Home / Browse projects / Thane, Maharashtra / Runwal Gardens Phase 3 Bldg no 24-26

Registration lapsed No litigation declared Residential / Group Housing project

Runwal Gardens Phase 3 Bldg no 24-26

By Runwal Residency Private Limited

RG-MH-28515 · RERA P51700026228 · Last updated on MahaRERA portal: 20 Oct 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 16 months past the filed date
  • 15 complaints at MahaRERA
  • Rs 790.00 crore secured on the land, in favour of Indusind Bank

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2025Possession promised16 months past this date
18 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 95%
15Complaints at MahaRERAon this registration
Jump to the 196 documents Report an error

Runwal Gardens Phase 3 Bldg no 24-26 is a Residential / Group Housing project by Runwal Residency Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700026228 on 30 Aug 2020. Possession was promised by 30 Jun 2025 and is now 16 months past that date. 15 complaints are on record with the regulator.

At a glance

Project

  • NameRunwal Gardens Phase 3 Bldg no 24-26
  • TypeResidential / Group Housing
  • Location
    • Village Gharivali usarghar and Sagoan
    • Dombivli
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • RERA no.P51700026228
  • ReraGenie IDRG-MH-28515

Builder

  • NameRunwal Residency Private Limited
  • Entity typeCompany
  • CINU45400MH2011PTC212140
  • CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorsVijay Kisan Patil, Lucy Roychoudhury
  • Other registrations17 more →
  • Completed3 of 18
  • No longer live5 lapsed, de-registered or revoked

Key dates

16 months past promisethis monthRegisteredAug 2020PromisedJun 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on30 Aug 2020
  • Promised completion30 Jun 2025
  • Revised completionNone
  • Buildings3 building records
  • Documents filed196 files

Current status

92.2%Work done, per cost certificate

Figures as on 20 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building Number 24NA350000
Building Number 25NA350000
Building Number 26NA350000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 20 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 95%.

Building Number 2485%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises72%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.85%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Building Number 2584%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises62%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
Building Number 2684%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises62%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 20 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,987 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofIndusind Bank
Secured amountRs 790.00 crore
CERSAI search filedYes
Declared on24 Jun 2025

Approvals and building plan

Sanctioning authorityMMRDA
Permissible FSI52588.18
Proposed, not sanctioned50,588 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop no 9 and 10 Mary Corner besides NEXT Showroom Near Sion Circle sion Mumbai 400022
Estimated costRs 230.79 cr
Cost incurredRs 212.91 cr
Work done92.25%
BuildingWingEstimatedIncurred
Building Number 24NARs 68.92 crRs 68.92 cr
Building Number 25NARs 55.77 crRs 55.77 cr
Building Number 26NARs 55.32 crRs 55.32 cr
-NARs 50.77 crRs 32.89 cr

Certifying professionals and partners10

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAr. Sandeep Prabhu for SAAKAAR
ArchitectPrecise Architects and consultants
ArchitectSaakar Architects
EngineerChetan Sampat
EngineerUTTAM KAWATHANKAR
EngineerSHAILESH MAHIMTURA
Chartered AccountantBhatter & Company Chartered Accountants
Chartered Accountantkshirsagar and associates
Chartered AccountantM.B. Agrawal & Co.
Chartered AccountantSINGHI AND CO
PartnerRole in project
Runwal Residency Private Limited-

Complaints filed with MahaRERA15

Case no.ComplainantRespondentFiled
CC006000000333935Runwal Residency Private LimitedSukesh J Mendon19/01/2023
CC006000000333945Mrs. Salma Abdul Rashid KhanM/S. RUNWAL RESIDENCY PVT. LTD.14/01/2023
CC12503231Runwal Residency Private LimitedMr Praveen Kumar Tiwari12/09/2025
CC12503386Runwal Residency Private LimitedSantosh Madhukar Jangam22/09/2025
CC12503501Ravindra TUKARAM RaoRunwal Residency Private Limited01/10/2025
CC12503727Ashutosh SangleRunwal Residency Private Limited23/10/2025
CC12504671SANJAY BALU BUTKARRunwal Residency Private Limited29/12/2025
CC12600370Runwal Residency Private LimitedPrathamesh Pruthviraj Kharate20/01/2026
CC12600536Runwal Residency Private LimitedRakesh Jagannatha Poojary31/01/2026
CC12600821Runwal Residency Private LimitedAditya Kashinath Mundekar13/02/2026
CC12601484Runwal Residency Private LimitedBhushan Santosh Dhasal17/03/2026
CC12601631Runwal Residency Private LimitedASHISH VISHWAKARMA23/03/2026
CC12601751Runwal Residency Private LimitedREKHA SUBHASH THAKKAR27/03/2026
CC12601974Runwal Residency Private LimitedMohammed Manzoor Farooquie03/04/2026
CC12602523Runwal Residency Private LimitedParameshwar Pitamabr Bagul30/04/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 4 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Aug 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed196

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 196 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: RRPL T24-26.pdf20 Oct 2025
Withdrawal Update Form 1File: Form 1 RG Phase 3 blg no 24 25 26.pdf10 Oct 2025
Withdrawal Update Form 2File: PH3 T24 to T26 RERA FORM 2 ENGINEERS CERTIIFICATE 30 06 2025.pdf10 Oct 2025
Withdrawal Update Form 3File: Form 3 Tower 24 to 26.pdf10 Oct 2025
Withdrawal Update Form 1File: Form 1 RG Phase 3 blg no 24 25 26.pdf9 Oct 2025
Withdrawal Update Form 2File: PH3 T24 to T26 RERA FORM 2 ENGINEERS CERTIIFICATE 30 06 2025.pdf9 Oct 2025
Withdrawal Update Form 3File: Form 3 Tower 24 to 26.pdf9 Oct 2025
Withdrawal Update Form 1File: Form 1 RG Phase 3 blg no 24 25 26.pdf7 Oct 2025
Withdrawal Update Form 1File: Form 1 RG Phase 3 blg no 24 25 26.pdf7 Oct 2025
Withdrawal Update Form 2File: PH3 T24 to T26 RERA FORM 2 ENGINEERS CERTIIFICATE 30 06 2025.pdf7 Oct 2025
Withdrawal Update Form 2File: PH3 T24 to T26 RERA FORM 2 ENGINEERS CERTIIFICATE 30 06 2025.pdf7 Oct 2025
Withdrawal Update Form 3File: Form 3 Tower 24 to 26.pdf7 Oct 2025
Withdrawal Update Form 3File: Form 3 Tower 24 to 26.pdf7 Oct 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 24 to 26.pdf2 May 2025
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 3 Bldg No 24 26.pdf2 May 2025
Form 1 24 25 26 25 04 2529 Apr 2025
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 3 Bldg No 24 26.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH3 T24 to T26 RERA FORM 2 ENGINEERS CERTIIFICATE 31 03 2025.pdf18 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 24 to 26.pdf12 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: done Form 1 24 25 26.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 3 Bldg No 24 to 26.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Done PH3 T24 to T26 RERA FORM 2 ENGINEERS CERTIIFICATE.pdf30 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Done Form 3 Tower 24 to 26.pdf27 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24 25 26 done.pdf24 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A NEW 2024-TW-24-26.pdf25 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH3 T24 to T26 RERA FORM 2 ENGINEERS CERTIIFICATE 30-09-2024.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 24-26.pdf21 Oct 2024
Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase 3 Bldg No 24-26.pdf21 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 24 to 26.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RRPL TOWER 24-26 Form-5 FY 23-24_signed.pdf7 Oct 2024
Disclosure of sold/ booked inventoryFile: Inventory Format - Phase-3A.pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -24-26 - June 24.pdf23 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH3 T24 to T26 FORM 2.pdf18 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 24-26.pdf18 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: RRPL Revised CC phase 8 dated 14 May 2024_11zon.pdf12 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -24-26 - March 24.pdf26 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Revised Form 3 T24-26.pdf24 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase 3 T24 to T26.pdf18 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 24-26.pdf24 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower 24-26.pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 24-26.pdf19 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 24-26.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 24-26.pdf21 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 24-26.pdf20 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Tower 24-26 Form 5 FY 2022-23-min.pdf30 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Tower 24-26 Form 5 FY 2022-23-min.pdf30 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 - 24-26.pdf21 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 24-26.pdf21 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 T24-T26.pdf20 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 T24-T26.pdf20 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 24-26.pdf24 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 BLDG NO 24 TO 26.pdf17 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - 24-26.pdf16 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Phase 3A 24-26.pdf16 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Runwal Gardens - Form 1 - Tower 24 to 26.pdf28 Apr 2023
Disclosure of sold/ booked inventoryFile: INVEN 24- 26.pdf22 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 BLDG NO 24-26.pdf21 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 BLDG NO 24 TO 26.pdf21 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 BLDG NO 27-28.pdf21 Apr 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A BLDG- 24-26.pdf17 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Runwal Name Registation - Phase 3 Tower 24 to 26.pdf12 Apr 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Extension Certificate-Phase -3 Tower 24 to 30FINAL.pdf28 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Phasse 3 Building 24-26.pdf24 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: From 5 Bldg 24-26.pdf30 Nov 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCH R Garden 3 24 to 26_compressed.pdf22 Oct 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Bldg 24 to 26_compressed.pdf22 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Runwal Gardens Phase 2 A_compressed.pdf22 Oct 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect 24-26 under 1mb.pdf26 Aug 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: eng 24-26 final.pdf26 Aug 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: ca 24-26 final under 1mb.pdf26 Aug 2022
Details of encumbrancesFile: ENCUMB INDUSIND.pdf19 Aug 2022
CERSAI detailsFile: CERSAI - Vistra.pdf20 Jul 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FROM 3 Phase 3 Bldg no 24-26.pdf7 Jul 2022
Layout approvalFile: layout plan 15-12.pdf4 May 2022
Copy of the legal title reportFile: Arcade tittle.pdf4 May 2022
Copy of Layout Approval (in case of layout)File: layout plan 15-12.pdf4 May 2022
Commencement Certificates / NA Order for plotted developmentFile: Arcade CC.pdf4 May 2022
Declaration about Commencement CertificateFile: DECLA SHOPPING.pdf4 May 2022
CERSAI detailsFile: CERSAI.pdf4 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Phase 3 Bldg no 24 to 26.pdf30 Apr 2022

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Runwal Gardens Phase 3 Bldg no 24-26 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dombivli7,600+ in Thane

Builder: Runwal Residency Private Limited

Runwal Residency Private Limited has 18 registrations on MahaRERA, including Runwal Gardens Phase I and Runwal Gardens Phase 2 Bldg no 18-23. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Runwal Gardens Phase 3 Bldg no 24-26 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Runwal Gardens Phase 3 Bldg no 24-26 is delayed beyond 30 Jun 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Runwal Gardens Phase 3 Bldg no 24-26?

The registered promoter entity is Runwal Residency Private Limited, a company as per the filing. Its CIN U45400MH2011PTC212140 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Runwal Gardens Phase 3 Bldg no 24-26?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Runwal Gardens Phase 3 Bldg no 24-26?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Runwal Gardens Phase 3 Bldg no 24-26?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Runwal Gardens Phase 3 Bldg no 24-26?

The professionals named in the filing: Architect: Ar. Sandeep Prabhu for SAAKAAR; Architect: Precise Architects and consultants; Architect: Saakar Architects; Engineer: Chetan Sampat; Engineer: UTTAM KAWATHANKAR; Engineer: SHAILESH MAHIMTURA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Runwal Gardens Phase 3 Bldg no 24-26?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Runwal Gardens Phase 3 Bldg no 24-26. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Runwal Gardens Phase 3 Bldg no 24-26 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.