Completed No litigation declared Residential / Group Housing project

Royal Fantasy Phase I

By Royal Fantasy Constructions Private Limited

RG-MH-85625 · RERA P51800009606 · Last updated on MahaRERA portal: 27 Nov 2023

Source: official MahaRERA filing

Red flags

  • 3 complaints at MahaRERA
  • Completion date moved by 42 months
  • 4 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2022Possession promisedregistration recorded completed
26 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 70%
3Complaints at MahaRERAon this registration
Jump to the 97 documents Report an error

Royal Fantasy Phase I is a Residential / Group Housing project by Royal Fantasy Constructions Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800009606 on 22 Aug 2017. The registration is recorded completed; possession was promised by 30 Jun 2022. The completion date has moved by 42 months from the original filing. 3 complaints are on record with the regulator.

At a glance

Project

  • NameRoyal Fantasy Phase I
  • TypeResidential / Group Housing
  • Location
    • Andheri
    • Mumbai Suburban
    • 400093
  • Pincode400093
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800009606
  • ReraGenie IDRG-MH-85625

Builder

  • NameRoyal Fantasy Constructions Private Limited
  • Entity typeCompany
  • Managing DirectorVijay Yadav
  • DirectorUTKARSH AGARWAL
  • Other registrations2 more →
  • Completed1 of 3
  • Declared earlier projects3 →

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toJun 2022Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on22 Aug 2017
  • Promised completion30 Jun 2022
  • Revised completionRevised to 30 Jun 2022 (originally 31 Dec 2018)
  • Buildings3 building records
  • Documents filed97 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Dreamax Vega Wing A FullNA160000
Dreamax Vega Wing B FullNA160000
Dreamax Height Wing C PTC up to 12th Floor - no SaleableNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 27 Nov 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

26 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 70%.

Dreamax Vega Wing A Full100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Dreamax Vega Wing B Full100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Dreamax Height Wing C PTC up to 12th Floor - no Saleable53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure60%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks70%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 27 Nov 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes65%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes50%
Electrical meter room, sub-station, receiving stationYes60%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed51

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots51
Closed/Covered51
BuildingClosed/CoveredTotal
Dreamax Vega Wing A Full1616
Dreamax Vega Wing B Full3535

Land and ownership9

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,117 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
LandownerVillageDistrict
Vidyabhushan Khudiram UpadhyayAndheriMumbai Suburban
Vanibhushan Khudiram UpadhyayAndheriMumbai Suburban
Bharatibhushan Khudiram UpadhyayAndheriMumbai Suburban
Satyanand Chitanand UpadhyayAndheriMumbai Suburban
Bhavanand Chitanand UpadhyayAndheriMumbai Suburban
Sachitanand Chitanand UpadhyayAndheriMumbai Suburban
Vivek Chitanand UpadhyayAndheriMumbai Suburban
Vishal Sampuranad UpadhyayAndheriMumbai Suburban
Ramdular Siddhinarayan UpadhyayAndheriMumbai Suburban

Approvals and building plan

Permissible FSI10494.8
Proposed, not sanctioned10,495 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMIDC Andheri East Mumbai 400059

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectArun Kumar Dube
EngineerACE Project Management Consultant
Chartered AccountantMNNY & Associates
PartnerRole in project
Royal Fantasy Constructions Private Limited-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800008934Dec 2018 → Jun 2021

Reason as filed by the promoter1. Temporary Negative cash flow due to, • Buyers not paying dues on time • financial institutions and lenders such as NBFCs are unable to lend funds due to severe liquidity crunch faced by them in current scenario. • Poor market condition for sale 2. Other reasons: • Contractor’s inability to complete scheduled phase due to shortage of labour faced by him. • Last year disruptions due to GST & demonetization implementations. • Non-availability of sand on time. 3. Default from contactors: • Contractor’s inability to perform their contractual obligations within the timescales detailed in the Cont

EXT51800011519Dec 2018 → Jun 2022

Reason as filed by the promoter1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availability of sand on time. 3. Due to default from contractors. 4. Still there are some outstanding receivables from the buyers. 5. Also the registrations of some of the flats were still pending. 6. Applied for OC but not received till date.

EXT51800005411Dec 2018 → Jun 2020

Reason as filed by the promoterThe company and its management apprehend that the said project will not be able to be completed by this due date i.e. till 31/12/2019 due to the following reasons: 1. There was temporary negative cash flow due to buyers not paying dues on time and poor market conditions for sale. 2. Other reasons like shortage of labour, disruptions due to implementation of GST & continuous updations & non availability of sand on time. 3. Due to default from contractors.

EXT51800001127Dec 2018 → Jun 2020

Reason as filed by the promoterOur under construction real estate project is getting delayed due to several reasons as follows: 1. MCGM notified only the Draft DP sheets 2034 on 8th September 2017. Since the DP sheets had many errors, the DP/DCR 2034 was held up again. DCR-2034 was finally notified recently sometime back and MCGM has increased the FSI for building development for various categories of real estate projects. Our project is also a beneficiary of increased FSI, as already envisaged by us and proposed accordingly at the time of MahaRERA registration. Delay in finalization of DP/DCR 2034 has resulted in huge dela

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000100442Farooq Ahmed AnsariRoyal Fantasy Construction Private Limited, Mr. Sajay Saraf (Director)16/08/2019
CC006000000198477Farooq Ahmed AnsariRoyal FantansyConstructions Pvt.Ltd29/09/2021
CC006000000408539BHAGCHAND C BHANDARIROYALFANTASYCONSTRUCTION PVT LTD19/12/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Nov 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 19 Apr 2022

Documents filed97

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 97 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Commencement Certificates / NA Order for plotted developmentFile: Further CC Dated 03102023 Vega Building.pdf27 Nov 2023
Commencement Certificates / NA Order for plotted developmentFile: Further CC dt 05092023 Composite Building.pdf27 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 signed_compressed.pdf26 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: New Form 4 (Reuploaded).pdf15 Apr 2023
Architect’s Certificate on Completion of Project (Form 4)File: New Form 4.pdf6 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Phase 1 Final_compressed.pdf1 Mar 2023
OtherFile: OC Application Sale Wing A and B Shop Part 1.pdf7 Feb 2023
OtherFile: OC Application Sale Wing A and B Shop Part 2.pdf7 Feb 2023
Disclosure of sold/ booked inventoryFile: Flat booked Sold Details_compressed (1).pdf30 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase 1_compressed.pdf19 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate Phase 1_New_compressed.pdf19 Apr 2022
Certificates of CA (Form 3)File: From 3_compressed.pdf19 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Dreamax Vega A and B Phase I.pdf19 Apr 2022
Declaration about Commencement CertificateFile: Form D_MahaRERA Circular 32_Phase_1.pdf7 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate Phase 1_compressed.pdf7 Mar 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_Phase-1_Final.pdf7 Mar 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Phase 1_compressed.pdf7 Mar 2022
Disclosure of sold/ booked inventoryFile: Revised Sold and Booked Inventory.pdf7 Mar 2022
Certificates of CA (Form 3)File: form 3_compressed.pdf7 Mar 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5.pdf7 Mar 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Phase 1 Architect Certificate_compressed.pdf3 Jul 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTI Phase 1.pdf3 Jul 2021
Certificates of CA (Form 3)File: Form 3 Phase 1_compressed.pdf3 Jul 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5.pdf19 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf16 Jun 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf16 Jun 2021
Certificates of CA (Form 3)File: Form 3 Phase 1_compressed.pdf16 Jun 2021
OtherFile: OC Application.pdf16 Jun 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_compressed.pdf26 Feb 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf26 Feb 2021
Certificates of CA (Form 3)File: Form 3_compressed (5).pdf26 Feb 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect's Certificate_Phase 1_compressed.pdf28 Sep 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTI Phase 1_compressed.pdf28 Sep 2020
Certificates of CA (Form 3)File: FORM-3 -9606_compressed.pdf28 Sep 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf13 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf13 Jul 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf13 Jul 2020
Certificates of CA (Form 3)File: Form 3.pdf13 Jul 2020
Certificates of CA (Form 3)File: Form 3.pdf13 Jul 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect's Certificate.pdf26 Jun 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTI.pdf26 Jun 2020
Certificates of CA (Form 3)File: Phase 1.pdf26 Jun 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect's Certificate_Phase 1.pdf1 Feb 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTI Phase 1.pdf1 Feb 2020
Certificates of CA (Form 3)File: form 3.pdf1 Feb 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM-5.pdf1 Feb 2020
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1- Architect's Certificate_Phase 1_compressed.pdf4 Oct 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate_compressed.pdf4 Oct 2019
Certificates of CA (Form 3)File: Ca Certificate_compressed (3).pdf4 Oct 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate.pdf15 Jul 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 ENG CERTI.pdf15 Jul 2019
Certificates of CA (Form 3)File: CA Certificate1.pdf15 Jul 2019
Certificates of CA (Form 5)File: Form 5.pdf22 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate.pdf24 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate.pdf24 Nov 2018
Certificates of CA (Form 3)File: CA Certificate.pdf24 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: ENG CERTI Phase 1.pdf28 May 2018
Certificates of CA (Form 3)File: FORM 3 Phase 1.pdf28 May 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect's Certificate_Phase 1.pdf26 May 2018
OtherFile: Declaration.pdf5 Feb 2018
Proforma of Allotment letterFile: Updated Agreement for Sale (A).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated Agreement for Sale (B).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated Agreement for Sale (C).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated agreement for Sale (D).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated agreement for Sale (D).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated Agreement for Sale (E).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated Agreement for Sale (E).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated Agreement for Sale (F).pdf31 Oct 2017
Proforma of Allotment letterFile: Updated Agreement for Sale (G).pdf31 Oct 2017
Layout approvalFile: Layout Plan .pdf31 Jul 2017
Building plan approvalFile: IOD_Height.pdf31 Jul 2017
Layout approvalFile: Approved Layout Plan.pdf31 Jul 2017
Building plan approvalFile: CC_Vega.pdf31 Jul 2017
PAN CardFile: RFCPL Pan Card.pdf31 Jul 2017
Copy of the legal title reportFile: Title Report.pdf31 Jul 2017
Details of encumbrancesFile: Encumbrance Certificate.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Approved Layout Plan.pdf31 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan .pdf31 Jul 2017
Building Plan Approval (IOD)File: IOD_Height.pdf31 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 42 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is completed

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Royal Fantasy Phase I on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri6,700+ in Mumbai Suburban

2 kmRoyal Fantasy Phase ICompleted 102Lapsed / revoked 56Other 87Dot size: filed unitsN

Filed coordinates, straight-line distance. 245 registered projects within 2 km.

Builder: Royal Fantasy Constructions Private Limited

Royal Fantasy Constructions Private Limited has 3 registrations on MahaRERA, including Royal Fantasy Phase I and Royal Fantasy Phase II. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Royal Fantasy Phase I is delayed beyond 30 Jun 2022?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Royal Fantasy Phase I?

The registered promoter entity is Royal Fantasy Constructions Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Royal Fantasy Phase I?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Royal Fantasy Phase I?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Royal Fantasy Phase I?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Royal Fantasy Phase I?

The professionals named in the filing: Architect: Arun Kumar Dube; Engineer: ACE Project Management Consultant; Chartered Accountant: MNNY & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Royal Fantasy Phase I?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Royal Fantasy Phase I. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Royal Fantasy Phase I to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.