JAY DEVELOPERS: RERA track record

Partnership ยท attribution by exact filing name, entity resolution in progress

JAY DEVELOPERS has 20 registrations in this build, including VIJAY RESIDENCY and VIJAYSHRUSHTI. Its filings disclose 7 earlier MahaRERA projects: 4 of 7 past projects completed on time.

20Registrations in this build
7Past projects disclosed
on timeMedian delivery slip
0Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
VIJAY RESIDENCYNashik, Maharashtra--Completed
VIJAYSHRUSHTINashik, Maharashtra--Completed
VIJAY ANNEXNashik, Maharashtra--Completed
VIJAY ROYALNashik, Maharashtra--Completed
VIJAYPARADISEPARKNashik, Maharashtra--Completed
VIJAY SONNETNashik, Maharashtra--Completed
SAIVIJAYNashik, Maharashtra--Completed
SAMRUDHIPALACENashik, Maharashtra--Completed
SAIVIJAYICONNashik, Maharashtra--Completed
SAISHRUSHTINashik, Maharashtra11689%Registration lapsed
SAI EMPIRENashik, Maharashtra--Completed
SAIVIJAYTRADECENTERNashik, Maharashtra--Completed
Jay EnclaveKolhapur, Maharashtra--Completed
SAI PARKNashik, Maharashtra16866%Registered
SAI TIRUMALANashik, Maharashtra--Completed
SAI SNEHNashik, Maharashtra--Completed
SAI ASHANashik, Maharashtra2825%Registration lapsed
SAICRYSTALSNashik, Maharashtra620%Registered
SAI CASTLENashik, Maharashtra4134%Registered
NARESH RESIDENCYThane, Maharashtra--Completed

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
VIJAY DARSHAN APARTMENT
22 Mar 201022 Mar 2010On time
ADITYA TOWER
28 Jun 201022 Jan 2014+43 months
ADITYA DARSHAN
21 Dec 201120 Apr 2012+4 months
ADITYA TOWER APARTMENT
22 Jan 201422 Jan 2014On time
VIJAY SHRUSHTI B
31 Dec 202031 Dec 2022+24 months
VIJAY SHRUSHTI
10 Sep 202129 Oct 2020On time
SAI TIRUMALA
30 Dec 20231 Apr 2021On time

Frequently asked questions

How do I verify JAY DEVELOPERS as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with JAY DEVELOPERS?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.