Royal Fantasy Phase III
By Royal Fantasy Constructions Private Limited
RG-MH-84810 · RERA P51800009920 · Last updated on MahaRERA portal: 26 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 90 months
- 6 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Royal Fantasy Phase III is a Residential / Group Housing project by Royal Fantasy Constructions Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009920 on 22 Aug 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 90 months from the original filing. 50 of the 60 units on this registration are recorded sold or booked, and 21 of 44 construction stages are filed complete.
At a glance
Project
- NameRoyal Fantasy Phase III
- TypeResidential / Group Housing
- Location
- Andheri
- Mumbai Suburban
- 400093
- Pincode400093
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800009920
- ReraGenie IDRG-MH-84810
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on22 Aug 2017
- Promised completion30 Jun 2027
- Revised completionRevised to 30 Jun 2027 (originally 31 Dec 2019)
- Buildings4 building records
- Documents filed176 files
Current status
Figures as on 26 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable | NA | 4 | 3 | 0 | 1 | 1 |
| Dreamax Height Wing A PH Full - no Saleable | NA | 16 | 15 | 11 | 0 | 11 |
| Dreamax Vega Wing D | NA | 16 | 12 | 40 | 0 | 40 |
| Dreamax Height Wing B 12th - 15th floor | NA | 5 | 4 | 8 | 0 | 8 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building4
As on 26 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
21 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 95%.
Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable45%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 90% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Dreamax Height Wing A PH Full - no Saleable73%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 95% |
| Sanitary Fittings within the flats / premises | 80% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 80% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 75% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 75% |
Dreamax Vega Wing D96%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 75% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 85% |
Dreamax Height Wing B 12th - 15th floor49%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 85% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 50% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 26 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | - |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 60% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed44
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| Dreamax Vega Wing D | 37 | 37 |
| Dreamax Height Wing B 12th - 15th floor | 7 | 7 |
Land and ownership9
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Vidyabhushan Khudiram Upadhyay | Andheri | Mumbai Suburban |
| Vanibhushan Khudiram Upadhyay | Andheri | Mumbai Suburban |
| Bhartibhushan Khudiram Upadhyay | Andheri | Mumbai Suburban |
| Satyanand Chitanand Upadhyay | Andheri | Mumbai Suburban |
| Bhavanand Chitanand Upadhyay | Andheri | Mumbai Suburban |
| Sachitanand Chitanand Upadhyay | Andheri | Mumbai Suburban |
| Vivekanand Chitanand Upadhyay | Andheri | Mumbai Suburban |
| Vishal Sampurnand Upadhyay | Andheri | Mumbai Suburban |
| Ramdular Siddhinarayan Upadhyay | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Dreamax Vega Wing D | NA | Rs 22.70 cr | Rs 22.25 cr |
| - | NA | Rs 14.57 cr | Rs 13.11 cr |
| Dreamax Height Wing A PH Full - no Saleable | NA | Rs 8.24 cr | Rs 7.83 cr |
| Dreamax Height Wing B 12th - 15th floor | NA | Rs 2.16 cr | Rs 1.94 cr |
| Dreamax Height Wing C PTC Slab 13th to 15th - no Saleable | NA | Rs 1.74 cr | Rs 1.48 cr |
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Arun Kumar Dubey |
| Architect | Arun Kumar Dube |
| Engineer | Ace Project Management Consultant |
| Engineer | AHMAD & ASSOCIATES |
| Chartered Accountant | Himani R Patel and Associates |
| Chartered Accountant | M N N Y & ASSOCIATES LLP |
| Chartered Accountant | Himani R Patel & Associates |
| Partner | Role in project |
|---|---|
| Royal Fantasy Constructions Private Limited | - |
Extensions applied for6
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending. 6. Due to COVID Pandemic Factor, the construction was not completed within the project completion date.
Reason as filed by the promoterOur under construction real estate project is getting delayed due to several reasons as follows: 1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition for sale 2. Other reasons: • Contractor’s inability to complete scheduled phase due to shortage of labour faced by him. • Last year disruptions due to GST & demonetization implementations. • Non-availability of sand on time. 3. Default from contactors: • Contracto
Reason as filed by the promoter1. Temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time 3. Default from contractors 4. Outstanding receivable from buyers 5. Registration of some flats were still pending
Reason as filed by the promoter1. Work in progress in phase 3 is slow as compared to our schedule because we have to take utmost care of possession given to flat buyers in phase 1 close to the phase 3 building during construction activity. 2. The Flat buyers are not paying payments as per the schedule and we have to arrange funds from other sources every time which takes time.
Reason as filed by the promoteri) The project comprises three phases-Phase 1, Phase 2, and Phase 3-being developed on the same plot of land and includes two buildings: Dreamax Vega and Dreamax Height. Phase 1 has been successfully completed, Occupation Certificate (OC) has been obtained, and possession has been handed over to the respective allottees. Phase 2 is nearing completion. However, the progress of Phase 3 has been comparatively slower due to the necessity of exercising extreme caution during construction activities, as Phase 3 is in close proximity to the already occupied Phase 1. This precaution is being taken to
Reason as filed by the promoterThe project completion was delayed due to the need for additional safety precautions during construction, as Phase 3 is located adjacent to the occupied Phase 1, to ensure the safety and comfort of residents. Further, irregular payments by certain allottees affected the project's cash flow, resulting in delays in arranging alternative funding and consequently slowing the construction progress.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 May 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 27 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 11 Jul 2024
Documents filed176
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 176 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Phase-III Form-1_Architect Certificate.pdf | 26 Aug 2026 |
| Withdrawal Update Form 2File: Phase-III Form-2_Engineer Certificate.pdf | 26 Aug 2026 |
| Withdrawal Update Form 3File: RFCPL Phase-III RERA Form-3 Q1.pdf | 26 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A 25-26_compressed.pdf | 3 Jul 2026 |
| Withdrawal Update Form 1File: Form-1 Q4 Phase-3.pdf | 6 May 2026 |
| Withdrawal Update Form 2File: Form-2 Q4 Phase-3.pdf | 6 May 2026 |
| Withdrawal Update Form 3File: Form-3 Q4 Phase-3.pdf | 6 May 2026 |
| Withdrawal Update Form 1File: Application Form1 Phase-III Q2_Final.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Application Form1 Phase-III Q3_Final.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Form-2 Phase-III_Q2_Final.pdf | 4 Feb 2026 |
| Withdrawal Update Form 2File: Application Form2 Phase-III Q3_Final.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Form-3 Phase-III Q2.pdf | 4 Feb 2026 |
| Withdrawal Update Form 3File: Application Form3 Phase-III Q3_Final.pdf | 4 Feb 2026 |
| Withdrawal Update Form 1File: Final form-1 Q1.pdf | 27 Jan 2026 |
| Withdrawal Update Form 2File: Final Form-2 Q1.pdf | 27 Jan 2026 |
| Withdrawal Update Form 3File: Final Form-3 Q1.pdf | 27 Jan 2026 |
| Form 5 (FY 2024-2025)File: Final Form 5_Phase 3.pdf | 6 Dec 2025 |
| Form 1File: Form 1.pdf | 30 Jul 2025 |
| Form 2File: Form 2.pdf | 30 Jul 2025 |
| Form 3File: Final Form-3.pdf | 30 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Booked Inventory.pdf | 30 Jul 2025 |
| Form 2A (FY 2023-2024)File: FORM 2A PHASE 3_ 2023-2024.pdf | 30 Jul 2025 |
| Form 2A (FY 2024-2025)File: FORM 2A PHASE 3_ 2024-2025.pdf | 30 Jul 2025 |
| Form 5 (FY 2023-2024)File: FORM 5_compressed.pdf | 23 Jul 2025 |
| Layout approvalFile: Approval Plan Height building 1st floor 2nd floor.pdf | 16 May 2025 |
| Copy of Layout Approval (in case of layout)File: Approval Plan Height building 1st floor 2nd floor.pdf | 16 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 16 May 2025 |
| Certificates of CA (Form 3)File: Form 3.pdf | 16 May 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 16 May 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 29 Apr 2025 |
| Certificates of CA (Form 3)File: Form-3_compressed.pdf | 29 Apr 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 29 Apr 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 31 Oct 2024 |
| Certificates of CA (Form 3)File: Form 3 compressed.pdf | 31 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 31 Oct 2024 |
| Certificates of CA (Form 3)File: Royal Fantasy Phase III Q1 24-25_compressed.pdf | 25 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf | 24 Oct 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf | 24 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Details of Encumbrances concerned to legal.pdf | 12 Jul 2024 |
| Details of encumbrances concerned to LegalFile: Details of Encumbrances concerned to legal.pdf | 12 Jul 2024 |
| Declaration in FORM BFile: Form B Affidavit For RERA Extension.pdf | 11 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Engineer Certificate_Form 2A.pdf | 11 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf | 11 Jul 2024 |
| CERSAI detailsFile: CERSAI Report.pdf | 11 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A - Disclosure of interest (RFCPL).pdf | 11 Jul 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Annexure A-Disclosure of Int (Vijay Yadav).pdf | 11 Jul 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Further CC.pdf | 11 Jul 2024 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Format A - Seperate Bank Account Details.pdf | 11 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III.pdf | 2 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase III.pdf | 2 Jul 2024 |
| Certificates of CA (Form 3)File: Form 3 phase III_compressed.pdf | 2 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase III.pdf | 30 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Revise Form 2.pdf | 30 Apr 2024 |
| Certificates of CA (Form 3)File: Final FORM 3 PHASE III Q3_compressed.pdf | 27 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FINAL SIGNED 2022-23.pdf | 20 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 14 Dec 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf | 14 Dec 2023 |
| Certificates of CA (Form 3)File: FORM 3 COMPRESSED.pdf | 14 Dec 2023 |
| Layout approvalFile: P1_organized.pdf | 9 Dec 2023 |
| Layout approvalFile: P2_organized.pdf | 9 Dec 2023 |
| Layout approvalFile: P3_organized.pdf | 9 Dec 2023 |
| Layout approvalFile: P4_organized.pdf | 9 Dec 2023 |
| Layout approvalFile: P5_organized.pdf | 9 Dec 2023 |
| Layout approvalFile: P6_organized.pdf | 9 Dec 2023 |
| Layout approvalFile: P7_organized.pdf | 9 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: P1_organized.pdf | 9 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: P2_organized.pdf | 9 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: P3_organized.pdf | 9 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: P4_organized.pdf | 9 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: P5_organized.pdf | 9 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: P6_organized.pdf | 9 Dec 2023 |
| Copy of Layout Approval (in case of layout)File: P7_organized.pdf | 9 Dec 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC Dated 03102023 Vega Building.pdf | 27 Nov 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC dt 05092023 Composite Building.pdf | 27 Nov 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase 3_compressed.pdf | 21 Aug 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 3.pdf | 21 Aug 2023 |
| Certificates of CA (Form 3)File: FORM 3 compressed.pdf | 21 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Phase 3__compressed.pdf | 18 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 3_.pdf | 18 May 2023 |
| Certificates of CA (Form 3)File: Phase III - ROYAL FANTASY FORM 3_compressed.pdf | 18 May 2023 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Royal Fantasy Phase IIP51800004649 | Andheri, Mumbai Suburban | 69 | Aug 2017 | Ongoing | Dec 2024Registered original: Jun 2019 | Not delivered |
| Royal Fantasy Phase IP51800009606 | Andheri, Mumbai Suburban | 64 | Aug 2017 | Completed | Jun 2022Registered original: Dec 2018 | Apr 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 176 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Royal Fantasy Phase III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Andheri6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 305 registered projects within 2 km.
INSPIRE RESIDENCY
SARDAR REALTY
MAHAKALI HILLS
Mohid Construction Co
ZENNITH
APEXBLISS INFRAVENTURES PRIVATE LIMITED
SHIVSAI SRA CHS
AARC REAL ESTATE DEVELOPERS PRIVATE LIMITE
SPLENDOR ESQUINA
SPLENDOR SRL PRIVATE LIMITED
93 PALLADIAN
Vijayalaxmi Builders & Contractors
See every Mumbai Suburban project, with the district possession charts
Builder: Royal Fantasy Constructions Private Limited
Royal Fantasy Constructions Private Limited has 3 registrations on MahaRERA, including Royal Fantasy Phase I and Royal Fantasy Phase II. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if Royal Fantasy Phase III is delayed beyond 30 Jun 2027?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Royal Fantasy Phase III?
The registered promoter entity is Royal Fantasy Constructions Private Limited, a company as per the filing. Its CIN U45200MH2008PTC182431 and GSTIN 27AADCR9796A1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Royal Fantasy Phase III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Royal Fantasy Phase III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Royal Fantasy Phase III?
The professionals named in the filing: Architect: Arun Kumar Dubey; Architect: Arun Kumar Dube; Engineer: Ace Project Management Consultant; Engineer: AHMAD & ASSOCIATES; Chartered Accountant: Himani R Patel and Associates; Chartered Accountant: M N N Y & ASSOCIATES LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Royal Fantasy Phase III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback