Home / Browse projects / Pune, Maharashtra / SADHGURU HOMES

Registered No litigation declared Residential / Group Housing project

SADHGURU HOMES

By ASHOK MOTIRAM TARAS

RG-MH-47870 · RERA P52100052586 · Last updated on MahaRERA portal: 15 Jul 2026

Source: official MahaRERA filing

Red flags

  • Possession 1 months past the filed date
  • Completion date moved by 9 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
9 of 11Construction stages donefurthest along: Basement (if any), 0%
8 of 23Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 67 documents Report an error

SADHGURU HOMES is a Residential / Group Housing project by ASHOK MOTIRAM TARAS in Pune, Maharashtra, registered with MahaRERA as P52100052586 on 11 Sep 2023. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 9 months from the original filing. 15 of the 23 units on this registration are recorded sold or booked, and 9 of 11 construction stages are filed complete.

At a glance

Project

  • NameSADHGURU HOMES
  • TypeResidential / Group Housing
  • Location
    • NEAR LEKHA FRAM
    • KIWALE
    • Kivale
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100052586
  • ReraGenie IDRG-MH-47870

Builder

  • NameASHOK MOTIRAM TARAS
  • Entity typeIndividual

Key dates

1 months past promisethis monthRegisteredSep 2023First promiseDec 2025Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed67 files

Current status

65%15 of 23 units booked
99.4%Work done, per cost certificate

Figures as on 15 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING - ANA7623023

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 15 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

9 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

BUILDING - A: 82% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 15 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed42

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots42
Closed/Covered25
Open Space17

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area582 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Dec 2025

Approvals and building plan

Sanctioning authorityPimpri-Chinchwad Municipal Corporation
Permissible FSI1955.2
Proposed, not sanctioned1,954 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchRAVET
Estimated costRs 4.99 cr
Cost incurredRs 4.96 cr
Work done99.4%
BuildingWingEstimatedIncurred
BUILDING - ANARs 4.71 crRs 4.71 cr
-NARs 28.57 lakhRs 25.58 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAMMEYA ENTERPRISES
EngineerRAVINDRA A. KARNAVAT
EngineerSHRIKANT MADANRAO AMBHURE
Chartered AccountantVINIT D ACHHA AND ASSOCIATES
Chartered AccountantSHUBHAM SANJAY BORA
Chartered AccountantDYANESHWAR GOPALE AND CO
Chartered AccountantSharma Jadhav and co
PartnerRole in project
ASHOK MOTIRAM TARAS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA17122518726Dec 2025 → Sep 2026

Reason as filed by the promoterOur project is more than 90% complete in terms of construction activity. We had applied to the municipal corporation for various NOCs to obtain the completion certificate, but due to the local corporation elections, we doubt that we will be able to obtain the completion certificate by December 31, 2025. Therefore, we are submitting this application for an extension of the deadline.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Mar 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 15 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed67

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 30062026.pdf15 Jul 2026
Withdrawal Update Form 2File: Form 2 30062026.pdf15 Jul 2026
Withdrawal Update Form 3File: Form 3 30062026.pdf15 Jul 2026
Form 5 (FY 2025-2026)File: Form 5 25-26.pdf27 Jun 2026
Withdrawal Update Form 1File: Form 1.pdf16 Apr 2026
Withdrawal Update Form 2File: Form 2.pdf16 Apr 2026
Withdrawal Update Form 3File: Form 3.pdf16 Apr 2026
Layout approvalFile: Layout Plan.pdf9 Mar 2026
Withdrawal Update Form 1File: Form 1.pdf20 Jan 2026
Withdrawal Update Form 2File: Form 2.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 scan.pdf17 Dec 2025
Withdrawal Update Form 2File: Sadguru homes Form 2.pdf17 Dec 2025
Withdrawal Update Form 3File: Form 3.pdf17 Dec 2025
Form 1File: Form 1 scan.pdf17 Oct 2025
Form 2File: Form 2 scan.pdf17 Oct 2025
Form 3File: Form 3.pdf17 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf17 Oct 2025
Form 1File: Form 1.pdf21 Jul 2025
Form 2File: Form 2.pdf21 Jul 2025
Form 3File: Form 3.pdf21 Jul 2025
Disclosure of Sold and Booked InventoryFile: Sold Unsold.pdf21 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf17 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf17 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf17 Apr 2025
Building plan approvalFile: imgw-410134852_organized.pdf15 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 20250410054521_organized.pdf15 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: imgw-410134852_organized.pdf15 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F- 1.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F - 3.pdf20 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F - 2.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sadguru homes Form 2.pdf15 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sadguru homes Form 1.pdf14 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: sadguru homes Form 3.pdf14 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf20 Jan 2024
Proforma of Agreement for saleFile: FORMATE OF RERA AGREEMENT OF ASHOK TARAS FINAL.pdf30 Aug 2023
Copy of the legal title reportFile: Legal Search 23-08-2023.pdf23 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sadhguru Homes Form 3.pdf14 Aug 2023
Details of encumbrances concerned to FinanceFile: No Enc Finance.pdf31 Jul 2023
Details of encumbrances concerned to FinanceFile: NO ENC LEGAL.pdf31 Jul 2023
Details of encumbrances concerned to LegalFile: No Enc Finance.pdf31 Jul 2023
Details of encumbrances concerned to LegalFile: NO ENC LEGAL.pdf31 Jul 2023
Declaration about Commencement CertificateFile: C C DEC.pdf31 Jul 2023
Declaration in FORM BFile: Form B.pdf31 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf31 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf31 Jul 2023
CERSAI detailsFile: Cersai Undertaking.pdf31 Jul 2023
Disclosure of sold/ booked inventoryFile: Inventory.pdf31 Jul 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Other Real Eastate.pdf31 Jul 2023
Proforma of Allotment letterFile: AL.pdf31 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf31 Jul 2023
Deviation Report with respect to Allotment letterFile: No Dev AL.pdf31 Jul 2023
Deviation Report with respect to model copy of AgreementFile: No Dev AFS.pdf31 Jul 2023
Layout approvalFile: Sanction Plan.pdf30 Jul 2023
Building plan approvalFile: Sanction Plan.pdf30 Jul 2023
PAN CardFile: Ashok Taras Pan.pdf30 Jul 2023
Copy of Layout Approval (in case of layout)File: Sanction Plan.pdf30 Jul 2023
Building Plan Approval / NA Order for plotted developmentFile: Sanction Plan.pdf30 Jul 2023
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf30 Jul 2023

How this compares with Pune

65%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 9 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SADHGURU HOMES on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KIWALE13,700+ in Pune

2 kmSADHGURU HOMESCompleted 76Lapsed / revoked 47Other 99Dot size: filed unitsN

Filed coordinates, straight-line distance. 222 registered projects within 2 km.

Builder: ASHOK MOTIRAM TARAS

ASHOK MOTIRAM TARAS has 1 registration on MahaRERA, including SADHGURU HOMES. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SADHGURU HOMES is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SADHGURU HOMES?

The registered promoter entity is ASHOK MOTIRAM TARAS, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SADHGURU HOMES?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for SADHGURU HOMES?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SADHGURU HOMES?

The professionals named in the filing: Architect: AMMEYA ENTERPRISES; Engineer: RAVINDRA A. KARNAVAT; Engineer: SHRIKANT MADANRAO AMBHURE; Chartered Accountant: VINIT D ACHHA AND ASSOCIATES; Chartered Accountant: SHUBHAM SANJAY BORA; Chartered Accountant: DYANESHWAR GOPALE AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SADHGURU HOMES?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SADHGURU HOMES. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SADHGURU HOMES to a free account