SAKINA RESIDENCY
RG-MH-69213 · RERA P99000032598 · Last updated on MahaRERA portal: 20 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAKINA RESIDENCY is a Residential / Group Housing project by vision developers in Palghar, Maharashtra, registered with MahaRERA as P99000032598 on 14 Jan 2022. Possession is promised by 30 Jun 2027. The completion date has moved by 18 months from the original filing. 16 of the 59 units on this registration are recorded sold or booked, and 14 of 27 construction stages are filed complete.
At a glance
Project
- NameSAKINA RESIDENCY
- TypeResidential / Group Housing
- Location
- MAHIM ROAD
- NEAR SUNDARAM SCHOOL
- Mahim
- Palghar
- 401404
- Pincode401404
- MapView location on Google Maps (as filed on RERA)
- RERA no.P99000032598
- ReraGenie IDRG-MH-69213
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on14 Jan 2022
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 25 Dec 2025)
- Buildings3 building records
- Documents filed106 files
Current status
Figures as on 20 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A Wing | NA | 5 | 5 | 15 | 6 | 21 |
| B Wing | NA | 4 | 4 | 12 | 9 | 21 |
| C Wing | NA | 4 | 4 | 12 | 5 | 17 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building3
As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
14 of 27 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 80%.
A Wing33%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 55% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 30% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 10% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
B Wing68%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 70% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 65% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
C Wing89%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 40% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 30% |
| Storm Water Drains | No | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | 100% |
| Water conservation /Rain water harvesting | No | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 30% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | 0% |
Parking filed105
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| A Wing | 0 | 37 | 37 |
| B Wing | 2 | 31 | 33 |
| C Wing | 4 | 31 | 35 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| A Wing | NA | Rs 5.80 cr | Rs 3.49 cr |
| B Wing | NA | Rs 5.80 cr | Rs 3.49 cr |
| C Wing | NA | Rs 5.80 cr | Rs 3.49 cr |
Certifying professionals and partners9
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | SARJAN ARC |
| Architect | Sarjanarc Associates |
| Engineer | SARJAN ARC |
| Engineer | Kavita Balsara |
| Chartered Accountant | JAIN ANIL AND ASSOCIATES |
| Chartered Accountant | ASADULLAH A SELIYA |
| Chartered Accountant | RAHUL M. AGARWAL & CO. |
| Chartered Accountant | Kazi And Associates |
| Chartered Accountant | PUKHRAJ SINGH RAJ PUROHIT |
| Partner | Role in project |
|---|---|
| Vision Developers | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promotera)As the entire country including Palghar District were under a total lock-down; and the Government of India as well as the Government of Maharashtra had announced a slew of measures including “work from home” and “social distancing” to curb the spread of the COVID-19. b)Inspite of best efforts, the said project was adversely affected due to unprecedented COVID-19 Pandemic which lasted for more than 2 years and are still facing aftermath of COVID-19 Pandemic. Though there is progress in construction of project, the project has got delayed due to COVID-19 Pandemic, the losses/cost overrun and t
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Dec 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 8 Jan 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 27 Feb 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 3 Jan 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 30 Jun 2027
Documents filed106
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 Architect June 2026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 Architect June 2026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer June 2026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 Engineer June 2026.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA June 2026 _compressed.pdf | 20 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 CA June 2026 _compressed.pdf | 20 Jul 2026 |
| Withdrawal Update Form 1File: FOrm 1 Architect March 2026.pdf | 27 Apr 2026 |
| Withdrawal Update Form 2File: FORM 2 Engineer March 2026.pdf | 27 Apr 2026 |
| Withdrawal Update Form 3File: Form 3 Jan-March 2026 Final Signed_compressed.pdf | 27 Apr 2026 |
| Building plan approvalFile: BP-1.pdf | 27 Feb 2026 |
| Building plan approvalFile: BP 2 .pdf | 26 Feb 2026 |
| Building plan approvalFile: BP 3 .pdf | 26 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT DEC 2025.pdf | 23 Jan 2026 |
| Withdrawal Update Form 2File: FORM 2 ENGINEER DEC 2025.pdf | 23 Jan 2026 |
| Withdrawal Update Form 3File: CA Form 3 December 2025 Signed_compressed.pdf | 23 Jan 2026 |
| Form 5 (FY 2021-2022)File: RERA Audit.pdf | 26 Dec 2025 |
| Withdrawal Update Form 1File: Architect Certificate.pdf | 26 Nov 2025 |
| Withdrawal Update Form 2File: Engineer Certificate.pdf | 26 Nov 2025 |
| Withdrawal Update Form 3File: Form 3 Vision Developers.pdf | 26 Nov 2025 |
| Form 2A (FY 2024-2025)File: form 2A - March 2025.pdf | 26 Nov 2025 |
| Form 2A (FY 2021-2022)File: form 2A - March 2022.pdf | 26 Nov 2025 |
| Form 2A (FY 2022-2023)File: form 2A - March 2023.pdf | 26 Nov 2025 |
| Form 2A (FY 2023-2024)File: form 2A - March 2024.pdf | 26 Nov 2025 |
| Form 5 (FY 2024-2025)File: Form 5 CA certificate March 2025_251126_134414.pdf | 26 Nov 2025 |
| Form 5 (FY 2023-2024)File: CA Certificate 2 form 5 2024.pdf | 14 Nov 2025 |
| Form 1File: AR - Mar 23.pdf | 11 Nov 2025 |
| Form 2File: ER - Mar 23.pdf | 11 Nov 2025 |
| Form 3File: CA - Mar 23.pdf | 11 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Dis - 28-02-23.pdf | 11 Nov 2025 |
| Form 5 (FY 2022-2023)File: Form 5 - 22-23.pdf | 11 Nov 2025 |
| Form 1File: Architect Form 1 3162025.pdf | 26 Sep 2025 |
| Form 2File: Engineer Form 2 3162025.pdf | 26 Sep 2025 |
| Form 3File: CA Form 3 .pdf | 26 Sep 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold 30062025.pdf | 26 Sep 2025 |
| Form 1File: Form 1 Architect april - june 2024.pdf | 12 Jun 2025 |
| Form 2File: Form 2 Engineer april - june 2024.pdf | 12 Jun 2025 |
| Form 3File: Form 3 CA april - june 2024.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 12 Jun 2025 |
| Form 1File: Form 1 Architect july - sept 2024.pdf | 12 Jun 2025 |
| Form 2File: Form 2 Engineer july - sept 2024.pdf | 12 Jun 2025 |
| Form 3File: Form 3 CA july - sept 2024.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 12 Jun 2025 |
| Form 1File: Form 1 Architect oct - dec 2024.pdf | 12 Jun 2025 |
| Form 2File: Form 2 Engineer oct - dec 2024.pdf | 12 Jun 2025 |
| Form 3File: Form 3 oct - dec 2024.pdf | 12 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: sold unsold.pdf | 12 Jun 2025 |
| Form 2File: CA certificate form 3 march 25.pdf | 11 Jun 2025 |
| Form 3File: sold unsold.pdf | 11 Jun 2025 |
| Disclosure of Sold and Booked InventoryFile: Form 5 CA certificate March 2025.pdf | 11 Jun 2025 |
| Others | 11 Jun 2025 |
| Form 1File: form 2 ENGINEER CERTIFICATE march 25.pdf | 1 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE JUNE 2024.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 1 2024.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Certificate 2 form 5 2024.pdf | 9 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf | 9 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 1 2024.pdf | 9 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE JUNE 2024.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: CA Certificate 2 form 5 2024.pdf | 9 Oct 2024 |
| Building plan approvalFile: Bldg Plan 1.pdf | 20 Jan 2024 |
| Building plan approvalFile: Bldg Plan 2.pdf | 20 Jan 2024 |
| Building plan approvalFile: Bldg Plan 3.pdf | 20 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Bldg Plan 1.pdf | 20 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Bldg Plan 2.pdf | 20 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Bldg Plan 3.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Vision Developers.pdf | 20 Jan 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Vision Developers.pdf | 20 Jan 2024 |
| Building plan approvalFile: BP 1.pdf | 3 Jan 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: BP 1.pdf | 3 Jan 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: New CC 2023.pdf | 3 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf | 3 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf | 3 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Quality Assurance Certificate.pdf | 3 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1.pdf | 3 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Form 2.pdf | 3 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: sold unsold.pdf | 3 Aug 2023 |
| PAN CardFile: VISION PAN.pdf | 16 Mar 2023 |
| Details of encumbrances concerned to FinanceFile: NO LEGAL ENCUMBRANCE.pdf | 16 Mar 2023 |
| Details of encumbrances concerned to LegalFile: NO LEGAL ENCUMBRANCE.pdf | 16 Mar 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 26112022.pdf | 16 Mar 2023 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| CAMPZ LANDMARK | AMBOLI JOGESHWARI MUMBAI | 1 | Completed | Apr 2007 | Late, Jun 2014 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Palghar
Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.
Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 12 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 106 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAKINA RESIDENCY on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR SUNDARAM SCHOOL3,200+ in Palghar
Filed coordinates, straight-line distance. 188 registered projects within 2 km.
Veena Samrajya-Sector-VIII
Veena Developers
Prithvi Anand Kuber Complex Phase 2
Prithvi Anand Housing and Land Developers
INFINIA PHASE 1
URBAN LAND SOLUTIONS
AV SMART CITY PHASE 1
ADITYA REALTORS
PRITHVI ANAND KUBER COMPLEX
Prithvi Anand Housing and Land Developers
OSTWAL IMPERIAL
SHREE OSTWAL BUILDERS LTD
See every Palghar project, with the district possession charts
Builder: vision developers
VISION DEVELOPERS has 13 registrations on MahaRERA, including Visions Indradhanu Phase 2 and VISION ETERNITY. Its filings disclose 4 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Palghar district page.
Frequently asked questions
What are my rights if SAKINA RESIDENCY is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAKINA RESIDENCY?
The registered promoter entity is vision developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAKINA RESIDENCY?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SAKINA RESIDENCY?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAKINA RESIDENCY?
The professionals named in the filing: Architect: SARJAN ARC; Architect: Sarjanarc Associates; Engineer: SARJAN ARC; Engineer: Kavita Balsara; Chartered Accountant: JAIN ANIL AND ASSOCIATES; Chartered Accountant: ASADULLAH A SELIYA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAKINA RESIDENCY?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback