Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Litigation declared, 4 cases
- 8 complaints at MahaRERA
- Completion date moved by 78 months
- 5 extensions taken
Clear
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Ruparel Iris is a Others project by Ruparel Estates India Pvt Ltd in Mumbai City, Maharashtra, registered with MahaRERA as P51900005988 on 14 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 78 months from the original filing. 30 of the 98 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 8 complaints are on record with the regulator.
At a glance
Project
- NameRuparel Iris
- TypeOthers
- Location
- Senapati Bapat Marg
- Mahim
- Mumbai City
- 400016
- Pincode400016
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900005988
- ReraGenie IDRG-MH-09098
Builder
- NameRuparel Estates India Pvt Ltd
- Entity typeCompany
- DirectorAmit Ruparel
- Other registrations1 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on14 Aug 2017
- Promised completion30 Jun 2026
- Revised completionRevised to 30 Jun 2026 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed87 files
Current status
Figures as on 4 Feb 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Ruparel Iris | NA | 46 | 44 | 73 | 25 | 98 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 4 Feb 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 90%.
Ruparel Iris: 84% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 90% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 90% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Progress on shared amenities15
As on 4 Feb 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 90% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 75% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed112
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Ruparel Iris | NA | Rs 498.27 cr | Rs 483.95 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Mr Rahul Kamathi Kamathi |
| Engineer | Sanjeev Sinha |
| Engineer | Ajay Gade |
| Chartered Accountant | Sarveshwar Sharma |
| Chartered Accountant | Shereena Jacob |
| Partner | Role in project |
|---|---|
| Ruparel Estates India Pvt Ltd | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterWe would like to apply for extension for our project “Ruparel Iris” vide RERA Regn. No.: P51900005988 as it has been delayed. The reason for delay has been explained below. The project “Ruparel Iris” comprise of single composite building with Rehab, commercial, residential sale units. The project is a high rise building with over 35 storeys and car parking tower. The project commenced in 2013 with first plinth CC being issued on October 8, 2013. We had applied for NOC from Civil Aviation Department for the building height of 153.758 ASMLin November 2017. The project received the height clearan
Reason as filed by the promoterdue to delay in getting approval from authorities; though we have applied for further height approvals in 2017 and the same height approval has been reflected in the draft GSR 365(E) dated 12th April, 2018. However, the final amendment is still not published as of date due to delay in the process
Reason as filed by the promoterApproval from Airport authority of India is pending for height due to which project is got delayed.
Reason as filed by the promoterWe would like to apply for extension for our project “Ruparel Iris” vide RERA Regn. No.: P51900005988 as it has been delayed. The reason for delay has been explained below. The project “Ruparel Iris” comprise of single composite building with Rehab, commercial, residential sale units. The project is a high rise building with over 35 storeys and car parking tower. The project commenced in 2013 with first plinth CC being issued on October 8, 2013. We had applied for NOC from Civil Aviation Department for the building height of 153.758 ASML in November 2017. The project received the height cleara
Reason as filed by the promoterThe project has encountered considerable delays primarily due to prolonged approval processes and height restrictions imposed by regulatory authorities. Height Restrictions and NOC Delays: The process began in November 2015, when we applied for a No Objection Certificate (NOC) from the Civil Aviation Department for a proposed building height of 134.70 meters ASML. On April 21, 2016, an initial clearance of 112.94 meters ASML was granted. Subsequently, in October 2017, we appealed to the Appellate Committee, Ministry of Civil Aviation (Letter No. IRIS/CA/2017/02 dated 05.10.2017) seeking permis
Litigation declared4
| Case | Court | Status |
|---|---|---|
| 775/2015 | High Court | For hearing of notice of motion |
| 776/2015 | High Court | For hearing of notice of motion |
| 602/2015 | High Court | For hearing of notice of motion |
| 608/2015 | High Court | For hearing of notice of motion |
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000012120 | Mrs. Milan Narendra Patkar | M/s. Ruparel Estate Private Limited | 02/12/2017 |
| CC006000000198241 | Mrs Parul Vedpathak and Mr Rahul Vedpathak | M/s Ruparel Estate India Pvt Ltd | 07/09/2021 |
| CC006000000231173 | Nitin ANANT KSHIRSAGAR | Ruparel Estates India Pvt. Ltd. | 17/05/2022 |
| CC006000000408582 | Kaykasshan Areef Patel | M/s Ruparel Estates (I) Private Limited | 27/12/2023 |
| CC006000000408583 | Kaykasshan Areef Patel | M/s Ruparel Estates (I) Private Limited | 27/12/2023 |
| CC006000000428751 | Kaykasshan Areef Patel | M/s Ruparel Estates (I) Private Limited | 06/01/2024 |
| CC12503731 | Priyanka Jha | Ruparel Estates India Pvt Ltd | 23/10/2025 |
| CC12603934 | Amit Indrajit Sheth | Ruparel Estates India Pvt Ltd | 25/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 28 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 4 Feb 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 4 Feb 2026 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 4 Feb 2026Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed87
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 87 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: Ruparel IRIS Layout Approval.pdf | 4 Feb 2026 |
| Building plan approvalFile: Ruparel IRIS Building Plan Approval.pdf | 4 Feb 2026 |
| Commencement certificateFile: Ruparel IRIS Revalidated Commencement Certificate.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Ruparel IRIS 30092025.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Ruparel IRIS 30092025 Signed.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Ruparel IRIS 30092025 Signed.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Ruparel IRIS 30092025 Signed.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Ruparel IRIS 30092025 Signed.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Ruparel IRIS 30092025.pdf | 3 Feb 2026 |
| Withdrawal Update Form 2File: Form 2 Ruparel IRIS 30092025.pdf | 3 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 Ruparel IRIS 30092025 Signed.pdf | 3 Feb 2026 |
| Withdrawal Update Form 1File: Form 1 Ruparel IRIS 30092025.pdf | 22 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 Ruparel IRIS 30092025.pdf | 22 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 Ruparel IRIS 30092025 Signed.pdf | 22 Oct 2025 |
| Withdrawal Update Form 1File: Iris.pdf | 14 Oct 2025 |
| Withdrawal Update Form 2File: EC IRIS.pdf | 14 Oct 2025 |
| Withdrawal Update Form 3File: IRIS CA.pdf | 14 Oct 2025 |
| Form 2A (FY 2022-2023)File: Form 2A FY 2022-23.pdf | 14 Oct 2025 |
| Form 2A (FY 2023-2024)File: Form 2A FY 2023-24.pdf | 14 Oct 2025 |
| Form 2A (FY 2017-2018)File: Form 2A FY 2017-18.pdf | 14 Oct 2025 |
| Form 2A (FY 2018-2019)File: Form 2A FY 2018-19.pdf | 14 Oct 2025 |
| Form 2A (FY 2019-2020)File: Iris March-2020.pdf | 14 Oct 2025 |
| Form 2A (FY 2020-2021)File: Iris March-2021.pdf | 14 Oct 2025 |
| Form 5 (FY 2017-2018)File: Ruparel IRIS Certificates of CA (Form 5) (FY 2017-18).pdf | 14 Oct 2025 |
| Form 2A (FY 2021-2022)File: IRIS_Form 2A_FY 21-22.pdf | 13 Oct 2025 |
| Form 5 (FY 2018-2019)File: Form 5 Ruparel IRIS FY 2018 19.pdf | 13 Oct 2025 |
| Form 5 (FY 2022-2023)File: Ruparel IRIS Form 5 FY 2022-23 Final.pdf | 13 Oct 2025 |
| Form 5 (FY 2023-2024)File: Ruparel IRIS Form 5 FY 2023-24 Final.pdf | 13 Oct 2025 |
| Form 5 (FY 2019-2020)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20).pdf | 13 Oct 2025 |
| Form 5 (FY 2020-2021)File: Form 5 FY 20-21.pdf | 13 Oct 2025 |
| Form 5 (FY 2021-2022)File: 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22).pdf | 13 Oct 2025 |
| Disclosure of sold/ booked inventoryFile: Ruparel IRIS Sold Unsold Inventory 17102024.pdf | 5 Nov 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A Declaration about RERA Designated Bank Accounts Iris.pdf | 5 Nov 2024 |
| Other - TechnicalFile: PERT CPM Analyis Ruparel IRIS.pdf | 5 Nov 2024 |
| Other - TechnicalFile: Extension Application Letter Final.pdf | 5 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 2022-23.pdf | 5 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A FY 2022-23.pdf | 5 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 2023-24.pdf | 5 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 2023-24.pdf | 5 Nov 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A FY 2023-24.pdf | 5 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ruparel IRIS 16102024.pdf | 4 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Ruparel IRIS Sold Unsold Inventory 17102024.pdf | 4 Nov 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Ruparel IRIS Form 5 FY 2022-23 Final.pdf | 29 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Ruparel IRIS Form 5 FY 2023-24 Final.pdf | 29 Oct 2024 |
| Certificates of CA (Form 3)File: IRIS_Form3_Sep24_Final.pdf | 17 Oct 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Sec Unsec Finance.pdf | 17 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: 1 Legal Financial Encumbrance_Iris.pdf | 16 Oct 2024 |
| Declaration in FORM BFile: Form B - Affidavit cum declaration - Iris - Extension upto 30 06 25.pdf | 16 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2 Ruparel IRIS.pdf | 16 Oct 2024 |
| Details of encumbrances concerned to LegalFile: 1 Legal Financial Encumbrance_Iris.pdf | 16 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Ruparel IRIS 2022-23 Sanjeev Sinha.pdf | 16 Oct 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A Ruparel IRIS 2023-24 Sanjeev Sinha.pdf | 16 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1-Architect Certificate-Iris.pdf | 15 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Engineers Certificate-Iris.pdf | 15 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD BOOKED INVENTORY - IRIS.pdf | 17 Jun 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A Disclosure of Interest - IRIS.pdf | 17 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Iris 2A_FY 2019-20.pdf | 14 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: IRIS_Form 2A_FY 21-22.pdf | 14 Jun 2023 |
| CERSAI detailsFile: Cersai Report IRIS.pdf | 13 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: IRIS_Form5_FY21-22.pdf | 13 Jun 2023 |
| Declaration about Commencement CertificateFile: Iris Form-D.pdf | 27 Jul 2021 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Iris 2A June 21.pdf | 27 Jul 2021 |
| Disclosure of sold/ booked inventoryFile: Iris Sold-Unsold.pdf | 27 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: IRIS.pdf | 27 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: IRIS FY 20-21.pdf | 27 Jul 2021 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Iris.pdf | 2 Jan 2020 |
| Certificates of CA (Form 5)File: IRIS.pdf | 31 Dec 2018 |
| Layout approvalFile: IRIS Layout PLan.pdf | 29 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: IRIS Layout PLan.pdf | 29 Jul 2017 |
| Certificates of CA (Form 3)File: IRIS CA.pdf | 29 Jul 2017 |
| PAN CardFile: REIPL PAN.pdf | 28 Jul 2017 |
| Copy of the legal title reportFile: Title Certificate.pdf | 28 Jul 2017 |
| Details of encumbrancesFile: REIPL.pdf | 28 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 87 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Ruparel Iris on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mahim780+ in Mumbai City
Filed coordinates, straight-line distance. 197 registered projects within 2 km.
Island Cove
LH Residential Housing Private Limited
Midtown Bay
Rising Sun Impex Private Limited
Island Cove Tower 4
LH Residential Housing Private Limited, Sh
Bayline Residences
HRUB Infra Projects Pvt Ltd
VITALIS
SURAJ ESTATE DEVELOPERS LTD
Suraj One Business Bay
ICONIC PROPERTY DEVELOPERS PVT LTD
See every Mumbai City project, with the district possession charts
Builder: Ruparel Estates India Pvt Ltd
Ruparel Estates India Pvt Ltd has 2 registrations on MahaRERA, including Ruparel Iris and Shaanti Ashish. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What does it mean that Ruparel Iris shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Ruparel Iris is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Ruparel Iris?
The registered promoter entity is Ruparel Estates India Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Ruparel Iris?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Ruparel Iris?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Ruparel Iris?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Ruparel Iris?
The professionals named in the filing: Architect: Mr Rahul Kamathi Kamathi; Engineer: Sanjeev Sinha; Engineer: Ajay Gade; Chartered Accountant: Sarveshwar Sharma; Chartered Accountant: Shereena Jacob. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Ruparel Iris?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback