Home / Browse projects / Pune, Maharashtra / SAI VELOCITY II

Registered No litigation declared Others project

SAI VELOCITY II

By PRAKASH PANDURANG CHAVAN

RG-MH-12169 · RERA P52100003410 · Last updated on MahaRERA portal: 29 May 2024

Source: official MahaRERA filing

Red flags

  • 58 complaints at MahaRERA
  • Completion date moved by 96 months
  • 3 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedmoved 96 months from the original
42 of 66Construction stages doneacross 6 buildings; furthest along: Internal walls, 98%
58Complaints at MahaRERAon this registration
Jump to the 48 documents Report an error

SAI VELOCITY II is a Others project by PRAKASH PANDURANG CHAVAN in Pune, Maharashtra, registered with MahaRERA as P52100003410 on 5 Aug 2017. Possession is promised by 30 Dec 2027. The completion date has moved by 96 months from the original filing. 58 complaints are on record with the regulator.

At a glance

Project

  • NameSAI VELOCITY II
  • TypeOthers
  • Location
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100003410
  • ReraGenie IDRG-MH-12169

Builder

  • NamePRAKASH PANDURANG CHAVAN
  • Entity typeIndividual
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Aug 2017
  • Promised completion30 Dec 2027
  • Revised completionRevised to 30 Dec 2027 (originally 25 Dec 2019)
  • Buildings6 building records
  • Documents filed48 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A BUILDINGNA140000
B BUILDINGNA140000
C BUILDINGNA140000
D BUILDINGNA140000
E BUILDINGNA20000
F BUILDINGNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building6

As on 29 May 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

42 of 66 construction stages are filed complete across 6 buildings. The stage furthest along is Internal walls, at 98%.

A BUILDING90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B BUILDING90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
C BUILDING90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
D BUILDING90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
E BUILDING80%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
F BUILDING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 29 May 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes95%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes50%
Street LightingYes90%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterYes80%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes70%
Open ParkingYes95%

Parking filed425

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots425
Closed/Covered308
Open Space117
BuildingClosed/CoveredOpen SpaceTotal
A BUILDING8434118
B BUILDING562076
C BUILDING562076
D BUILDING8420104
E BUILDING606
F BUILDING222345

Land and ownership2

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area15,086 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
LandownerVillageDistrict
AKASH KUNDALIK BHUNDEBavadhan BKPune
SOMNATH CHANDRAKANT BHUNDEBavadhan BKPune

Approvals and building plan

Permissible FSI17183.27
Proposed, not sanctioned14,982 sq m
Buildings approved6
Buildings sanctioned6

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPAUD ROAD KOTHRUD PUNE 411038

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAJIT VISHWAS THAKUR
EngineerHEMANT VISHNU NIMBKAR
PartnerRole in project
PRAKASH PANDURANG CHAVAN-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100000419Dec 2019 → Dec 2020

Reason as filed by the promoterThe Procedure for handing over of amenity space to the PMRDA (Competent Authority) is pending at PMRDA since last more than 14 months, which is resulted in substantial delay for revised building permission.

EXT52100009805Dec 2019 → May 2022

Reason as filed by the promoterSir, I Prithvi Shelters , Prakash Pandurang Chavan here by requesting you to extent our project date of Rera Registration completion from 23/06/2021 to 31/05/2022 the reason is as below. Sir, since last 2 years do to covid 19 because of which we are unable to progress the work in all respect. And mostly labour problem has been accorded. And unavailability of material supply has been accorded along with all above reasons finance prevision problem from all sources has been accorded. Myself was get infected by covid 19 and I was admitted in Pune Sasoon Hospital and prescribed to rest for at least

EXT52100019883Dec 2019 → Dec 2027

Reason as filed by the promoterI, Prithvi Shelters, Prop. Shri. Prakash Pandurang Chavan, here by requesting you that, our project is almost for completion, but some project work is still to be completed, and our project having completion date 30 November 2022 as per RERA Registration. We are having in this phase A,B,C,D Building having total 374 flats and we have given the possession of 325 flats till today. and only 49 flats out of 374 flats, have to be given the possession. we require upto 30/12/2027 For completing the balance work.

Complaints filed with MahaRERA58

Case no.ComplainantRespondentFiled
CC005000000043738Pradeep Dashrath MatadeM/S Prithvi Shelters02/12/2019
CC005000000011913BHARAT CHAUDHARIPRAKASH PANDURANG CHAVAN10/08/2018
CC005000000022517ABHIRUCHI PRASHANT KULKARNIPRAKASH CHAVAN30/01/2019
CC005000000022518MANGESH CHOUGULEPRAKASH CHAVAN30/01/2019
CC005000000022519KANCHAN KOTHAWADEPRAKASH CHAVAN30/01/2019
CC005000000022550Sarang TakalkarPRAKASH CHAVAN03/02/2019
CC005000000022551Revati Ramesh JoshiPRAKASH CHAVAN02/02/2019
CC005000000022552Anil Chavdas ChaudharyPRAKASH CHAVAN08/02/2019
CC005000000022554Chetan MarnePRAKASH CHAVAN02/02/2019
CC005000000022555Rakesh Kailash AgarwalPRAKASH CHAVAN03/02/2019
CC005000000022556Sumitra Panchaxari SwamiPRAKASH CHAVAN02/02/2019
CC005000000022557Nilesh Premraj IngalePRAKASH CHAVAN03/02/2019
CC005000000022560Deepak GhapurePRAKASH CHAVAN02/02/2019
CC005000000022561Sameer BothrePRAKASH CHAVAN02/02/2019
CC005000000022563Amar Arun AwatiPRAKASH CHAVAN03/02/2019
CC005000000022564Preeti ChoudharyPRAKASH CHAVAN02/02/2019
CC005000000022565Chetan Vasant MarnePRAKASH CHAVAN02/02/2019
CC005000000022566Suresh KalePRAKASH CHAVAN02/02/2019
CC005000000022568Rajendra Baban MahalePRAKASH CHAVAN02/02/2019
CC005000000022569Rupesh Ramesh MedhekarPRAKASH CHAVAN08/02/2019
CC005000000022571Chetan UdgirPRAKASH CHAVAN02/02/2019
CC005000000022572KAILAS YENPUREPRAKASH CHAVAN02/02/2019
CC005000000022573Sharad MahalePRAKASH CHAVAN02/02/2019
CC005000000022574Sandeep Shrikant KondharePRAKASH CHAVAN02/02/2019
CC005000000022575Swanand Madhusudan KulkarniPRAKASH CHAVAN02/02/2019
CC005000000022577Umesh PatilPRAKASH CHAVAN15/02/2019
CC005000000022578Amol Ankush BhandawalkarPRAKASH CHAVAN02/02/2019
CC005000000022579Suhas Pradeep HarishchandrePRAKASH CHAVAN03/02/2019
CC005000000022580Sanjay Shankar PatilPRAKASH CHAVAN08/02/2019
CC005000000022581Vishal Vinayak DivekarPRAKASH CHAVAN02/02/2019
CC005000000022585Swapnil S SawargaonkarPRAKASH CHAVAN02/02/2019
CC005000000022586Vilas Namdeo PhalakPRAKASH CHAVAN03/02/2019
CC005000000022587Pritam KulkarniPRAKASH CHAVAN02/02/2019
CC005000000022588Neeraj MaheshwariPRAKASH CHAVAN02/02/2019
CC005000000022589Rajiv Laxmikant BhoplePRAKASH CHAVAN03/02/2019
CC005000000022591Shrirang Shrikant KumbharPRAKASH CHAVAN04/02/2019
CC005000000022592Sagar Prakash MethaPRAKASH CHAVAN04/02/2019
CC005000000022594Laxmikant MandolePRAKASH CHAVAN03/02/2019
CC005000000022595Priyanka Niranjan JadhavPRAKASH CHAVAN04/02/2019
CC005000000022597Ajit GujrathiPRAKASH CHAVAN02/02/2019
CC005000000022598Lahu WaghPRAKASH CHAVAN03/02/2019
CC005000000022600Shrirang KadamPRAKASH CHAVAN02/02/2019
CC005000000022603PRACHI S KOTASTHANEPrakash Chavan02/02/2019
CC005000000022604SANJAY UBHEPRAKASH CHAVAN02/02/2019
CC005000000022086LAXMIKANT MANDOLEPRAKASH PANDURANG CHAVAN30/09/2018
CC005000000022505PRAVIN MANILAL SANGHVIM/S PRITHVI SHELTERS THROUGH PROPRIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000022506PRAVIN MANILAL SANGHVIM/S PRITHVI SHELTERS THROUGH PROPRIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000022507PRAVIN MANILAL SANGHVIM/S PRITHVI SHELTERS THROUGH PROPRIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000022503KALPANA PRAVIN SANGHVIM/S PRITHVI SHELTERS THROUGH PROPRIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000022624KALPANA PRAVIN SANGHVIM/S PRITHVI SHELTERS THROUGH PROPRIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000022549DEEPAK PRAVIN SANGHVIM/S PRITHVI SHELTERS THROUGH PROPRIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000022553DEEPAK PRAVIN SANGHVIM/S PRITHVI SHELTERS THROUGH PROPIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000022558DEEPAK PRAVIN SANGHVIM/S PRITHVI SHELTERS THROUGH PROPIETOR PRAKASH PANDURANG CHAVAN14/02/2019
CC005000000023456DINKAR GIRIJA PUJARIPRAKASH PANDURANG CHAVAN21/09/2019
CC005000000033570NARESH KULKARNIPRAKASH PANDURANG CHAVAN25/10/2019
CC005000000033571JAYESH DHAMUNSHE AND JAYASHREE DHAMUNSHEPRAKASH PANDURANG CHAVAN02/11/2019
CC005000000053973SUNIL SHIVAJI NANDAVADEKAR AND SHIVAJI BABU NANDAVADEKARPRAKASH PANDURANG CHAVAN22/01/2020
CC005000000075092CHANDRASHEKHAR PHALKE AND PRADNYA PHALKEPRAKASH PANDURAN CHAVAN15/01/2021

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 27 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Dec 2027

Documents filed48

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Details of encumbrances concerned to FinanceFile: encumbrances.pdf29 May 2024
Details of encumbrances concerned to LegalFile: encumbrances.pdf29 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Engineers Certificate.pdf29 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Engineers Certificate.pdf29 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineers Certificate.pdf29 May 2024
CERSAI detailsFile: clear tile.pdf29 May 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Other Real Estate.pdf29 May 2024
Proforma of Agreement for saleFile: Agreement For Sale.pdf29 May 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: account details.pdf29 May 2024
Deviation Report with respect to Allotment letterFile: Deviation Report.pdf29 May 2024
Deviation Report with respect to model copy of AgreementFile: Agreement For Sale.pdf29 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate.pdf27 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Form 5 2017-18.pdf27 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 2018-19.pdf27 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 2019-20.pdf27 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 2020-21.pdf27 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FROM 2A (1).pdf26 Jul 2021
OtherFile: Maha Rera.pdf21 Jul 2021
Disclosure of sold/ booked inventoryFile: sai velocity sold unsold 1.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: sai velocity sold unsold 2.pdf20 Jul 2021
Disclosure of sold/ booked inventoryFile: sai velocity sold unsold 3.pdf20 Jul 2021
Declaration about Commencement CertificateFile: Declaration.pdf10 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_.pdf9 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_.pdf9 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PRITHVI SHELTER RERA 2021_1.pdf9 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: PRITHVI SHELTER RERA 2021_1.pdf9 Jul 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect form 1 28072017.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENGINEERS CERTIFICATE New.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA FORM 3.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA Sold Flat.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA Unsold Flat Land Owner.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA Unsold Flat Prithvi Shelters.pdf28 Jul 2017
Proforma of Allotment letterFile: Agreement 28072017.pdf28 Jul 2017
Building plan approvalFile: 2 to 4.pdf27 Jul 2017
Building plan approvalFile: 5 to 7.pdf27 Jul 2017
Building plan approvalFile: 8 to 10.pdf27 Jul 2017
Layout approvalFile: Layout Plan.pdf27 Jul 2017
Building plan approvalFile: 11 to 15.pdf27 Jul 2017
PAN CardFile: PAN CARD.pdf27 Jul 2017
Copy of the legal title reportFile: Search Title Report.pdf27 Jul 2017
Details of encumbrancesFile: Encumbrances Letter.pdf27 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf27 Jul 2017
Building Plan Approval (IOD)File: 2 to 4.pdf27 Jul 2017
Building Plan Approval (IOD)File: 5 to 7.pdf27 Jul 2017
Building Plan Approval (IOD)File: 8 to 10.pdf27 Jul 2017
Building Plan Approval (IOD)File: 11 to 15.pdf27 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificates.pdf27 Jul 2017
Declaration in FORM BFile: Declaration From B.pdf27 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
SAI VELOCITY IP52100003671Bavadhan BK, PuneAug 2017CompletedDec 2017Jul 2017

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 96 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI VELOCITY II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavadhan BK13,700+ in Pune

2 kmSAI VELOCITY IICompleted 61Lapsed / revoked 41Other 77Dot size: filed unitsN

Filed coordinates, straight-line distance. 179 registered projects within 2 km.

Builder: PRAKASH PANDURANG CHAVAN

PRAKASH PANDURANG CHAVAN has 2 registrations on MahaRERA, including SAI VELOCITY II and SAI VELOCITY I. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SAI VELOCITY II is delayed beyond 30 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI VELOCITY II?

The registered promoter entity is PRAKASH PANDURANG CHAVAN, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI VELOCITY II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAI VELOCITY II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAI VELOCITY II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI VELOCITY II?

The professionals named in the filing: Architect: AJIT VISHWAS THAKUR; Engineer: HEMANT VISHNU NIMBKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI VELOCITY II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI VELOCITY II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI VELOCITY II to a free account