Royal Fantasy Phase II

By Royal Fantasy Constructions Private Limited

RG-MH-77169 · RERA P51800004649 · Last updated on MahaRERA portal: 6 May 2026

Source: official MahaRERA filing

Red flags

  • 5 complaints at MahaRERA
  • Completion date moved by 90 months
  • 6 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 90 months from the original
15 of 22Construction stages doneacross 2 buildings; furthest along: Sanitary Fittings within the flats /..., 75%
1 of 68Units unsoldnot recorded sold or booked
5Complaints at MahaRERAon this registration
Jump to the 168 documents Report an error

Royal Fantasy Phase II is a Residential / Group Housing project by Royal Fantasy Constructions Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800004649 on 9 Aug 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 90 months from the original filing. 67 of the 68 units on this registration are recorded sold or booked, and 15 of 22 construction stages are filed complete. 5 complaints are on record with the regulator.

At a glance

Project

  • NameRoyal Fantasy Phase II
  • TypeResidential / Group Housing
  • Location
    • Andheri
    • Mumbai Suburban
    • 400093
  • Pincode400093
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800004649
  • ReraGenie IDRG-MH-77169

Builder

  • NameRoyal Fantasy Constructions Private Limited
  • Entity typeCompany
  • CINU45200MH2008PTC182431
  • GSTIN27AADCR9796A1Z1
  • Managing DirectorVijay Yadav
  • DirectorsUTKARSH AGARWAL, Ajay Singh
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017First promiseJun 2019Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Aug 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2019)
  • Buildings2 building records
  • Documents filed168 files

Current status

99%67 of 68 units booked
95.8%Work done, per cost certificate

Figures as on 6 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dreamax Height Wing B up to 11th FloorNA131141041
Dreamax Vega Wing C FullNA161227027

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 6 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Sanitary Fittings within the flats / premises, at 75%.

Dreamax Height Wing B up to 11th Floor71%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.70%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Dreamax Vega Wing C Full95%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises75%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Progress on shared amenities15

As on 6 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes50%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed59

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots59
Closed/Covered59
BuildingClosed/CoveredTotal
Dreamax Height Wing B up to 11th Floor3535
Dreamax Vega Wing C Full2424

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,117 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on18 Sep 2024
LandownerVillageDistrict
Vidyabhushan Khudiram UpadhyayAndheriMumbai Suburban
Vanibhushan Khudiram UpadhyayAndheriMumbai Suburban
Bhartibhushan Khudiram UpadyayAndheriMumbai Suburban
Satyanand Chitanand UpadhyayAndheriMumbai Suburban
Bhavanand Chitanand UpadhyayAndheriMumbai Suburban
Sachitanand Chitanand UpadhyayAndheriMumbai Suburban
Vivekanand Chitanand UpadhyayAndheriMumbai Suburban
Vishal Sampurnand UpadhyayAndheriMumbai Suburban
Ramdular Siddhinarayan UpadhyayAndheriMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI5607.52
Proposed, not sanctioned3,436 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop 1 and 2 Options Primo Plot No X21 MIDC Cross Road No 21 MIDC Marol Andheri East Mumbai 93
Estimated costRs 32.68 cr
Cost incurredRs 31.29 cr
Work done95.76%
BuildingWingEstimatedIncurred
Dreamax Vega Wing C FullNARs 16.81 crRs 16.48 cr
Dreamax Height Wing B up to 11th FloorNARs 11.06 crRs 10.40 cr
-NARs 4.80 crRs 4.42 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArun Kumar Dube
EngineerAce Project Management Consultant
EngineerAHMAD & ASSOCIATES
Chartered AccountantHimani R Patel and Associates
Chartered AccountantM N N Y & ASSOCIATES LLP
Chartered AccountantHimani R Patel & Associates
PartnerRole in project
Royal Fantasy Constructions Private Limited-

Extensions applied for6

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800001942Jun 2019 → Jun 2020

Reason as filed by the promoterOur under construction real estate project is getting delayed due to several reasons as follows: 1. MCGM notified only the Draft DP sheets 2034 on 8th September 2017. Since the DP sheets had many errors, the DP/DCR 2034 was held up again. DCR-2034 was finally notified recently sometime back and MCGM has increased the FSI for building development for various categories of real estate projects. Our project is also a beneficiary of increased FSI, as already envisaged by us and proposed accordingly at the time of MahaRERA registration. Delay in finalization of DP/DCR 2034 has resulted in huge dela

EXT51800012172Jun 2019 → Dec 2023

Reason as filed by the promoter1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updation & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending.

EXT51800008935Jun 2019 → Dec 2021

Reason as filed by the promoter1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition for sale 2. Other reasons: • Contractor’s inability to complete scheduled phase due to shortage of labour faced by him. • Last year disruptions due to GST & demonetization implementations. • Non-availability of sand on time. 3. Default from contactors: • Contractor’s inability to perform their contractual obligations within the timescales detailed in the Cont

EXT51800018643Jun 2019 → Dec 2024

Reason as filed by the promoter1. There was a temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale 2. Shortage of labor, disruptions due to implementation of GST and continuous updation and non availability of sand on time 3. Default from customers 4. Outstanding receivables from customers 5. Registration of some of the flats are still pending

EXT51800027178Jun 2019 → Dec 2025

Reason as filed by the promoter1. Work in Progress in Phase 2 is slow compared to our schedule because we have to take utmost care of possession given to flat buyers in Phase 1 close to the Phase 2 building during construction activity. 2. The Flat buyers are not paying payments as per the schedule and we have to arrange funds from other sources every time which takes time.

EA04022619699Jun 2019 → Dec 2026

Reason as filed by the promoterPhase 1 of the project has been completed, with the Occupation Certificate received and possession handed over, while Phase 3 is close to completion. Phase 2 has taken longer as it is next to the occupied Phase 1, requiring extra care and safety measures during construction. The delay was also due to irregular payments by some allottees, which created financial pressure and required the developer to arrange alternative funding to continue the work.

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC006000000195437Harpreet Rajendra Singh AlagRoyal Fantasy Constructions Private Limited29/12/2020
CC006000000195697MANOJ DINANATH UPADHYAYROYAL FANTASY CONSTRUCTIONS PVT LTD29/01/2021
CC006000000209527JAYSHANKAR SHUKLA AND SUMAN SHUKLAROYAL FANTASYCONSTRUCTIONS PVT. LTD24/12/2021
CC006000000385417Melroy Francis PereiraRoyal Fantasy Constructions Private Limited27/04/2023
CC12601391Sanjay Tukaram MankarRoyal Fantasy Constructions Private Limited13/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Dec 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed168

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 168 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form-1 Q4 Phase-2.pdf6 May 2026
Withdrawal Update Form 2File: Form-2 Q4 Phase-2.pdf6 May 2026
Withdrawal Update Form 3File: Form-3 Q4 Phase-2.pdf6 May 2026
Withdrawal Update Form 1File: Application Form1 Phase-II Q3_With Sign.pdf3 Feb 2026
Withdrawal Update Form 1File: Application Form1 Phase-II Q3_With Sign.pdf3 Feb 2026
Withdrawal Update Form 2File: Application Form2 Phase-II Q3_With Sign.pdf3 Feb 2026
Withdrawal Update Form 2File: Application Form2 Phase-II Q3_With Sign.pdf3 Feb 2026
Withdrawal Update Form 3File: Royal Fantasy Q3 Phase II Form 3.pdf3 Feb 2026
Withdrawal Update Form 3File: Royal Fantasy Q3 Phase II Form 3.pdf3 Feb 2026
Form 2A (FY 2024-2025)File: Form-2A Phase-II Final.pdf3 Feb 2026
Withdrawal Update Form 1File: Final Form-1 Phase-II Q2.pdf7 Jan 2026
Withdrawal Update Form 2File: Form-2 Phase-II_Q2.pdf7 Jan 2026
Withdrawal Update Form 3File: Final Form-3 Phase-2 Q2.pdf7 Jan 2026
Form 5 (FY 2024-2025)File: Final Form 5_Phase 2.pdf5 Dec 2025
Withdrawal Update Form 1File: Withdrawal Application Form1_Signed.pdf11 Sep 2025
Withdrawal Update Form 2File: Withdrawal Application Form2_Signed.pdf11 Sep 2025
Withdrawal Update Form 3File: Royal Fantasy Phase II_compressed.pdf11 Sep 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf7 May 2025
Certificates of CA (Form 3)File: Form 3.pdf7 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf7 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf29 Apr 2025
Certificates of CA (Form 3)File: Form-3 Phase 2_compressed.pdf29 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf29 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Final Form 5 compressed.pdf11 Mar 2025
Declaration in FORM BFile: Form B- Affidavit Cum Declaration.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf16 Jan 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf16 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf16 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf28 Oct 2024
Certificates of CA (Form 3)File: Form 3 Phase 2 Sept 24_compressed.pdf28 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf28 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf12 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf12 Aug 2024
Certificates of CA (Form 3)File: CA Certificate Phase II_compressed.pdf12 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Phase (II).pdf2 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Phase II.pdf2 Jul 2024
Certificates of CA (Form 3)File: Form 3 Phase II_compressed.pdf2 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect (Vega C-Wing ) Certifiacte Pahse II.pdf12 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 FINAL.pdf12 Apr 2024
Certificates of CA (Form 3)File: CA Certificate-Royal Fantasy PHASE II Q3_compressed.pdf12 Apr 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 2022-23_compressed.pdf19 Jan 2024
Declaration in FORM BFile: Form B Affidavit cum Declaration.pdf4 Jan 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A.pdf4 Jan 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory.pdf4 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf14 Dec 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf14 Dec 2023
Certificates of CA (Form 3)File: Form 3 FINAL COMPRESSED.pdf14 Dec 2023
Layout approvalFile: part1 final_organized.pdf9 Dec 2023
Layout approvalFile: part2-final_organized.pdf9 Dec 2023
Layout approvalFile: part3_final_organized.pdf9 Dec 2023
Layout approvalFile: part4_final_organized.pdf9 Dec 2023
Layout approvalFile: part5_final_organized.pdf9 Dec 2023
Layout approvalFile: part6_final_organized.pdf9 Dec 2023
Layout approvalFile: part7_final_organized.pdf9 Dec 2023
Copy of Layout Approval (in case of layout)File: part1 final_organized.pdf9 Dec 2023
Copy of Layout Approval (in case of layout)File: part2-final_organized.pdf9 Dec 2023
Copy of Layout Approval (in case of layout)File: part3_final_organized.pdf9 Dec 2023
Copy of Layout Approval (in case of layout)File: part4_final_organized.pdf9 Dec 2023
Copy of Layout Approval (in case of layout)File: part5_final_organized.pdf9 Dec 2023
Copy of Layout Approval (in case of layout)File: part6_final_organized.pdf9 Dec 2023
Copy of Layout Approval (in case of layout)File: part7_final_organized.pdf9 Dec 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC Dated 03102023 Vega Building.pdf27 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC dt 05092023 Composite Building.pdf27 Nov 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase 2.pdf21 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 2.pdf21 Aug 2023
Certificates of CA (Form 3)File: FORM 3 compressed.pdf21 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate_Phase 2_.pdf18 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 2_.pdf18 May 2023
Certificates of CA (Form 3)File: PHASE II ROYAL FANTASY FORM 3_compressed.pdf18 May 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 signed_compressed (1).pdf26 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Phase 2_Final_compressed.pdf7 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Phase 2 Final_compressed.pdf1 Mar 2023
Certificates of CA (Form 3)File: Form 3 certified_compressed.pdf28 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase 2.pdf25 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 2_December 2022.pdf25 Feb 2023
Certificates of CA (Form 3)File: Royal Phase II Certified_compressed.pdf25 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect Certificate.pdf19 Dec 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Engineer Certificate.pdf19 Dec 2022
Certificates of CA (Form 3)File: Form 3 CA Certificate.pdf19 Dec 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 Architect Certificate.pdf29 Sep 2022

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Royal Fantasy Phase IIIP51800009920Andheri, Mumbai Suburban50Aug 2017OngoingJun 2025Registered original: Dec 2019Not delivered
Royal Fantasy Phase IP51800009606Andheri, Mumbai Suburban64Aug 2017CompletedJun 2022Registered original: Dec 2018Apr 2022

How this compares with Mumbai Suburban

99%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 90 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Royal Fantasy Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmRoyal Fantasy Phase IICompleted 115Lapsed / revoked 77Other 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 305 registered projects within 2 km.

Builder: Royal Fantasy Constructions Private Limited

Royal Fantasy Constructions Private Limited has 3 registrations on MahaRERA, including Royal Fantasy Phase I and Royal Fantasy Phase II. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Royal Fantasy Phase II is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Royal Fantasy Phase II?

The registered promoter entity is Royal Fantasy Constructions Private Limited, a company as per the filing. Its CIN U45200MH2008PTC182431 and GSTIN 27AADCR9796A1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Royal Fantasy Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Royal Fantasy Phase II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Royal Fantasy Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Royal Fantasy Phase II?

The professionals named in the filing: Architect: Arun Kumar Dube; Engineer: Ace Project Management Consultant; Engineer: AHMAD & ASSOCIATES; Chartered Accountant: Himani R Patel and Associates; Chartered Accountant: M N N Y & ASSOCIATES LLP; Chartered Accountant: Himani R Patel & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Royal Fantasy Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Royal Fantasy Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Royal Fantasy Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.