Home / Browse projects / Thane, Maharashtra / Runwal Gardens Phase 8 Bldg No. 43 and 45

Registered No litigation declared Residential / Group Housing project

Runwal Gardens Phase 8 Bldg No. 43 and 45

By Runwal Residency Private Limited

RG-MH-06319 · RERA P51700052441 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 21 months
  • 1 extension taken
  • Rs 525.00 crore secured on the land, in favour of ICICI bank ltd

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Sep 2028Possession promisedmoved 21 months from the original
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 57%
97 of 248Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 138 documents Report an error

Runwal Gardens Phase 8 Bldg No. 43 and 45 is a Residential / Group Housing project by Runwal Residency Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700052441 on 25 Aug 2023. Possession is promised by 30 Sep 2028. The completion date has moved by 21 months from the original filing. 151 of the 248 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameRunwal Gardens Phase 8 Bldg No. 43 and 45
  • TypeResidential / Group Housing
  • Location
    • Kalyan Shilphata Road
    • Dombivali
    • gharivle
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • RERA no.P51700052441
  • ReraGenie IDRG-MH-06319

Builder

  • NameRunwal Residency Private Limited
  • Entity typeCompany
  • CINU45400MH2011PTC212140
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsVijay Kisan Patil, Lucy Roychoudhury
  • Other registrations17 more →
  • Completed3 of 18
  • No longer live5 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2023First promiseDec 2026Revised toSep 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on25 Aug 2023
  • Promised completion30 Sep 2028
  • Revised completionRevised to 30 Sep 2028 (originally 31 Dec 2026)
  • Buildings2 building records
  • Documents filed138 files

Current status

61%151 of 248 units booked
10.2%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bldg No 43NA35301550155
Bldg No 45NA363093093

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 57%.

Bldg No 4334%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure57%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises15%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Bldg No 4530%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure26%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes40%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1862

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1,862
Closed/Covered1,862
BuildingClosed/CoveredTotal
Bldg No 43931931
Bldg No 45931931

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,245 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI bank ltd
Secured amountRs 525.00 crore
CERSAI search filedYes
Declared on13 May 2026

Approvals and building plan

Sanctioning authorityMumbai Metropolitan Region Development Authority (MMRDA)
Permissible FSI39905.43
Proposed, not sanctioned36,905 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop no 9 and 10 Mary Corner Besides NEXT Showroom Near Sion Circle Sion Mumbai 400022
Estimated costRs 203.94 cr
Cost incurredRs 20.85 cr
Work done10.23%
BuildingWingEstimatedIncurred
Bldg No 45NARs 75.48 crRs 10.22 cr
Bldg No 43NARs 73.96 crRs 10.21 cr
-NARs 54.50 crRs 41.81 lakh

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSandeep Prabhu Sakaar
ArchitectSakar Architects
ArchitectSaakar Architects
EngineerUTTAM KAWATHANKAR
EngineerChetan Sampat
EngineerSAAKAR ARCHITECTS
Chartered AccountantM.B. AGRAWAL & CO.
Chartered AccountantKshirsagar and Associates
Chartered AccountantKshirsagar & Associates
Chartered AccountantM B AGARWAL AND CO
PartnerRole in project
Runwal Residency Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA15052620972Dec 2026 → Sep 2028

Reason as filed by the promoterThe delay in the completion of the project has primarily occurred due to the encounter of unexpected hard rock strata during the excavation and foundation stage, which required a shift from standard methods to highly time-consuming, specialized rock-breaking techniques. This initial geological setback resulted in an unavoidable delay of approximately 9 to 10 months and significantly hindered subsequent structural works. Furthermore, the project's timeline was severely impacted by the poor performance of the initial RCC contractor, Jiban Construction Rising Private Limited, which caused a cumul

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC12504509Runwal Residency Private LimitedMOHAN KUMAR NAIR17/12/2025
CC12600477Runwal Residency Private LimitedPrashant Yashwant Kulkarni27/01/2026
CC12604853Runwal Residency Private LimitedAjay Ravindra Pandit01/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 20 Jul 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 1 Jun 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Jun 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Sep 2028

Documents filed138

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 138 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Form 2A (FY 2025 - 2026).pdf24 Jul 2026
Withdrawal Update Form 1File: FORM 1 - 43-45.pdf18 Jul 2026
Withdrawal Update Form 2File: FORM 2 - 43-45.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3 Tower 43 - 45..pdf18 Jul 2026
Disclosure of Sold and Booked InventoryFile: Runwal Gardens 43 45.pdf20 Apr 2026
Form 1File: 43-45 GARDENS FORM 1 COMPRESS.pdf20 Apr 2026
Form 2File: ENGINEERS CERTIFICATE 43-45 FORM 2.pdf20 Apr 2026
Form 3File: Form 3 Tower 43 45.pdf20 Apr 2026
Disclosure of Sold and Booked InventoryFile: Runwal Gardens 43 45.pdf20 Apr 2026
Form 1File: 43-45 GARDENS FORM 1 COMPRESS.pdf20 Apr 2026
Form 2File: ENGINEERS CERTIFICATE 43-45 FORM 2.pdf20 Apr 2026
Form 3File: Form 3 Tower 43 45.pdf20 Apr 2026
Form 1File: Form 1 -43-45 - DEC 25.pdf19 Jan 2026
Form 2File: form 2 43-45 dec 25.pdf19 Jan 2026
Form 3File: Form 3 Tower 43 to 45.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Runwal Gardens 43 and 45 2026 .pdf19 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration for Compliance RRPL.pdf19 Jan 2026
Form 1File: Form 1 43 45.pdf20 Oct 2025
Form 2File: Form 2 43 45.pdf20 Oct 2025
Form 3File: Form 3 Tower 43 to 45.pdf20 Oct 2025
Disclosure of Sold and Booked InventoryFile: Gardens 43 & 45 Inventory.pdf20 Oct 2025
Self-declaration of Quarterly ProgressFile: Declaration for Compliance RRPL final.pdf20 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A 43 45.pdf20 Oct 2025
Form 1File: Form 1 RG Phase 8 blg 43 45.pdf29 Jul 2025
Form 2File: PH8 T43 and T45 RERA FORM 2.pdf29 Jul 2025
Form 3File: Form 3 Tower 43 to 45.pdf29 Jul 2025
Disclosure of Sold and Booked InventoryFile: Runwal Gardens Phase 8 Bldg No 43 AND 45.pdf29 Jul 2025
Self-declaration of Quarterly ProgressFile: Declaration for Compliance RRPL.pdf29 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 43 to 45.pdf3 May 2025
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 8 Bldg No 43 and 45.pdf2 May 2025
Form 1 43 45 25 04 2529 Apr 2025
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 8 Bldg No 43 and 45.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH8 T43 and T45 RERA FORM 2 ENGINEERS CERTIIFICATE 31 03 2025.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 43 to 45.pdf12 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Done Form 1 43 45 December 2024.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 8 Bldg No 43 and 45.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Done Form 1 43 45 December 2024.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 43 to 45 done.pdf21 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A NEW 2024-TW-43-45.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH8 T43 and T45 RERA FORM 2 ENGINEERS CERTIIFICATE 30-09-2024.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -43-45 - Sept 24.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 8 Bldg No 43 and 45.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 43 to 45.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RRPL TOWER 43- 45 Form 5 Fy 23-24_signed.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Inventory Format Phase-8.pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -43-45 - June 24.pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH8 T43 and T45 FORM 2.pdf18 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: RRPL Revised CC phase 8 dated 14 May 2024_11zon.pdf12 Jul 2024
Building plan approvalFile: Tower 43 - 32.pdf21 Jun 2024
Building plan approvalFile: Tower 43 - 33.pdf21 Jun 2024
Building plan approvalFile: Tower 43 - 34.pdf21 Jun 2024
Building plan approvalFile: Tower 43 - 35.pdf21 Jun 2024
Building plan approvalFile: Tower 43 - 36.pdf21 Jun 2024
Building plan approvalFile: Tower 43 - 37.pdf21 Jun 2024
Building plan approvalFile: Tower 43 - 38.pdf21 Jun 2024
Building plan approvalFile: Tower 45 - 46.pdf21 Jun 2024
Building plan approvalFile: Tower 45 - 47.pdf21 Jun 2024
Building plan approvalFile: Tower 45 - 48.pdf21 Jun 2024
Building plan approvalFile: Tower 45 - 49.pdf21 Jun 2024
Building plan approvalFile: Tower 45 - 50.pdf21 Jun 2024
Building plan approvalFile: Tower 45 - 51.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 43 - 32.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 43 - 33.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 43 - 34.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 43 - 35.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 43 - 36.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 43 - 37.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 43 - 38.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 45 - 46.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 45 - 47.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 45 - 48.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 45 - 49.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 45 - 50.pdf21 Jun 2024
Building Plan Approval / NA Order for plotted developmentFile: Tower 45 - 51.pdf21 Jun 2024
Layout approvalFile: AMENDED CC 46-29.pdf1 Jun 2024
Layout approvalFile: AMENDED CC 46-30.pdf1 Jun 2024
Layout approvalFile: AMENDED CC 46-31.pdf1 Jun 2024
Copy of Layout Approval (in case of layout)File: AMENDED CC 46-29.pdf1 Jun 2024
Copy of Layout Approval (in case of layout)File: AMENDED CC 46-30.pdf1 Jun 2024
Copy of Layout Approval (in case of layout)File: AMENDED CC 46-31.pdf1 Jun 2024

How this compares with Thane

61%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 21 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Runwal Gardens Phase 8 Bldg No. 43 and 45 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dombivali7,600+ in Thane

Builder: Runwal Residency Private Limited

Runwal Residency Private Limited has 18 registrations on MahaRERA, including Runwal Gardens Phase I and Runwal Gardens Phase 2 Bldg no 18-23. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Runwal Gardens Phase 8 Bldg No. 43 and 45 is delayed beyond 30 Sep 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Runwal Gardens Phase 8 Bldg No. 43 and 45?

The registered promoter entity is Runwal Residency Private Limited, a company as per the filing. Its CIN U45400MH2011PTC212140 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Runwal Gardens Phase 8 Bldg No. 43 and 45?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Runwal Gardens Phase 8 Bldg No. 43 and 45?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Runwal Gardens Phase 8 Bldg No. 43 and 45?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Runwal Gardens Phase 8 Bldg No. 43 and 45?

The professionals named in the filing: Architect: Sandeep Prabhu Sakaar; Architect: Sakar Architects; Architect: Saakar Architects; Engineer: UTTAM KAWATHANKAR; Engineer: Chetan Sampat; Engineer: SAAKAR ARCHITECTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Runwal Gardens Phase 8 Bldg No. 43 and 45?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Runwal Gardens Phase 8 Bldg No. 43 and 45. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Runwal Gardens Phase 8 Bldg No. 43 and 45 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.