ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / SAHADEO IRIS

Completed No litigation declared Residential / Group Housing project

SAHADEO IRIS

By J K HOUSING DEVELOPMENT CORPORATION

RG-MH-47030 · RERA P52100018262 · Last updated on MahaRERA portal: 5 Nov 2024

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2022Possession promisedregistration recorded completed
2 of 11Construction stages donefurthest along: Basement (if any), 75%
1Complaints at MahaRERAon this registration
Jump to the 29 documents Report an error

SAHADEO IRIS is a Residential / Group Housing project by J K HOUSING DEVELOPMENT CORPORATION in Pune, Maharashtra, registered with MahaRERA as P52100018262 on 22 Oct 2018. The registration is recorded completed; possession was promised by 30 Dec 2022. 1 complaint is on record with the regulator.

At a glance

Project

  • NameSAHADEO IRIS
  • TypeResidential / Group Housing
  • Location
    • PARK RIDGE ROAD
    • PASHAN
    • Haveli
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100018262
  • ReraGenie IDRG-MH-47030

Builder

  • NameJ K HOUSING DEVELOPMENT CORPORATION
  • Entity typePartnership
  • PartnersKANCHAN KAILAS NIMHAN, KANCHAN KAILAS NIMHAN

Key dates

this monthRegisteredOct 2018PromisedDec 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Oct 2018
  • Promised completion30 Dec 2022
  • Revised completionNone
  • Buildings1 building record
  • Documents filed29 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING ANA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 5 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 75%.

BUILDING A: 50% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)75%
Podiums (if any)0%
Plinth75%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.30%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities18

As on 5 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes25%
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes60%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes50%
Open ParkingNoNot applicable
ROOF TOP GARDENYes0%
Outer Compound WallYes100%
Decorative Entrance Lobby mainYes0%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,000 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI2742.15
Proposed, not sanctioned1,702 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTEJAS ETERNITY BANER BALEWADI ROAD BANER

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVISHWAS KULKARNI
EngineerG A BHILARE
PartnerRole in project
J K HOUSING DEVELOPMENT CORPORATION-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC005000000340664Akshay Shivajirao GokhareJ K HOUSING DEVELOPMENT CORPORATION25/04/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 9 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 8 Nov 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 9 Oct 2018
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 8 Nov 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 22 Oct 2021

Documents filed29

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society formation certificate- Sahadeo Iris.pdf5 Nov 2024
Status of Formation of Legal Entity (Society/Co Op etc.)File: 3 Distric Register coop Soc Letter.pdf2 Nov 2024
Status of ConveyanceFile: 2 Conveyance Deed Draft compress.pdf2 Nov 2024
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - 1.pdf25 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5 (FY 18-19)_compressed.pdf22 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM-5 (FY 19-20)_compressed.pdf22 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM -5 (FY 20-21)_compressed.pdf22 Oct 2021
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: PMC COMPLITION CERTIFICATE.pdf22 Oct 2021
Declaration about Commencement CertificateFile: Format D.pdf18 Oct 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_compressed.pdf18 Oct 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A er iris_compressed.pdf18 Oct 2021
Disclosure of sold/ booked inventoryFile: iris sold unsold.pdf18 Oct 2021
Proforma of Allotment letterFile: Final Agreement to Sale of Sahadeo Iris.pdf14 Nov 2019
Layout approvalFile: REVISED SANCTION PLAN.pdf8 Nov 2019
Copy of Layout Approval (in case of layout)File: REVISED SANCTION PLAN.pdf8 Nov 2019
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC_compressed.pdf8 Nov 2019
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter 14-10-2019_compressed.pdf4 Nov 2019
Engineers Certificate on Quality Assurance (Form 2A)File: Engineer Certificate Form 2A 21-10-2019_compressed.pdf4 Nov 2019
Certificates of CA (Form 3)File: CA Certificate.pdf13 Oct 2018
Proforma of Allotment letterFile: Allotment Letter III.pdf13 Oct 2018
Building plan approvalFile: Commencement Certificate.pdf9 Oct 2018
Layout approvalFile: Approved site Plan final .pdf9 Oct 2018
PAN CardFile: Pancard of Organization.pdf9 Oct 2018
Copy of the legal title reportFile: LEGAL 2.pdf9 Oct 2018
Details of encumbrancesFile: Non Encumbrances Decleration Letter.pdf9 Oct 2018
Copy of Layout Approval (in case of layout)File: Approved site Plan final .pdf9 Oct 2018
Building Plan Approval (IOD)File: Commencement Certificate.pdf9 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf9 Oct 2018
Declaration in FORM BFile: FORM - B.pdf9 Oct 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAHADEO IRIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PASHAN13,700+ in Pune

Builder: J K HOUSING DEVELOPMENT CORPORATION

J K HOUSING DEVELOPMENT CORPORATION has 1 registration on MahaRERA, including SAHADEO IRIS. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SAHADEO IRIS is delayed beyond 30 Dec 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAHADEO IRIS?

The registered promoter entity is J K HOUSING DEVELOPMENT CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAHADEO IRIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAHADEO IRIS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAHADEO IRIS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAHADEO IRIS?

The professionals named in the filing: Architect: VISHWAS KULKARNI; Engineer: G A BHILARE. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAHADEO IRIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAHADEO IRIS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAHADEO IRIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.