SAFAL TRADEMARK
By JAI MATA DI HOME CONSTRUCTION PVT LTD
RG-MH-25169 · RERA P51800003754 · Last updated on MahaRERA portal: 29 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- 30 complaints at MahaRERA
- Completion date moved by 36 months
- 5 extensions taken
- Rs 45.00 crore secured on the land, in favour of BANK OF INDIA
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAFAL TRADEMARK is a Residential / Group Housing project by JAI MATA DI HOME CONSTRUCTION PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800003754 on 6 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 36 months from the original filing. 212 of the 252 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 30 complaints are on record with the regulator.
At a glance
Project
- NameSAFAL TRADEMARK
- TypeResidential / Group Housing
- Location
- V.N.PURAV MARG
- CHEMBUR
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800003754
- ReraGenie IDRG-MH-25169
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on6 Aug 2017
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Dec 2023)
- Buildings1 building record
- Documents filed176 files
Current status
Figures as on 29 Jul 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV | NA | 19 | 16 | 252 | 0 | 252 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 29 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 95%.
SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV: 81% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 70% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 85% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Progress on shared amenities15
As on 29 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 20% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 70% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 10% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed323
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAFAL TRADEMARK TOWER 1,2,3 4 WAMANDEV | NA | Rs 147.00 cr | Rs 130.60 cr |
| - | NA | Rs 11.00 cr | Rs 3.40 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DILIP SANGHVI CONSULTANTS |
| Engineer | VIJAY NARANG |
| Chartered Accountant | BANWAT & CO. |
| Chartered Accountant | P.C. DHOLAKIA & CO. |
| Partner | Role in project |
|---|---|
| JAI MATA DI HOME CONSTRUCTION PVT LTD | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterTHE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW WE HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS.
Reason as filed by the promoterDUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS NOT COMPLETED THEREFORE REQUIRE EXTENSION UPTO 31ST MARCH 2025.
Reason as filed by the promoterDUE TO UNRESOLVED FINANCIAL CONSTRAINTS FACED , CONSTRUCTION WORK OF THE BUILDINGS ARE NOT COMPLETED . THEREFORE, WE REQUIRE ADDTIONAL TIME I.E EXTENSION UPTO 31ST DECEMBER 2025 TO COMPLETE THE CONSTRUCTION OF PROJECT. WE ARE COMMITTED TO RESOLVE THE FINANCIAL MATTERS AT THE EARLIEST AND ENSURE TIMELY COMPLETION OF PROJECT.
Reason as filed by the promoterDue to financial constraints faced by us, the progress of the project was temporarily affected. We wish to inform you that all financial issues have now been resolved, and construction work has recommenced in full swing with adequate resources deployed at site. We assure you that the interests of the allottees / customers are fully secured, and the project shall be completed within the extended period.
Reason as filed by the promoter1. The structural construction of the project is fully completed. However, additional time of approximately7 (Seven Months) months is required to complete the remaining finishing works, Car Parking, testing, common area development, and rectification of minor pending items and statutory inspections, compliance procedures, and obtaining the Occupancy Certificate from the competent authority. Please Grant extension upto 31st December 2026
Complaints filed with MahaRERA30
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12401251 | Sumeet Ramnath Nayak | JAI MATA DI HOME CONSTRUCTION PVT LTD | 27/12/2024 |
| CC12501118 | MANISH SINGHVI | JAI MATA DI HOME CONSTRUCTION PVT LTD | 03/04/2025 |
| CC12501604 | PRITHIPAL SINGH BHAMBRA | JAI MATA DI HOME CONSTRUCTION PVT LTD | 15/05/2025 |
| CC12501639 | HARLEEN PASRICHA | JAI MATA DI HOME CONSTRUCTION PVT LTD | 21/05/2025 |
| CC12501640 | MANINDER PASRICHA | JAI MATA DI HOME CONSTRUCTION PVT LTD | 21/05/2025 |
| CC12502045 | Sonal Sharma | JAI MATA DI HOME CONSTRUCTION PVT LTD | 23/06/2025 |
| CC12502586 | Rakesh Prakash Bhat | JAI MATA DI HOME CONSTRUCTION PVT LTD | 27/07/2025 |
| CC12502587 | Sharad Nagesh Shenoy | JAI MATA DI HOME CONSTRUCTION PVT LTD | 27/07/2025 |
| CC12502589 | Shankar Jagtap | JAI MATA DI HOME CONSTRUCTION PVT LTD | 27/07/2025 |
| CC12502509 | Deep Mukherjee | JAI MATA DI HOME CONSTRUCTION PVT LTD | 21/07/2025 |
| CC12502625 | Rajesh Bhatia | JAI MATA DI HOME CONSTRUCTION PVT LTD | 30/07/2025 |
| CC12502591 | Rahul Rajanikant Pathak | JAI MATA DI HOME CONSTRUCTION PVT LTD | 27/07/2025 |
| CC12502593 | Deepak Prakash Gurnane | JAI MATA DI HOME CONSTRUCTION PVT LTD | 28/07/2025 |
| CC12502603 | Sonali Melmane | JAI MATA DI HOME CONSTRUCTION PVT LTD | 28/07/2025 |
| CC12502626 | Amit Chanda | JAI MATA DI HOME CONSTRUCTION PVT LTD | 30/07/2025 |
| CC12502607 | Ronak Johari | JAI MATA DI HOME CONSTRUCTION PVT LTD | 28/07/2025 |
| CC12502627 | Offshore Infrastructures Limited | JAI MATA DI HOME CONSTRUCTION PVT LTD | 30/07/2025 |
| CC12502592 | Amit Gulshan Talwar | JAI MATA DI HOME CONSTRUCTION PVT LTD | 27/07/2025 |
| CC12502594 | Sethu naga muthu Rakkumuthu Thangavelu | JAI MATA DI HOME CONSTRUCTION PVT LTD | 28/07/2025 |
| CC12503369 | Neha Chendvankar | JAI MATA DI HOME CONSTRUCTION PVT LTD | 21/09/2025 |
| CC12503409 | Unita Agatha Dmello | JAI MATA DI HOME CONSTRUCTION PVT LTD | 23/09/2025 |
| CC12503517 | Rajesh Chander Jagasia | JAI MATA DI HOME CONSTRUCTION PVT LTD | 02/10/2025 |
| CC12503559 | Jagan Ramaswamy | JAI MATA DI HOME CONSTRUCTION PVT LTD | 07/10/2025 |
| CC12503523 | Umesh Ravindra Gupta | JAI MATA DI HOME CONSTRUCTION PVT LTD | 03/10/2025 |
| CC12503524 | Shailendra Surendra Gupta | JAI MATA DI HOME CONSTRUCTION PVT LTD | 03/10/2025 |
| CC12503849 | Bina Vijay Patel | JAI MATA DI HOME CONSTRUCTION PVT LTD | 02/11/2025 |
| CC12503848 | Vijay Ambalal Patel | JAI MATA DI HOME CONSTRUCTION PVT LTD | 02/11/2025 |
| CC12600574 | Arvind Setia | JAI MATA DI HOME CONSTRUCTION PVT LTD | 02/02/2026 |
| CC12601626 | Mona Ajay Kakar | JAI MATA DI HOME CONSTRUCTION PVT LTD | 23/03/2026 |
| CC12601245 | Sunil Kumar Singh | JAI MATA DI HOME CONSTRUCTION PVT LTD | 07/03/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 2 May 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Jul 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 Feb 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed176
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 176 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Building plan approvalFile: TRADEMARK PLAN NO 1.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 2.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 3.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 4.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 5.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 6.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 7.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 8.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 9.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 10.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 11.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 12.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 13.pdf | 29 Jul 2026 |
| Building plan approvalFile: trademark plan no 14.pdf | 29 Jul 2026 |
| Building plan approvalFile: rehab sale.pdf | 29 Jul 2026 |
| Withdrawal Update Form 1File: FORM 1 SAFAL STRADEMARK APR TO JUNE 2026.pdf | 24 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 SAFAL TRADEMARK APR TO JUNE 2026.pdf | 24 Jul 2026 |
| Withdrawal Update Form 3File: FORM 3 SAFAL TRADEMARK APR TO JUNE 2026.pdf | 24 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 MAR 2026 SAFAL TRADEMARK.pdf | 27 May 2026 |
| Withdrawal Update Form 1File: Form 1 MAR 2026 SAFAL TRADEMARK.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2 TRADEAMRK MAR 2026.pdf | 27 May 2026 |
| Withdrawal Update Form 2File: Form 2 TRADEAMRK MAR 2026.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: FORM 3 SAFAL TRADEMARK mar26.pdf | 27 May 2026 |
| Withdrawal Update Form 3File: FORM 3 SAFAL TRADEMARK mar26.pdf | 27 May 2026 |
| Form 2A (FY 2025-2026)File: Safal Treadmark Form 2A.pdf | 27 May 2026 |
| Layout approvalFile: Layout with highlights.pdf | 2 May 2026 |
| Building plan approvalFile: PLAN with highlights.pdf | 2 May 2026 |
| Building plan approvalFile: Rehab Sale.pdf | 2 May 2026 |
| Commencement certificateFile: SAFAL TRADEMARK Full CC.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: SAFAL TRADEMARK FORM 1 JUNE 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: TM FORM 1 SEPT 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 1File: TM FORM 1 DEC 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: Safal Traedmark Form 2 JUNE 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: SAFAL TRADEMARK FORM 2 SEPT 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 2File: TM FORM 2 DEC 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: SAFAL TRADEMARK FORM 3 JUNE 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: SAFAL TRADEMARK FROM 3 SEPT 2025.pdf | 16 Feb 2026 |
| Withdrawal Update Form 3File: SAFAL TRADEMARK FROM 3 DEC 2025.pdf | 16 Feb 2026 |
| Declaration in FORM BFile: TM FORM B.pdf | 19 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Safal Treadmark Form 1.pdf | 17 Apr 2025 |
| Certificates of CA (Form 3)File: FORM 3 TM MAR 2025.pdf | 17 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Safal Treadmark Form 2.pdf | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: MARCH TM INVENTORY.pdf | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: inventory december 2024.pdf | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: MARCH TM INVENTORY.pdf | 17 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Safal Treadmark Form 2A.pdf | 17 Apr 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 TM MAR 2025.pdf | 17 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 tm dec 2024.pdf | 28 Jan 2025 |
| Certificates of CA (Form 3)File: TM FORM 3 DEC 2024.pdf | 28 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 tm dec 2024.pdf | 28 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 TM SEPT 2024.pdf | 9 Jan 2025 |
| Certificates of CA (Form 3)File: FORM 3 TM SEPT 2024.pdf | 9 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: TM FORM 2 SEPT 2024.pdf | 9 Jan 2025 |
| Building plan approvalFile: Amended Letter.pdf | 17 Oct 2024 |
| Building plan approvalFile: S1.pdf | 17 Oct 2024 |
| Building plan approvalFile: S3.pdf | 17 Oct 2024 |
| Building plan approvalFile: S6.pdf | 17 Oct 2024 |
| Building plan approvalFile: S2.pdf | 17 Oct 2024 |
| Building plan approvalFile: S10.pdf | 17 Oct 2024 |
| Building plan approvalFile: Built-up Area.pdf | 17 Oct 2024 |
| Building plan approvalFile: Proforma.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: Proforma.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: Built-up Area.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: S10.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: S2.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: S6.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: S3.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: Amended Letter.pdf | 17 Oct 2024 |
| Building Plan Approval (IOD)File: S1.pdf | 17 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: TM Form 2A WITH SIGN.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: TM FORM 5 WITH SIGN.pdf | 17 Oct 2024 |
| Building plan approvalFile: Amended Letter (1).pdf | 14 Oct 2024 |
| Building plan approvalFile: Typical Floor Diagram.pdf | 14 Oct 2024 |
| Building plan approvalFile: Amended Letter.pdf | 14 Oct 2024 |
| Copy of Layout Approval (in case of layout)File: Layout.pdf | 14 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: SAFAL TRADEMARK Full CC.pdf | 14 Oct 2024 |
| Building Plan Approval (IOD)File: R6.pdf | 14 Oct 2024 |
| Building Plan Approval (IOD)File: R1.pdf | 14 Oct 2024 |
| Building Plan Approval (IOD)File: Amended Letter.pdf | 14 Oct 2024 |
| Building Plan Approval (IOD)File: Typical Floor Diagram.pdf | 14 Oct 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 176 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAFAL TRADEMARK on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near CHEMBUR6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 395 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: JAI MATA DI HOME CONSTRUCTION PVT LTD
JAI MATA DI HOME CONSTRUCTION PVT LTD has 2 registrations on MahaRERA, including SAFAL TRADEMARK and SAFAL MONTBAY. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if SAFAL TRADEMARK is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAFAL TRADEMARK?
The registered promoter entity is JAI MATA DI HOME CONSTRUCTION PVT LTD, a company as per the filing. Its GSTIN 27AABCJ0318A1ZB can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAFAL TRADEMARK?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SAFAL TRADEMARK?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SAFAL TRADEMARK?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAFAL TRADEMARK?
The professionals named in the filing: Architect: DILIP SANGHVI CONSULTANTS; Engineer: VIJAY NARANG; Chartered Accountant: BANWAT & CO.; Chartered Accountant: P.C. DHOLAKIA & CO.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAFAL TRADEMARK?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback