Home / Browse projects / Mumbai Suburban, Maharashtra / SAFAL SAI AND SAFAL SAINATH

Registered No litigation declared Residential / Group Housing project

SAFAL SAI AND SAFAL SAINATH

By MANGALNATH DEVELOPERS PVT LTD

RG-MH-26726 · RERA P51800009799 · Last updated on MahaRERA portal: 27 Jun 2026

Source: official MahaRERA filing

Red flags

  • 10 complaints at MahaRERA
  • Completion date moved by 34 months
  • 5 extensions taken
  • Rs 35.00 crore secured on the land, in favour of CATALYST TRUSTEESHIP LIMITED

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 34 months from the original
13 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 60%
53 of 198Units unsoldnot recorded sold or booked
10Complaints at MahaRERAon this registration
Jump to the 118 documents Report an error

SAFAL SAI AND SAFAL SAINATH is a Residential / Group Housing project by MANGALNATH DEVELOPERS PVT LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009799 on 22 Aug 2017. Possession is promised by 31 Oct 2026. The completion date has moved by 34 months from the original filing. 145 of the 198 units on this registration are recorded sold or booked, and 13 of 22 construction stages are filed complete. 10 complaints are on record with the regulator.

At a glance

Project

  • NameSAFAL SAI AND SAFAL SAINATH
  • TypeResidential / Group Housing
  • Location
    • KELKARWADI GHATLA
    • KELKARWADI
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009799
  • ReraGenie IDRG-MH-26726

Builder

  • NameMANGALNATH DEVELOPERS PVT LTD
  • Entity typeCompany
  • PartnersSANJAY VINOD ASRANI, VARUN VINOD ASRANI
  • Other registrations1 more →
  • Declared earlier projects1 →

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on22 Aug 2017
  • Promised completion31 Oct 2026
  • Revised completionRevised to 31 Oct 2026 (originally 30 Dec 2023)
  • Buildings2 building records
  • Documents filed118 files

Current status

73%145 of 198 units booked
69.9%Work done, per cost certificate

Figures as on 27 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
SAFAL SAI WING A WING B AND WING CNA14121370137
SAFAL SAINATHNA212058361

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 27 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 60%.

SAFAL SAI WING A WING B AND WING C96%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
SAFAL SAINATH34%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure25%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks30%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes15%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed126

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots126
Closed/Covered126
BuildingClosed/CoveredTotal
SAFAL SAI WING A WING B AND WING C125125
SAFAL SAINATH11

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area4,686 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofCATALYST TRUSTEESHIP LIMITED
Secured amountRs 35.00 crore
CERSAI search filedYes
Declared on14 Sep 2024

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI9367.0
Proposed, not sanctioned9,367 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDEONAR MUMBAI 400088
Estimated costRs 83.00 cr
Cost incurredRs 58.00 cr
Work done69.88%
BuildingWingEstimatedIncurred
-NARs 34.70 crRs 10.95 cr
SAFAL SAI WING A WING B AND WING CNARs 25.77 crRs 25.30 cr
SAFAL SAINATHNARs 22.53 crRs 21.75 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCONSULTANTS COMBINED ARCHITECTS
EngineerVIJAY NARANG
Chartered AccountantBANWAT & CO
Chartered AccountantP.C.DHOLAKIA & CO
PartnerRole in project
MANGALNATH DEVELOPERS PVT LTD-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800018316Dec 2023 → Aug 2024

Reason as filed by the promoterTHE LOCKDOWNS LED TO CONSTRUCTION ACTIVITIES COMING TO A STANDSTILL DUE TO NON-AVAILABILITY OF LABOUR AND IMPACT ON THE MOVEMENT OF BUILDING MATERIAL. COVID-19 OUT BREAK DELAYED PROJECT COMPLETION TIMELINES, SALES ARE BADLY AFFECTED, EVEN WE ARE UNABLE TO RECOVER FUNDS EXISTING BUYERS AS FINANCIAL CRISIS ARE FACED BY ALMOST EVERYONE DUE TO FUND ISSUE, NOW WE HAVE TAKEN CONSTRUCTION FINANCE, CONSTRUCTION WORK IS IN PROGRESS.

EXT51800024699Dec 2023 → Mar 2025

Reason as filed by the promoterDUE TO FINANCIAL CONSTRAINTS FACED CONSTRUCTION WORK IS STILL NOT COMPLETED THEREFORE REQUEST TO GIVE EXTENSION UPTO 31ST MARCH 2025.

EXT51800028420Dec 2023 → Dec 2025

Reason as filed by the promoterDue to unresolved financial issues that have impacted the progress of the project. Despite of our best efforts, the required financial resources are not yet fully secured. we therefore request for an extension up to December 2025

EA28042620761Dec 2023 → May 2026

Reason as filed by the promoterDue to financial issues project was slow now all financial issues have been fully resolved, and construction work has recommenced in full swing with adequate manpower, machinery, and materials deployed at site. Considering the present progress and the revised construction schedule, we requires an additional 5 months (up to May 2026) to complete the project in all respects. We assures the Hon’ble Authority that the interests of allottees are fully safeguarded, and the project shall be completed within the extended period.

EA27062621575Dec 2023 → Oct 2026

Reason as filed by the promoterThe structural construction of the project is fully completed. However, we require additional time of approximately five months to complete the remaining finishing works, testing, common area development, and rectification of minor pending items and statutory inspections, compliance procedures, and obtaining the Occupancy Certificate from the competent authority. You are therefore requested to kindly consider application and grant us extension upto 31st October 2026

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000428707Praveen Pathak and Shreeya AtreMangalnath Developers Pvt Ltd Earlier known as Mangalnath Developers04/01/2024
CC12601887Pooja SachdevaMANGALNATH DEVELOPERS PVT LTD31/03/2026
CC12502121Urvish Mahendrabhai ModhMANGALNATH DEVELOPERS PVT LTD27/06/2025
CC12502133SURYAKANT RAMACHANDRA JADHAVMANGALNATH DEVELOPERS PVT LTD28/06/2025
CC12504426Rekha JaiswarMANGALNATH DEVELOPERS PVT LTD12/12/2025
CC12600010VAIBHAV DILIP KHADEMANGALNATH DEVELOPERS PVT LTD01/01/2026
CC12602722Ajay GuptaMANGALNATH DEVELOPERS PVT LTD10/05/2026
CC12602498Sharda Rohit KandwalMANGALNATH DEVELOPERS PVT LTD29/04/2026
CC12603760Rekha JaiswarMANGALNATH DEVELOPERS PVT LTD18/06/2026
CC12604134Vaibhav Dilip KhadeMANGALNATH DEVELOPERS PVT LTD02/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 May 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 18 Sep 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 31 Jan 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Oct 2026

Documents filed118

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Safal Saimay 2026.pdf27 Jun 2026
Withdrawal Update Form 2File: Form 2 Safal Sai.pdf27 Jun 2026
Withdrawal Update Form 3File: FORM 3 May 2026.pdf27 Jun 2026
Withdrawal Update Form 1File: FORM 1 MAR 2026.pdf28 May 2026
Withdrawal Update Form 2File: FROM 2 MAR 2026.pdf28 May 2026
Withdrawal Update Form 3File: FORM 3 MAR 2026 (2).pdf28 May 2026
Form 2A (FY 2025-2026)File: FROM 2 A.pdf28 Apr 2026
Form 5 (FY 2025-2026)File: FROM 5 MAR 2026.pdf28 Apr 2026
Commencement certificateFile: SAFAL SAI CC.pdf31 Jan 2026
Commencement certificateFile: sainth cc new.pdf31 Jan 2026
Withdrawal Update Form 1File: SAFAL SAI FORM 1 JULY TO SEPT 2025.pdf31 Jan 2026
Withdrawal Update Form 1File: SAFAL SAI FORM 1 OCT TO DEC 2025.pdf31 Jan 2026
Withdrawal Update Form 2File: SAFAL SAI FORM 2 JULY TO SEPT 2025.pdf31 Jan 2026
Withdrawal Update Form 2File: SAFAL SAI FORM 2 OCT TO DEC 2025.pdf31 Jan 2026
Withdrawal Update Form 3File: SAFAL SAI FORM 3 JULY TO SEPT 2025.pdf31 Jan 2026
Withdrawal Update Form 3File: SAFAL SAI FORM 3 OCT TO DEC 2025.pdf31 Jan 2026
Withdrawal Update Form 1File: SAFAL SAI FORM 1 APR TO JUNE 2025.pdf30 Jan 2026
Withdrawal Update Form 2File: SAFAL SAI FORM 2 APR TO JUNE 2025.pdf30 Jan 2026
Withdrawal Update Form 3File: SAFAL SAI FORM 3 APR TO JUNE 2025.pdf30 Jan 2026
Declaration in FORM BFile: FORM B SAI DEC 2025.pdf4 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAI FORM 1 MARCH 2025.pdf2 May 2025
Certificates of CA (Form 3)File: SAI FORM 3 MARCH 2025.pdf2 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: SAI FORM 2 MARCH 2025.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: sai inventory dec 2024.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: sai iventory mar 2025.pdf2 May 2025
Disclosure of Interest in Other Real Estate OrganizationsFile: disclosure on int sai.pdf2 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 5 SAI 24 25.pdf2 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 5 SAI 24 25.pdf2 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SAI 24 25.pdf2 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Safal Sai Form 1 DEC 2024.pdf1 Feb 2025
Certificates of CA (Form 3)File: FORM 3 SAI SAINATH dec 2024.pdf1 Feb 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Safal Sai Form 2 DEC 2024.pdf1 Feb 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: SAI FORM 1SEPT 2024.pdf9 Jan 2025
Certificates of CA (Form 3)File: SAI FORM 3 SEPT 2024.pdf9 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Safal Sai Form 2 SEPT 2024.pdf9 Jan 2025
Declaration about all RERA Designated Bank Accounts (Format A)File: FORMAT A SAI DESIGNATED BANK AC.pdf28 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 SAI 2023 -2024.pdf28 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: SAI FORM 2A 23-24.pdf14 Oct 2024
Declaration in FORM BFile: FORM B (MDPVT).pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 MARCH 2024.pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FROM 1 JUNE 2024.pdf7 Oct 2024
Certificates of CA (Form 3)File: FORM 3 MARCH 2024 MD.pdf7 Oct 2024
Certificates of CA (Form 3)File: FORM 3 JUNE 2024 MD.pdf7 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 JUNE 2024.pdf7 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 MARCH 2024.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: SAI DISCLOSURE OF INVENTORY MARCH 2024.pdf7 Oct 2024
CERSAI detailsFile: CERSAI REPORT SAI.pdf7 Oct 2024
Form 1File: FORM 1 MARCH 2024.pdf4 Oct 2024
Form 2File: FORM 2 MARCH 2024.pdf4 Oct 2024
Form 3File: FORM 3 MARCH 2024.pdf4 Oct 2024
Disclosure of Sold and Booked InventoryFile: SAI DISCLOSURE OF INVENTORY MARCH 2024.pdf4 Oct 2024
Self-declaration of Quarterly ProgressFile: SAI & SAINATH PROGRESS REPORT MARCH 2024.pdf4 Oct 2024
Form 1File: SAI & SAINATH PROGRESS REPORT MARCH 2024.pdf4 Oct 2024
Form 2File: SAI DISCLOSURE OF INVENTORY MARCH 2024.pdf4 Oct 2024
Form 3File: FORM 3 MARCH 2024.pdf4 Oct 2024
Disclosure of Sold and Booked InventoryFile: FORM 1 MARCH 2024.pdf4 Oct 2024
Self-declaration of Quarterly ProgressFile: FORM 2 MARCH 2024.pdf4 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 SAI 31ST DEC 2023.pdf28 Mar 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 SAI DEC 2023.pdf28 Mar 2024
Certificates of CA (Form 3)File: FORM 3 SAI 31ST DEC 2023.pdf28 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: sai cc.pdf20 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: sai CC Revalidation.pdf20 Dec 2023
Declaration in FORM BFile: MANGALNATH FORM B.pdf20 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: 2019-2020.pdf20 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2020-2021.pdf20 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2021-2022.pdf20 Dec 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2022-2023.pdf20 Dec 2023
Disclosure of sold/ booked inventoryFile: SAI DISCLOSURE OF INVENTORY.pdf20 Dec 2023
Disclosure of sold/ booked inventoryFile: SAI DISCLOSURE INVENTORY.pdf20 Dec 2023
Disclosure of sold/ booked inventoryFile: SAINATH DISCLOSURE INVENTORY.pdf20 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30TH JUNE 2023.pdf12 Dec 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 30TH SEPT 2023.pdf12 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30TH JUNE 2023.pdf12 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 30TH SEPT 2023.pdf12 Dec 2023
Certificates of CA (Form 3)File: FORM 3 30TH JUNE 2023 C.pdf12 Dec 2023
Certificates of CA (Form 3)File: FORM 3 30TH SEPT 2023C.pdf12 Dec 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FROM 2022 TO 2023.pdf30 Oct 2023
Commencement Certificates / NA Order for plotted developmentFile: Rehab 1 CC SAINATH.pdf5 Oct 2023
Building plan approvalFile: SAFAL SAINATH IOA UPDATED.pdf18 Sep 2023
Building Plan Approval (IOD)File: SAFAL SAINATH IOA UPDATED.pdf18 Sep 2023

How this compares with Mumbai Suburban

73%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 34 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SAFAL SAI AND SAFAL SAINATH on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KELKARWADI6,700+ in Mumbai Suburban

2 kmSAFAL SAI AND SAFAL SAINCompleted 120Lapsed / revoked 90Other 110Dot size: filed unitsN

Filed coordinates, straight-line distance. 320 registered projects within 2 km.

Builder: MANGALNATH DEVELOPERS PVT LTD

MANGALNATH DEVELOPERS PVT LTD has 2 registrations on MahaRERA, including SAFAL SAI AND SAFAL SAINATH and SAFAL GOLF RESIDENCES. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if SAFAL SAI AND SAFAL SAINATH is delayed beyond 31 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SAFAL SAI AND SAFAL SAINATH?

The registered promoter entity is MANGALNATH DEVELOPERS PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SAFAL SAI AND SAFAL SAINATH?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SAFAL SAI AND SAFAL SAINATH?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SAFAL SAI AND SAFAL SAINATH?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SAFAL SAI AND SAFAL SAINATH?

The professionals named in the filing: Architect: CONSULTANTS COMBINED ARCHITECTS; Engineer: VIJAY NARANG; Chartered Accountant: BANWAT & CO; Chartered Accountant: P.C.DHOLAKIA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SAFAL SAI AND SAFAL SAINATH?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SAFAL SAI AND SAFAL SAINATH. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SAFAL SAI AND SAFAL SAINATH to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.