pdf | 17 Jul 2026 |
| Withdrawal Update Form 2File: FORM 2 -9-07-26 SAMARTH COUNTY (2).pdf | 17 Jul 2026 |
| Withdrawal Update Form 3File: Samarth County Form 3 _ Q1 _ 2026.pdf | 17 Jul 2026 |
| Form 2A (FY 2024-2025)File: form 2A.pdf | 9 Jun 2026 |
| Form 5 (FY 2024-2025)File: form.pdf | 9 Jun 2026 |
| Withdrawal Update Form 1File: Q4 SC FORM 1 10-4-2026 (1).pdf | 21 Apr 2026 |
| Withdrawal Update Form 2File: SC Form 2 10-4-2026 (2).pdf | 21 Apr 2026 |
| Withdrawal Update Form 3File: SAMARTH COUNTY FORM 3 25-26 Q4 (1)_compressed.pdf | 21 Apr 2026 |
| Withdrawal Update Form 1File: SC Form-1 Q3 2026-27.pdf | 29 Jan 2026 |
| Withdrawal Update Form 2File: Form2 SC Q2 2025-26 (final).pdf | 29 Jan 2026 |
| Withdrawal Update Form 3File: Samarth County _Form 3 Q3 2026_Final.pdf | 29 Jan 2026 |
| Layout approvalFile: Samarth County CC and Sanction Plan.pdf | 12 Nov 2025 |
| Layout approvalFile: Sanction Plan.pdf | 12 Nov 2025 |
| Withdrawal Update Form 1File: Form 1 SC Q2 2025 (Final).pdf | 17 Oct 2025 |
| Withdrawal Update Form 1 | 17 Oct 2025 |
| Withdrawal Update Form 2File: Form2 SC Q2 2025-26 (final).pdf | 17 Oct 2025 |
| Withdrawal Update Form 2 | 17 Oct 2025 |
| Withdrawal Update Form 3File: form 3 samarth county 16-10-25 (1).pdf | 17 Oct 2025 |
| Withdrawal Update Form 3 | 17 Oct 2025 |
| Withdrawal Update Form 1File: Form 1 SC 4-7-25.pdf | 22 Sep 2025 |
| Withdrawal Update Form 2File: Form 2 SC 6-7-25.pdf | 22 Sep 2025 |
| Withdrawal Update Form 3File: form 3 samarth county.pdf | 22 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SAMARTH COUNTY FORM 1 Q4 2025.pdf | 20 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: samarth county q42025_compressed.pdf | 20 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SC Q4 FORM 2 2025.pdf | 20 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form-2 Engg certificate SC.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 20 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SC Architects certificate_compressed.pdf | 19 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: SC FORM 3.pdf | 19 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SC Engineer's certifacte_compressed.pdf | 19 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure Samarth County 19-10_compressed.pdf | 19 Oct 2024 |
| Building plan approvalFile: SACTION DWG SC 5-08-2024_compressed (1).pdf | 10 Aug 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: SACTION DWG SC 5-08-2024_compressed (1).pdf | 10 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: COMMENCMENT SC 5-8-24.pdf | 10 Aug 2024 |
| Declaration about Commencement CertificateFile: DECLARATION ABOUT CC 10-8-2024.pdf | 10 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SAMARTH COUNTY 10-8-2024_compressed (2).pdf | 10 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA FORM 3 SAMARTH COUNTY 10-8-24_compressed (1).pdf | 10 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 architect samarth County 7-7-2024.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SAMARTH COUNTY (2)_compressed (1).pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold sc 7-5-14.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA CERTIFICATE SAMARTH COUNTY 12-7-2024_compressed.pdf | 20 Jul 2024 |
| Details of encumbrancesFile: ENCOMBRANCES 5 CR 11CR.pdf | 12 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 SAMARTH COUNTY -5-04-2024.pdf | 2 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 SAMARTH COUNTY -4-04-2024.pdf | 2 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A SAMARTH COUNTY -4-04-2024.pdf | 2 May 2024 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTRY.pdf | 2 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 SAMARTH COUNTY -5-04-2024.pdf | 2 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf | 2 Mar 2024 |
| Building plan approvalFile: RAVET REVI 20-02-2024_compressed.pdf | 22 Feb 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: RAVET REVI 20-02-2024_compressed.pdf | 22 Feb 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC RAVET 21-02-2024_compressed.pdf | 22 Feb 2024 |
| Declaration about Commencement CertificateFile: declaration about cc 22-02-2024.pdf | 22 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engg Certificate form 2 samarth county 20-02-2024.pdf | 22 Feb 2024 |
| Disclosure of sold/ booked inventoryFile: sold unsold 21-2-2024.pdf | 22 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 21 Feb 2024_compressed.pdf | 22 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_compressed.pdf | 23 Nov 2023 |
| Copy of the legal title reportFile: search report samarth county 11-10-2023.pdf | 19 Oct 2023 |
| Details of encumbrancesFile: Encumbrances.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: quality assurance 21-22.pdf | 19 Oct 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Compressed_quality assurance 22-23.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: SOLD UNSOLD.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: ca form 5 21-22.pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 17 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 17 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engg Cert.pdf | 17 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold .pdf | 17 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: A Wing Sold.pdf | 17 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: B Wing Sold.pdf | 17 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3.pdf | 17 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Form 3_compressed (1).pdf | 17 Oct 2023 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: format A rera samarth County .pdf | 17 Oct 2023 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate - Samarth County.pdf | 2 Jun 2023 |
| Building plan approvalFile: Plan no-7.pdf | 24 May 2023 |
| Building plan approvalFile: Plan no-1.pdf | 24 May 2023 |
| Building plan approvalFile: Plan no-2.pdf | 24 May 2023 |
| Building plan approvalFile: Plan no-3.pdf | 24 May 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| SAMRUDDHI ORCHIDP51500022942 | SHENDRA JAHANGIR, Aurangabad | 90 | Nov 2019 | Completed | Aug 2025 | Nov 2023 |
| SAMARTH VILLAP52100050168 | VISHAL NAGAR, Pune | 10 | Mar 2023 | Completed | Mar 2024 | Late, Apr 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 119 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAMARTH COUNTY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Ravet13,700+ in Pune
Filed coordinates, straight-line distance. 234 registered projects within 2 km.
Godrej Park Greens
Godrej Skyline Developers Limited
FOREST GROVE AT GODREJ PARK GREENS
Godrej Skyline Developers Limited
Om Mangalam Samruddhi
NDG Homes LLP
PCMC EWS KIWALE
Pimpri Chinchwad Municipal Corporation
Godrej Nurture
Godrej Skyline Developers Limited
My Home Sanctuary Phase I
MAMURDI DEVELOPERS LLP
Builder: D A BORADE AND SONS
D.A.BORADE AND SONS has 2 registrations on MahaRERA, including Shraddha Orchid and SAMARTH COUNTY. Its filings disclose 3 earlier MahaRERA projects: declares 2 of 3 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SAMARTH COUNTY is delayed beyond 31 Oct 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAMARTH COUNTY?
The registered promoter entity is D A BORADE AND SONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAMARTH COUNTY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAMARTH COUNTY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAMARTH COUNTY?
The professionals named in the filing: Architect: AJINKYA BORADE ARCHITECTS; Engineer: RITESH S CHAVAN; Engineer: GANESH B PATIL; Chartered Accountant: INDAPURKAR & MUNDADA CHARTERED ACCOUNTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAMARTH COUNTY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback