Runwal Shopping Arcade

By Runwal Residency Private Limited

RG-MH-28520 · RERA P51700026438 · Last updated on MahaRERA portal: 23 Apr 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken
  • Rs 790.00 crore secured on the land, in favour of Indusind Bank Ltd

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Apr 2025Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
1Complaints at MahaRERAon this registration
Jump to the 103 documents Report an error

Runwal Shopping Arcade is a Commercial project by Runwal Residency Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700026438 on 22 Sep 2020. The registration is recorded completed; possession was promised by 30 Apr 2025. The completion date has moved by 12 months from the original filing. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRunwal Shopping Arcade
  • TypeCommercial
  • Location
    • Village Gharivali usarghar and Sagoan
    • Dombivli
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700026438
  • ReraGenie IDRG-MH-28520

Builder

  • NameRunwal Residency Private Limited
  • Entity typeCompany
  • CINU45400MH2011PTC212140
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsVijay Kisan Patil, Lucy Roychoudhury
  • Other registrations17 more →
  • Completed3 of 18
  • No longer live5 lapsed, de-registered or revoked

Key dates

this monthRegisteredSep 2020First promiseApr 2024Revised toApr 2025Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Sep 2020
  • Promised completion30 Apr 2025
  • Revised completionRevised to 30 Apr 2025 (originally 30 Apr 2024)
  • Buildings1 building record
  • Documents filed103 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Shopping Arcade also known as R GalleriaNA40000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Shopping Arcade also known as R Galleria: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes80%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed234

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots234
Closed/Covered234

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area6,730 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofIndusind Bank Ltd
Secured amountRs 790.00 crore
CERSAI search filedYes
Declared on2 Oct 2024

Approvals and building plan

Sanctioning authorityMMRDA
Permissible FSI18225.22
Proposed, not sanctioned16,225 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGORUND FLOOR, MTNL TELEPHONE EXCHANGE BUILDING OPP MATUNGA POLICE STATION MUMBAI - 400019

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. Sandeep Prabhu for SAAKAAR
ArchitectSaakar Architects
ArchitectSakar Architects
EngineerChetan Sampat
EngineerUttam Kawathankar
EngineerSHAILESH MAHIMTURA
Chartered AccountantBhatter & Company Chartered Accountants
Chartered Accountantkshirsagar and associates
Chartered AccountantM.B. Agrawal & Co.
PartnerRole in project
Runwal Residency Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700019573Apr 2024 → Apr 2025

Reason as filed by the promoter1. I, Mr. Saurabh Natu duly authorised by Runwal Residency Private Limited, Promoter of the project “Runwal Shopping Arcade” (also known as R-Galleria) registered with MahaRERA under project registration number P51700026438 (hereinafter referred to as the “said Project”), here by state that the project registration validity of the said Project is due to expire on 30th April 2024. 2. I hereby state that the Runwal Shopping Arcade comprises of 353 shops, and we have already completed construction of the entire project in a timely manner. Out of those 353 shops, part occupation certificate for 76

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12501757AMOL HEMANT APTERunwal Residency Private Limited29/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 17 Oct 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Aug 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Apr 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 26 Feb 2025

Documents filed103

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 103 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: Runwal Shopping Arcade.pdf23 Apr 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Shopping Form 4 OC with marked plan_compressed.pdf26 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 SHOPPING ARCADE 09 Jan 25.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: Runwal Shopping Arcade.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Done Shopping Arcade RERA FORM 2 ENGINEERS CERTIIFICATE.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shopping Arcade done.pdf21 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 shopping.pdf14 Jan 2025
Status of Formation of Legal Entity (Society/Co Op etc.)File: RUNWAL SHOPPING ARACDE NAME RESERVATION.pdf6 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: shopping arcade oc_compressed.pdf4 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dombivli Shopping Arcade RERA FORM 2 ENGINEERS CERTIIFICATE 30-09-2024.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Shopping Arcade.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Runwal Shopping Arcade.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shopping Arcade.pdf18 Oct 2024
Disclosure of sold/ booked inventoryFile: Inventory Format Shopping Arcade.pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Shopping Arcade.pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shopping Arcade FORM 2.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shopping Arcade.pdf18 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22).pdf6 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM-2A-APRIL 2022 TO MARCH-2023.pdf6 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM-2A-APRIL 2023 TO MARCH-2024.pdf6 May 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory Details.pdf6 May 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Occupancy Certificate- Shopping Arcade.pdf6 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Shopping Arcade - March 24.pdf26 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shopping Arcade.pdf18 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shopping Arcade.pdf18 Apr 2024
Commencement Certificates / NA Order for plotted developmentFile: Amended CC for school 21082023.pdf10 Apr 2024
Declaration in FORM BFile: Form B for extension of Runwal Shopping Arcade.pdf10 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Shopping Arcade.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Shoping Arcade.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shopping Arcade.pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Arcade.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shopping Arcade.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arcade.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Runwal Shopping Arcade Form 5 FY 2022-23-min.pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Runwal Shopping Arcade Form 5 FY 2022-23-min.pdf30 Sep 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Shopping Arcade.pdf18 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 - Arcade.pdf21 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Arcade.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Shopping Arcade.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Shopping Arcade.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Shopping Arcade.pdf16 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 - Shopping Arcade.pdf16 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Runwal Gardens - Form 1 - Shop Arcade.pdf28 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3- SA.pdf22 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 SHOPPING ARCADE.pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: INVENTORY SHOPPING ARCADE_compressed.pdf21 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: F1 Architect Certificate Shopping arcade - 12-12-22.pdf10 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: F 2- Certificate of cost- Shopping arcade.pdf9 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: F 3 -CERTIFICATE OF FINANCIAL Shopping arcade.pdf9 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 SA.pdf30 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Shopping Arcade_compressed.pdf22 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Shopping Arcade.pdf22 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 RRPL SA_compressed (1).pdf22 Oct 2022
Other - FinanceFile: encrumbrance.pdf22 Sep 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 026438 arcade.pdf7 Jul 2022
Declaration about Commencement CertificateFile: DECLA SHOPPING.pdf4 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FROM5 26438 ARCADE 20-21.pdf4 May 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Quality Assurance 03-05-2022 arcade 21-22.pdf4 May 2022
Disclosure of sold/ booked inventoryFile: Runwal shopping Arcade 03-05-2022 inventory_11zon.pdf4 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 026438 arcade.pdf30 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Runwal Gardens Shopping Arcade.pdf21 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Shopping_Arcade 20-21.pdf19 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: R Gardens arcade jnaury 22.pdf3 Mar 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engi Certificate Of cost.pdf3 Mar 2022
Details of encumbrancesFile: LICHFL to RRPL_No Dues Certificate.pdf31 Jan 2022
Details of encumbrancesFile: Encumbrance Certificate - Phase 1 2A 2B and Arcade.pdf31 Jan 2022
CERSAI detailsFile: CERSAI_Ackn_Report_LIC.pdf31 Jan 2022
Details of encumbrancesFile: Encumbrance shopping arade.pdf23 Nov 2020
Proforma of Allotment letterFile: AFS.pdf5 Nov 2020
Copy of the legal title reportFile: Supplememtary Title Certificate 06102020.pdf17 Oct 2020
Commencement Certificates / NA Order for plotted developmentFile: CC 14102020.pdf14 Oct 2020
Proforma of Allotment letterFile: Allotment Letter andAFS arcade new.pdf19 Sep 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA certificate.pdf3 Sep 2020
Building plan approvalFile: MYSCAN_20200824_0001.pdf29 Aug 2020
Building plan approvalFile: MYSCAN_20200824_0002.pdf29 Aug 2020
Building plan approvalFile: MYSCAN_20200824_0003.pdf29 Aug 2020
Building plan approvalFile: MYSCAN_20200824_0004.pdf29 Aug 2020
Building plan approvalFile: MYSCAN_20200824_0005.pdf29 Aug 2020
Building plan approvalFile: MYSCAN_20200824_0006.pdf29 Aug 2020
Building plan approvalFile: MYSCAN_20200824_0007.pdf29 Aug 2020

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Runwal Shopping Arcade on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dombivli7,600+ in Thane

2 kmRunwal Shopping ArcadeCompleted 10Lapsed / revoked 7Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 51 registered projects within 2 km.

Builder: Runwal Residency Private Limited

Runwal Residency Private Limited has 18 registrations on MahaRERA, including Runwal Gardens Phase I and Runwal Gardens Phase 2 Bldg no 18-23. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Runwal Shopping Arcade is delayed beyond 30 Apr 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Runwal Shopping Arcade?

The registered promoter entity is Runwal Residency Private Limited, a company as per the filing. Its CIN U45400MH2011PTC212140 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Runwal Shopping Arcade?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Runwal Shopping Arcade?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Runwal Shopping Arcade?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Runwal Shopping Arcade?

The professionals named in the filing: Architect: Ar. Sandeep Prabhu for SAAKAAR; Architect: Saakar Architects; Architect: Sakar Architects; Engineer: Chetan Sampat; Engineer: Uttam Kawathankar; Engineer: SHAILESH MAHIMTURA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Runwal Shopping Arcade?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Runwal Shopping Arcade. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Runwal Shopping Arcade to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.