Home / Browse projects / AAYESHA PALACE

Registered No litigation declared Residential / Group Housing project

AAYESHA PALACE

By ZOEB ENTERPRISES

RG-MH-21801 · RERA P51900023852 · Last updated on MahaRERA portal: 30 Apr 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 48 months
  • 3 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2027Possession promisedmoved 48 months from the original
7 of 11Construction stages donefurthest along: Sanitary Fittings within the flats /..., 95%
149 of 162Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 185 documents Report an error

AAYESHA PALACE is a Residential / Group Housing project by ZOEB ENTERPRISES in PAREL, 400012, registered with MahaRERA as P51900023852 on 7 Jan 2020. Possession is promised by 31 Dec 2027. The completion date has moved by 48 months from the original filing. 13 of the 162 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameAAYESHA PALACE
  • TypeResidential / Group Housing
  • Location
    • ADAM MISTRY LANE
    • PAREL
    • 400012
  • Pincode400012
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900023852
  • ReraGenie IDRG-MH-21801

Builder

  • NameZOEB ENTERPRISES
  • Entity typePartnership
  • PartnerRUBINA MOHD ASLAM ANSARI

Key dates

this monthRegisteredJan 2020First promiseDec 2023Revised toDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on7 Jan 2020
  • Promised completion31 Dec 2027
  • Revised completionRevised to 31 Dec 2027 (originally 30 Dec 2023)
  • Buildings1 building record
  • Documents filed185 files

Current status

8%13 of 162 units booked
96.6%Work done, per cost certificate

Figures as on 30 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
AAYESHA PALACENA23231620162

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Sanitary Fittings within the flats / premises, at 95%.

AAYESHA PALACE: 98% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 30 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes100%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area769 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
Declared on14 May 2025

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI5865.64
Proposed, not sanctioned5,866 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMUMBAI CENTRAL, MUMBAI
Estimated costRs 27.00 cr
Cost incurredRs 26.09 cr
Work done96.63%
BuildingWingEstimatedIncurred
AAYESHA PALACENARs 27.00 crRs 26.09 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectQURESHI AND ASSOCIATES
EngineerZZ CONSULTANT
EngineerMohammed Monis Ansari
Chartered AccountantSHAFI AHMED SIDDIQUI
Chartered AccountantMEHJABEEN NADEEM BAMNE
Chartered AccountantABDUL HALIM SIDDIQUI
PartnerRole in project
ZOEB ENTERPRISES-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900018767Dec 2023 → Dec 2024

Reason as filed by the promoterProject CC for Approved number of Floors from 17th to 22nd on 13-11-2022. Therefore, the time for Constructing the additional 5 Floors is taking time. There is delay on part of MCGM to issue CC on time.

EXT51900027276Dec 2023 → Dec 2025

Reason as filed by the promoterDear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the full RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying

EA24022619992Dec 2023 → Dec 2027

Reason as filed by the promoterDear Sir/Ma’am, I, Mr. Mohammed Alam Abdul Majid Ansari, hereby declare the following with respect to the project “AAYESHA PALACE” bearing registration number P51900023852 registered under MahaRERA 1. Status of Work Completed: We are pleased to inform you that we have completed the 100% RCC (Reinforced Cement Concrete) work for the building. Currently, we are undertaking the finishing work, which includes plastering, flooring, electrical fittings, and other essential internal and external works. 2. Expected Timeline for Completion: We are committed to completing all balance works and applying

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000192528SHAKEEL AHMED MOHAMMED YUNUSZOEB ENTERPRISES10/02/2020
CC006000000397480Chirag GohilAAYESHA PALACE (Zoeb Enterprises)13/09/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 6 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 Oct 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed185

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 185 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Q4.pdf30 Apr 2026
Withdrawal Update Form 2File: Form 2 Q4.pdf30 Apr 2026
Withdrawal Update Form 3File: Form 3 25-26 Q3_11zon.pdf30 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf30 Apr 2026
Form 1File: Form 1 Q4 - 19-20.pdf25 Feb 2026
Form 2File: Form 2 Q4 - 19-20.pdf25 Feb 2026
Form 3File: Form 3 19-20 Q4.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 19-20 Q4.pdf25 Feb 2026
OthersFile: Form 2A 19-20.pdf25 Feb 2026
Form 1File: Form 1 Q1 - 20-21.pdf25 Feb 2026
Form 2File: Form 2 Q1 - 20-21.pdf25 Feb 2026
Form 3File: Form 3 Q1 - 20-21.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 20-21 Q1.pdf25 Feb 2026
Form 1File: Form 1 Q2 - 20-21.pdf25 Feb 2026
Form 2File: Form 2 Q2 - 20-21.pdf25 Feb 2026
Form 3File: Form 3 Q2 - 20-21.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 20-21 Q2.pdf25 Feb 2026
Form 1File: Form 1 Q3 - 20-21.pdf25 Feb 2026
Form 2File: Form 2 Q3 - 20-21.pdf25 Feb 2026
Form 3File: Form 3 Q3 - 20-21.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 20-21 Q3.pdf25 Feb 2026
Form 1File: Form 1 Q4 - 20-21.pdf25 Feb 2026
Form 2File: Form 2 Q4 - 20-21.pdf25 Feb 2026
Form 3File: Form 3 Q4 - 20-21.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 20-21 Q4.pdf25 Feb 2026
OthersFile: Form 2A 20-21.pdf25 Feb 2026
Form 1File: Form 1 Q1 - 21-22.pdf25 Feb 2026
Form 2File: Form 2 Q1 - 21-22.pdf25 Feb 2026
Form 3File: Form 3 Q1 - 21-22.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 21-22 Q1.pdf25 Feb 2026
Form 1File: Form 1 Q2 - 21-22.pdf25 Feb 2026
Form 2File: Form 2 Q2 - 21-22.pdf25 Feb 2026
Form 3File: Form 3 Q2 - 21-22.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 21-22 Q2.pdf25 Feb 2026
Form 1File: Form 1 Q3 - 21-22.pdf25 Feb 2026
Form 2File: Form 2 Q3 - 21-22.pdf25 Feb 2026
Form 3File: Form 3 Q3 - 21-22.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 21-22 Q3.pdf25 Feb 2026
Form 1File: Form 1 Q4 - 21-22.pdf25 Feb 2026
Form 2File: Form 2 Q4 - 21-22.pdf25 Feb 2026
Form 3File: Form 3 Q4 - 21-22.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 21-22 Q4.pdf25 Feb 2026
OthersFile: Form 2A 21-22.pdf25 Feb 2026
Form 1File: Form 1 Q1 - 22-23.pdf25 Feb 2026
Form 2File: Form 2 Q1 - 22-23.pdf25 Feb 2026
Form 3File: Form 3 Q1 - 22-23.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 22-23 Q1.pdf25 Feb 2026
Form 1File: Form 1 Q2 - 22-23.pdf25 Feb 2026
Form 2File: Form 2 Q2 - 22-23.pdf25 Feb 2026
Form 3File: Form 3 Q2 - 22-23.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 22-23 Q2.pdf25 Feb 2026
Form 1File: Form 1 Q3 - 22-23.pdf25 Feb 2026
Form 2File: Form 2 Q3 - 22-23.pdf25 Feb 2026
Form 3File: Form 3 Q3 - 22-23.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 22-23 Q3.pdf25 Feb 2026
Form 1File: Form 1 Q4 - 22-23.pdf25 Feb 2026
Form 2File: Form 2 Q4 - 22-23.pdf25 Feb 2026
Form 3File: Form 3 Q4 - 22-23.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 22-23 Q4.pdf25 Feb 2026
OthersFile: Form 2A 22-23.pdf25 Feb 2026
Form 1File: Form 1 Q1 - 23-24.pdf25 Feb 2026
Form 2File: Form 2 Q1 - 23-24.pdf25 Feb 2026
Form 3File: Form 3 Q1 - 23-24.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 23-24 Q1.pdf25 Feb 2026
Form 1File: Form 1 Q2 - 23-24.pdf25 Feb 2026
Form 2File: Form 2 Q2 - 23-24.pdf25 Feb 2026
Form 3File: Form 3 Q2 - 23-24.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 23-24 Q2.pdf25 Feb 2026
Form 1File: Form 1 Q3 - 23-24.pdf25 Feb 2026
Form 2File: Form 2 Q3 - 23-24.pdf25 Feb 2026
Form 3File: Form 3 Q3 - 23-24.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 23-24 Q3.pdf25 Feb 2026
Form 1File: Form 1 Q4 - 23-24.pdf25 Feb 2026
Form 2File: Form 2 Q4 - 23-24.pdf25 Feb 2026
Form 3File: Form 3 Q4 - 23-24.pdf25 Feb 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold 23-24 Q4.pdf25 Feb 2026
OthersFile: Form 2A 23-24.pdf25 Feb 2026
Form 1File: Form 1 Q1 - 24-25.pdf25 Feb 2026
Form 2File: Form 2 Q1 - 24-25.pdf25 Feb 2026
Form 3File: Form 3 Q1 - 24-25.pdf25 Feb 2026

Keep AAYESHA PALACE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PAREL

2 kmAAYESHA PALACECompleted 28Lapsed / revoked 13Other 12Dot size: filed unitsN

Filed coordinates, straight-line distance. 53 registered projects within 2 km.

Builder: ZOEB ENTERPRISES

ZOEB ENTERPRISES has 1 registration on MahaRERA, including AAYESHA PALACE. Its filings disclose no earlier MahaRERA projects. Read the full track record.

Frequently asked questions

What are my rights if AAYESHA PALACE is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of AAYESHA PALACE?

The registered promoter entity is ZOEB ENTERPRISES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in AAYESHA PALACE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against AAYESHA PALACE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for AAYESHA PALACE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at AAYESHA PALACE?

The professionals named in the filing: Architect: QURESHI AND ASSOCIATES; Engineer: ZZ CONSULTANT; Engineer: Mohammed Monis Ansari; Chartered Accountant: SHAFI AHMED SIDDIQUI; Chartered Accountant: MEHJABEEN NADEEM BAMNE; Chartered Accountant: ABDUL HALIM SIDDIQUI. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in AAYESHA PALACE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About AAYESHA PALACE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save AAYESHA PALACE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.