Home / Browse projects / Pune, Maharashtra / SAI DWARKA PHASE 3

Completed No litigation declared Residential / Group Housing project

SAI DWARKA PHASE 3

By MAA SANKALP BUILDCON

RG-MH-12373 · RERA P52100011408 · Last updated on MahaRERA portal: 25 Dec 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 48 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2023Possession promisedregistration recorded completed
8 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 72%
1Complaints at MahaRERAon this registration
Jump to the 51 documents Report an error

SAI DWARKA PHASE 3 is a Residential / Group Housing project by MAA SANKALP BUILDCON in Pune, Maharashtra, registered with MahaRERA as P52100011408 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2023. The completion date has moved by 48 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAI DWARKA PHASE 3
  • TypeResidential / Group Housing
  • Location
    • YAWALEWADI
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100011408
  • ReraGenie IDRG-MH-12373

Builder

  • NameMAA SANKALP BUILDCON
  • Entity typePartnership
  • Other registrations3 more →
  • Completed4 of 4
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2019Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on31 Aug 2017
  • Promised completion31 Dec 2023
  • Revised completionRevised to 31 Dec 2023 (originally 31 Dec 2019)
  • Buildings2 building records
  • Documents filed51 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING D1NA110000
BUILDING D2NA110000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 25 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 72%.

BUILDING D146%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure72%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises27%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks9%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
BUILDING D245%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure72%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises27%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities18

As on 25 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%
GYMYes0%
CHILDREN PLAY AREAYes0%
WATER BODYYes0%

Parking filed12

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots12
Closed/Covered12
BuildingClosed/CoveredTotal
BUILDING D11111
BUILDING D211

Land and ownership7

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,805 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
LandownerVillageDistrict
SANGITA RAMCHANDRAJADHAVYAWALEWADIPune
MANGAL LAXMAN JADHAVYAWALEWADIPune
DURGA DEVIDAS JADHAVYAWALEWADIPune
VALMIKI JADHAVYAWALEWADIPune
PARUBAI KAMTHEYAWALEWADIPune
SUMAN PATHAREYAWALEWADIPune
KAMAL KAMATHEYAWALEWADIPune

Approvals and building plan

Permissible FSI3120.62
Proposed, not sanctioned3,121 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKondwe 098 Branch, Pune 411048

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectRAJENDRA H. THITE
EngineerTHE AXIS STRUCTURAL CONSULTANTS STR
PartnerRole in project
MAA SANKALP BUILDCON-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012610Dec 2019 → Dec 2023

Reason as filed by the promoterThe Promoter has applied for second extension with the requisite consent of the Allottees as per Rule. The Promoter has completed the buildings under this Registration upto 90%-95% & undertakes to complete the building/s under registration along with the Completion Certificate till 31/12/2023. Attached herewith copy of Consent obtained from the concerned Allottees. Hence, the application may kindly be allowed and project may kindly be extended till 31/12/2023

EXT52100003738Dec 2019 → Dec 2020

Reason as filed by the promoterOut of the entire Project, the Promoter has completed 90% of work till date and undertakes to complete balance of the remaining work within 11 months. The Promoter / Developer are slightly in financial crunch hence could not complete the project within stipulated time. The Promoter / Developer assures that the said remaining balance work would be completed within 11 months, however seeking extension for the period of one year so that there is no hindrances in completing the project as stated herein above period.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12601241SHIVAJI VITTHAL DANGEMAA SANKALP BUILDCON07/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Dec 2024

Documents filed51

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Sai Dwarka Phase- III.pdf25 Dec 2024
Details of encumbrancesFile: DETAIL OF ENCUMBRANCES Part 1 D E F.pdf5 May 2023
Details of encumbrances concerned to FinanceFile: DETAIL OF ENCUMBRANCES Part 1 D E F.pdf5 May 2023
Details of encumbrances concerned to LegalFile: DETAIL OF ENCUMBRANCES Part 1 D E F.pdf5 May 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory 18-10-2022.pdf18 Oct 2022
CERSAI detailsFile: CERSAI_Search_Report_200247876017_For_Asset_Based_Search_22_09_2022_17_15_28_146.pdf23 Sep 2022
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf22 Sep 2022
Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf22 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Engineers Certificate on Quality Assurance (Form 2A FY 2019-20).pdf22 Sep 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineers Certificate on Quality Assurance Form 2A FY 2020-21.pdf22 Sep 2022
Disclosure of sold/ booked inventoryFile: Disclosure of sold booked inventory.pdf22 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Phase 3 1920 form 5.pdf19 Sep 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Phase 3 2021 form 5.pdf19 Sep 2022
Details of encumbrancesFile: Encumbrances Part 2.pdf28 Jan 2022
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Phase 3.pdf17 Jan 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng certificate Phase 3_compressed.pdf16 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Phase 3 FY 2017-2018.pdf16 Jan 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Phase 3 FY 2018-2019_compressed.pdf16 Jan 2020
Certificates of CA (Form 5)File: form 3.pdf24 May 2019
Details of encumbrancesFile: LETTER OF ENCUMBRANCE.pdf2 Jul 2018
Details of encumbrancesFile: release deed index 2.pdf2 Jul 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Updt Arc Cer Ph 3.pdf29 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA UPDATE ENG PH 3.pdf29 Mar 2018
Building plan approvalFile: D1 5.pdf31 Jul 2017
Building plan approvalFile: IOD.pdf31 Jul 2017
Building plan approvalFile: D1.pdf31 Jul 2017
Building plan approvalFile: D1 1.pdf31 Jul 2017
Layout approvalFile: MASTER LAYOUT DEF.pdf31 Jul 2017
Building plan approvalFile: D1 2.pdf31 Jul 2017
Building plan approvalFile: D1 3.pdf31 Jul 2017
Building plan approvalFile: D1 4.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: MASTER LAYOUT DEF.pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD.pdf31 Jul 2017
Building Plan Approval (IOD)File: D1.pdf31 Jul 2017
Building Plan Approval (IOD)File: D1 1.pdf31 Jul 2017
Building Plan Approval (IOD)File: D1 2.pdf31 Jul 2017
Building Plan Approval (IOD)File: D1 3.pdf31 Jul 2017
Building Plan Approval (IOD)File: D1 4.pdf31 Jul 2017
Building Plan Approval (IOD)File: D1 5.pdf31 Jul 2017
Declaration in FORM BFile: Form B D E F.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENINEER CERTIFICATE SAI DWARKA d1d2.pdf31 Jul 2017
Certificates of CA (Form 3)File: ca certificate phase 3.pdf31 Jul 2017
PAN CardFile: PANCARD.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE REPORT 1.pdf29 Jul 2017
Copy of the legal title reportFile: TITLE REPORT 2.pdf29 Jul 2017
Details of encumbrancesFile: ENCUMBRANCE D.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 1.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: 2.pdf29 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: ARCHITECT CERTIFICATE-ilovepdf-compressed (1).pdf29 Jul 2017
Proforma of Allotment letterFile: allotment D building.pdf29 Jul 2017
Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf29 Jul 2017

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SADGURU RESIDENCYP52100017241YEWALEWADI, Pune2Jul 2018OngoingDec 2026Registered original: Dec 2023Not due yet

How this compares with Pune

26%of Pune projects moved their completion datethis one moved by 48 months
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAI DWARKA PHASE 3 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near YAWALEWADI13,700+ in Pune

2 kmSAI DWARKA PHASE 3Completed 7Lapsed / revoked 5Dot size: filed unitsN

Filed coordinates, straight-line distance. 12 registered projects within 2 km.

Builder: MAA SANKALP BUILDCON

MAA SANKALP BUILDCON has 4 registrations on MahaRERA, including SAI DWARKA PHASE 1 and SAI DWARKA PHASE 3. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SAI DWARKA PHASE 3 is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAI DWARKA PHASE 3?

The registered promoter entity is MAA SANKALP BUILDCON, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAI DWARKA PHASE 3?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAI DWARKA PHASE 3?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAI DWARKA PHASE 3?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAI DWARKA PHASE 3?

The professionals named in the filing: Architect: RAJENDRA H. THITE; Engineer: THE AXIS STRUCTURAL CONSULTANTS STR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAI DWARKA PHASE 3?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAI DWARKA PHASE 3. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAI DWARKA PHASE 3 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.