Home / Browse projects / Mumbai Suburban, Maharashtra / SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD
SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD
RG-MH-24536 · RERA P51800004137 · Last updated on MahaRERA portal: 28 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 1 complaint at MahaRERA
- Completion date moved by 64 months
- 6 extensions taken
- Rs 12.00 crore secured on the land, in favour of STATE BANK OF INDIA
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD is a Residential / Group Housing project by VARUN HOMES PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004137 on 8 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 64 months from the original filing. 32 of the 81 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameSAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD
- TypeResidential / Group Housing
- Location
- W.T. Patil Marg
- Chembur
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800004137
- ReraGenie IDRG-MH-24536
Builder
- NameVARUN HOMES PVT LTD
- Entity typeCompany
- Managing DirectorsVARUN VINOD ASRANI, SANJAY VINOD ASRANI
- Other registrations1 more →
- No longer live1 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on8 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 Aug 2020)
- Buildings1 building record
- Documents filed96 files
Current status
Figures as on 28 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SAFAL SKY WING A AND WING B | NA | 16 | 14 | 81 | 0 | 81 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 90%.
SAFAL SKY WING A AND WING B: 70% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 90% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 75% |
| Sanitary Fittings within the flats / premises | 30% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 71% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 28 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 80% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed170
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SAFAL SKY WING A AND WING B | NA | Rs 39.59 cr | Rs 36.25 cr |
| - | NA | Rs 2.00 cr | - |
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Engineer | VIJAY NARANG |
| Chartered Accountant | P.C.DHOLAKIA & CO. |
| Chartered Accountant | BANWAT & CO |
| Partner | Role in project |
|---|---|
| VARUN HOMES PVT LTD | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterBUILDING WORK IS COMPLETED UPTO 11TH FLOOR, FOR CONSTRUCTION ADDITIONAL 2 FLOORS TDR IS REQUIRED DUE TO SHORTAGE OF TDR IN THE MARKET WE ARE UNABLE TO BUY THE SAME THEREFORE YOU ARE REQUESTED TO GIVE EXTENSION OF 10 MONTHS FOR PURCHASE OF TDR & CONSTRUCTING ADDITIONAL 2 FLOORS OF THE BUILDING.
Reason as filed by the promoterBuilding work is completed up to 11th floor and internal work is in progress, earlier developer had taken extension up to June 2024, extension was received in August 2023, Developer took TDR for additional 2 floor and taken approval from BMC which took 6 months. Now Developer is waiting for fund allocation from Bank, as Developer have taken construction finance. Therefore, developer require 4 months to complete the construction of project.
Reason as filed by the promoterDUE TO DISAGREEMENT BETWEEN AMOGH AND AMEYA FOR SUBDIVISION OF LAYOUT R.G. PLOT CTS NO. 409/6 , WE ARE UNABLE TO TAKE ADVANTAGE OF RG PLOT FSI AND PROJECT ID DELAYED.
Reason as filed by the promoterLOCK DOWN LED TO CONSTRUCTION ACTIVITIES COMING TO STANDSTILL DUE TO NON AVAILABILITY OF LABOUR & MOVEMENT OF BUILDING MATERIAL. COVID-19 OUTBREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY EFFECTED UNBALE TO RECOVER FUNDS FROM BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE.
Reason as filed by the promoterDUE TO FINANCIAL CONSTRAINTS CONSTRUCTION WORK IS NOT COMPLETED THEREFORE REQUEST TO GIVE EXTENSION UPTO 31ST MARCH 2025.
Reason as filed by the promoterDUE TO UNRESOLVED FINANCIAL ISSUES WE REQUEST TO GRANT EXTENSION UPTO DEC 2025.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12600231 | GAURAV VINOD KAPUR | VARUN HOMES PVT LTD | 13/01/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 27 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 27 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Oct 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed96
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 96 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 june 2025 sky.pdf | 28 May 2026 |
| Withdrawal Update Form 1File: Form 1 SEPT 2025 SKY.pdf | 28 May 2026 |
| Withdrawal Update Form 1File: Form DEC 2025 sky.pdf | 28 May 2026 |
| Withdrawal Update Form 2File: Form 2 june 2025 sky.pdf | 28 May 2026 |
| Withdrawal Update Form 2File: Form 2 SEPT 25 sky.pdf | 28 May 2026 |
| Withdrawal Update Form 2File: Form 2 DEC sky.pdf | 28 May 2026 |
| Withdrawal Update Form 3File: FROM 3 SAFAL SKYjune 2025.pdf | 28 May 2026 |
| Withdrawal Update Form 3File: FROM 3 SAFAL SKY SEPT 2025.pdf | 28 May 2026 |
| Withdrawal Update Form 3File: FROM 3 SAFAL SKY DEC 25.pdf | 28 May 2026 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SKY FORM 1 MARCH 2025.pdf | 2 May 2025 |
| Certificates of CA (Form 3)File: SKY FORM 3 MARCH 2025.pdf | 2 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SKY FORM 2 MARCH 2025.pdf | 2 May 2025 |
| Disclosure of sold/ booked inventoryFile: SKY INVENTORY.pdf | 2 May 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Safal Sky Form 2 A 24 25.pdf | 2 May 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SKY 24 25.pdf | 2 May 2025 |
| Details of encumbrancesFile: CLOSURE LETTER SAFAL SKY.pdf | 7 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Safal Sky Form 1.pdf | 7 Apr 2025 |
| Certificates of CA (Form 3)File: SKY FORM 3.pdf | 7 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Safal Sky Form 2.pdf | 7 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: CERSAI SAFAL SKY.pdf | 7 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: SKY DISCLOSURE OF INVENTORY DEC 2024.pdf | 7 Apr 2025 |
| CERSAI detailsFile: CERSAI SAFAL SKY.pdf | 7 Apr 2025 |
| CERSAI detailsFile: CLOSURE LETTER SAFAL SKY.pdf | 7 Apr 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: DISCLOSURE OF OTHER REAL ESTATE PROJECT SKY.pdf | 7 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SAFAL SKY SEPT 2024.pdf | 19 Dec 2024 |
| Certificates of CA (Form 3)File: FORM 3 SEPT 2024 SKY.pdf | 19 Dec 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Safal Sky Form 2.pdf | 19 Dec 2024 |
| Declaration in FORM BFile: sky form b march 2025.pdf | 9 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SKY FORM 2A 2023-24.pdf | 9 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: SKY Form 2A 19-20.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: SKY Form 2A 20-21.pdf | 29 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: SKY Form 2A 21-22.pdf | 29 Oct 2024 |
| Building plan approvalFile: Amend letter_signed.pdf | 28 Oct 2024 |
| Building plan approvalFile: Drawing (9) (1).pdf | 28 Oct 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC_signed.pdf | 28 Oct 2024 |
| Building Plan Approval (IOD)File: Amend letter_signed.pdf | 28 Oct 2024 |
| Building Plan Approval (IOD)File: Drawing (9) (1).pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOCURE OF INVENTORY SKY SEPT 2024.pdf | 28 Oct 2024 |
| Declaration about Commencement CertificateFile: FORMAT D FOR CC SKY.pdf | 28 Oct 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A SKY DESIGNATED BANK AC.pdf | 28 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SKY FORM 2A 2023-24.pdf | 28 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SKY FORM 2A 2023-24.pdf | 28 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: form 5 sky 2023 2024.pdf | 28 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: DISCLOSURE OF OTHER REAL ESTATE PROJECT SKY.pdf | 28 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 JUNE 2024.pdf | 7 Oct 2024 |
| Certificates of CA (Form 3)File: FORM 3 JUNE 2024 (2).pdf | 7 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2JUNE 2024.pdf | 7 Oct 2024 |
| Declaration in FORM BFile: form b safal sky oct 2024.pdf | 12 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SAFAL SKY march 2024.pdf | 11 Jun 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SAFAL SKY march 2024.pdf | 11 Jun 2024 |
| Certificates of CA (Form 3)File: form 3 mar 2024.pdf | 11 Jun 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAFAL SKY FORM 1 SEPT 2023.pdf | 29 Feb 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAFAL SKY FROM 1 DEC 2023.pdf | 29 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAFAL SKY FROM 2 SEPT 2023.pdf | 29 Feb 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAFAL SKY FORM 2DEC 2023.pdf | 29 Feb 2024 |
| Certificates of CA (Form 3)File: SAFAL SKY FORM 3 SEPT 2023.pdf | 29 Feb 2024 |
| Certificates of CA (Form 3)File: SAFAL SKY FORM 3 DEC 2023.pdf | 29 Feb 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 2021 TO 2022.pdf | 30 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM5 2022 TO 2023.pdf | 30 Oct 2023 |
| Certificates of CA (Form 3)File: FORM -3 SAFAL SKY.pdf | 18 Sep 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - SAFAL SKY MAR 2023.pdf | 4 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - SAFAL SKY MARCH 2023.pdf | 4 Aug 2023 |
| Certificates of CA (Form 3)File: FORM 3 SAFAL SKY 31march 23.pdf | 4 Aug 2023 |
| Certificates of CA (Form 3)File: FORM 3 SAFAL SKY 03 10 22.pdf | 3 Feb 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAFAL SKY FORM 1 31 12 2022.pdf | 2 Feb 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAFAL SKY FORM 2 31 12 22.pdf | 2 Feb 2023 |
| Certificates of CA (Form 3)File: SAFAL SKY FORM 3 31 12 22.pdf | 2 Feb 2023 |
| Details of encumbrancesFile: SAFAL SKY ENCUMBRANCE CERTIFICATE 17012023.pdf | 19 Jan 2023 |
| Certificates of CA (Form 3)File: SAFAL SKY FORM 3 CA CERTIFICATE.pdf | 19 Sep 2022 |
| Certificates of CA (Form 3)File: SAFAL SKY FORM 3 CA CERTIFICATE.pdf | 10 Sep 2022 |
| Building plan approvalFile: SAFAL SKY APPROVED PLAN.pdf | 8 Sep 2022 |
| Building Plan Approval (IOD)File: SAFAL SKY APPROVED PLAN.pdf | 8 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: SAFAL SKY CC REVALIDATION.pdf | 3 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAFAL SKY FORM 1 ARCHITECT CERTIFICATE.pdf | 3 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: SAFAL SKY DISCLOSURE OF INVENTORY TILL JULY 2022.pdf | 3 Sep 2022 |
| Certificates of CA (Form 3)File: SAFAL SKY FORM 3 CA CERTIFICATE.pdf | 3 Sep 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: SKY CC.pdf | 28 Jan 2020 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENGINEER CERTIFICATE.pdf | 28 Jan 2020 |
| Certificates of CA (Form 3)File: FROM 3 CA CERTIFICATE.pdf | 28 Jan 2020 |
| Certificates of CA (Form 5)File: VH SKY FORM 5.pdf | 3 Aug 2019 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 96 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chembur6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 264 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: VARUN HOMES PVT LTD
VARUN HOMES PVT LTD has 2 registrations on MahaRERA, including SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD and SAFAL GANGA SMRUTI. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What does it mean that SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?
The registered promoter entity is VARUN HOMES PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?
The professionals named in the filing: Engineer: VIJAY NARANG; Chartered Accountant: P.C.DHOLAKIA & CO.; Chartered Accountant: BANWAT & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SAFAL SKY REDEVELOPMENT OF AMEYA CHS LTD?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback