Home / Browse projects / Mumbai Suburban, Maharashtra / RUDRAKSH
RUDRAKSH
RG-MH-49746 · RERA P51800010914 · Last updated on MahaRERA portal: 6 Nov 2023
Source: official MahaRERA filing
Red flags
- Completion date moved by 12 months
- 2 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RUDRAKSH is a Others project by SANDU DEVELOPERS in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800010914 on 31 Aug 2017. The registration is recorded completed; possession was promised by 31 Oct 2019. The completion date has moved by 12 months from the original filing.
At a glance
Project
- NameRUDRAKSH
- TypeOthers
- Location
- Kurla
- Mumbai Suburban
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800010914
- ReraGenie IDRG-MH-49746
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on31 Aug 2017
- Promised completion31 Oct 2019
- Revised completionRevised to 31 Oct 2019 (originally 31 Oct 2018)
- Buildings1 building record
- Documents filed33 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RUDRAKSH | NA | 15 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 6 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
11 of 11 construction stages are filed complete.
RUDRAKSH: 100% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 6 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed61
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners2
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ashish Bhatt |
| Engineer | Nirav P Shah |
| Partner | Role in project |
|---|---|
| SANDU DEVELOPERS | - |
Extensions applied for2
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe Project “Rudraksh” has been approved as per Development Control Regulations 1991 (“DCR 1991”) and all approvals with respect to Concessions, IOD & CC have been processed as per DCR 1991. As you may be aware, the Development Control and Promotion Regulations 2034 (“DCPR 2034”) were released on 8th May, 2018 which did not have the transition policy required to process the files which were submitted under DCR 1991. Further, there was no clarity if the existing projects approved under DCR 1991 would require to be further amended in accordance with the DCPR 2034. In the meantime, Hon’ble Chief
Reason as filed by the promoterAs per the DCR 1991(Regulation 31-Table 13),permissible height of a Building is 61m+1.5m=62.5m and Project Rudraksh falls within the criteria mentioned therein & hence the permissible height for the said Project is 61m+1.5m=62.5m.However, as per the Civil Aviation NOC dated 08-11-2012 bearing reference no. BT-1/NOC/MUM/12/NOCAS/102 the concerned authorities permitted us to construct the said Project Building upto a height of 56.28m. The AAI, Delhi revised the permissible height to 56.9m vide NOC dated 30-06-2017 bearing NOC ID SNCR/WEST/B/052417/221652.Since the permission granted as per the a
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 31 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 6 Nov 2023
Documents filed33
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: LISONSEROS CERTIFICATE- RUDRAKSH-1.pdf | 6 Nov 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE.pdf | 4 Nov 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Registration Certificate-Seeta Sadan CHSL.pdf | 4 Nov 2023 |
| OtherFile: Seeta sadan - Disclosure Letter - 17022020.pdf | 20 Feb 2020 |
| Certificates of CA (Form 5)File: Form-5 Rudraksh.pdf | 4 Oct 2019 |
| Certificates of CA (Form 5)File: Form 5 - Rudraksh - 2017-18.pdf | 17 Nov 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rudraksh Form I 31st March 2018.pdf | 11 Jul 2018 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architects certificate for Seeta Sadan 31st Jan 2018.pdf | 22 Feb 2018 |
| Building plan approvalFile: Rudraksh IOD.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 3.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 2.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Letter.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 1.pdf | 31 Jul 2017 |
| Layout approvalFile: Amended Plan 1.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 4.pdf | 31 Jul 2017 |
| Building plan approvalFile: Amended Plan 5.pdf | 31 Jul 2017 |
| PAN CardFile: PAN Card-Sandu Developers.pdf | 31 Jul 2017 |
| Copy of the legal title reportFile: Rudraksh- Title Certificate.pdf | 31 Jul 2017 |
| Details of encumbrancesFile: Details of Encumbrances.PDF | 31 Jul 2017 |
| Copy of Layout Approval (in case of layout)File: Amended Plan 1.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Rudraksh IOD.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Letter.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 1.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 2.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 3.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 4.pdf | 31 Jul 2017 |
| Building Plan Approval (IOD)File: Amended Plan 5.pdf | 31 Jul 2017 |
| Commencement Certificates / NA Order for plotted developmentFile: Seeta Sadan-CC.pdf | 31 Jul 2017 |
| Declaration in FORM BFile: Declaration Form B.pdf | 31 Jul 2017 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate Rudraksh.pdf | 31 Jul 2017 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate -Rudraksh.pdf | 31 Jul 2017 |
| Certificates of CA (Form 3)File: Form 3 CA Certificate Rudraksh.pdf | 31 Jul 2017 |
| Proforma of Allotment letterFile: Merged-AFS and Allotment Letter.pdf | 31 Jul 2017 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 4 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 33 filed documents as one ZIP, foldered, with a manifest
Keep RUDRAKSH on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Kurla6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 421 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai Suburban project, with the district possession charts
Builder: SANDU DEVELOPERS
Sandu Developers has 5 registrations on MahaRERA, including Sandu Aarambh and RUDRAKSH. Its filings disclose 2 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if RUDRAKSH is delayed beyond 31 Oct 2019?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RUDRAKSH?
The registered promoter entity is SANDU DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RUDRAKSH?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for RUDRAKSH?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RUDRAKSH?
The professionals named in the filing: Architect: Ashish Bhatt; Engineer: Nirav P Shah. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RUDRAKSH?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback