ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / MAHAKALI HILLS

Registered No litigation declared Others project

MAHAKALI HILLS

By Mohid Construction Co

RG-MH-30540 · RERA P51800031191 · Last updated on MahaRERA portal: 25 May 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 24 months from the original
11 of 33Construction stages doneacross 5 buildings; furthest along: Staircases, 90%
90 of 305Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 106 documents Report an error

MAHAKALI HILLS is a Others project by Mohid Construction Co in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800031191 on 11 Oct 2021. Possession is promised by 31 Dec 2026. The completion date has moved by 24 months from the original filing. 215 of the 305 units on this registration are recorded sold or booked, and 11 of 33 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameMAHAKALI HILLS
  • TypeOthers
  • Location
    • MAHAKALI CAVES ROAD
    • ANDHERI EAST
    • Andheri
    • Mumbai Suburban
    • 400093
  • Pincode400093
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800031191
  • ReraGenie IDRG-MH-30540

Builder

  • NameMohid Construction Co
  • Entity typeOthers
  • ProprietorZAHUR MOHID Abdulaziz Mohid
  • Other registrations2 more →
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects1 →

Key dates

this monthRegisteredOct 2021First promiseDec 2024Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Oct 2021
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 31 Dec 2024)
  • Buildings5 building records
  • Documents filed106 files

Current status

70%215 of 305 units booked
53.1%Work done, per cost certificate

Figures as on 25 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C WINGNA808131112
D WINGNA809331124
E WINGNA50292049
A WING-REHABNA7001212
B WING-REHABNA70088

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 25 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

11 of 33 construction stages are filed complete across 5 buildings. The stage furthest along is Staircases, at 90%.

C WING56%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises30%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks80%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
D WING65%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.40%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
E WING11%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth25%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
A WING-REHABNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable
B WING-REHABNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 25 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingNoNot applicable
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,097 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on25 Jul 2025

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI11913.04
Proposed, not sanctioned11,913 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchUpper Ground floor, shop no 18, Lodha Amara MLCP retail, Opp sandozbaug,Kholset road,Thane400607
Estimated costRs 63.25 cr
Cost incurredRs 33.61 cr
Work done53.14%
BuildingWingEstimatedIncurred
C WINGNARs 13.50 crRs 6.25 cr
D WINGNARs 12.75 crRs 11.44 cr
B WING-REHABNARs 11.00 crRs 1.25 cr
A WING-REHABNARs 10.75 crRs 9.31 cr
E WINGNARs 8.25 crRs 64.46 lakh
-NARs 7.00 crRs 4.72 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectIBADUT REHMAN MOMIN
EngineerZiaur Rehman Khan
Chartered AccountantMahesh Bajaj
Chartered AccountantADP & Associates
PartnerRole in project
Mohid Construction Co-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025105Dec 2024 → Dec 2026

Reason as filed by the promoterWe hereby declare that our above project about to expire on31.12.2024 and we have submitted our application for extension for completion of the project to be valid till 31.12.2026 u/s of 7(3) of RERA. Our Project got delayed due to COVID impact, labour problem, timely payment or non-payment of instalments by allottees, marketing issues & financial crunch, etc. We have submitted affidavit in Form B, justification & Request for Extension of project apart of Resolution copy signed by more than requisite number of allottees.

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12604330Neel Umesh RaoMohid Construction Co10/07/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Sep 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Nov 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 25 Aug 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Nov 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed106

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 106 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 31-03-2026 mahakali.pdf25 May 2026
Withdrawal Update Form 2File: FORM_2_Rera_Certificates-Mahakali_Hills_Qtr_ending_31-03-26.pdf25 May 2026
Withdrawal Update Form 3File: Form 3 Mahakali Hills 31-03-2026_compressed.pdf25 May 2026
Withdrawal Update Form 1File: FORM 1 MAHAKALI HILLS-Qtr 31-12-25 (2).pdf20 Jan 2026
Withdrawal Update Form 2File: FORM 2 MAHAKALI HILLS-Qtr 31-12-25.pdf20 Jan 2026
Withdrawal Update Form 3File: FORM 3 MAHAKALI HILLS-Qtr 31-12-2025_compressed.pdf20 Jan 2026
Form 5 (FY 2024-2025)File: Mahakali Form 5 FY 2024-25.pdf8 Dec 2025
Withdrawal Update Form 1File: Form 1.pdf17 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf17 Nov 2025
Withdrawal Update Form 1File: Form 1.pdf17 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf17 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf17 Nov 2025
Withdrawal Update Form 2File: Form 2.pdf17 Nov 2025
Withdrawal Update Form 3File: Form 3_compressed (3).pdf17 Nov 2025
Withdrawal Update Form 3File: Form 3_compressed (3).pdf17 Nov 2025
Withdrawal Update Form 3File: Form 3_compressed (3).pdf17 Nov 2025
Withdrawal Update Form 1File: form 1.pdf19 Sep 2025
Withdrawal Update Form 1File: form 1.pdf19 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2025
Withdrawal Update Form 2File: Form 2.pdf19 Sep 2025
Withdrawal Update Form 3File: Form 3 Mahakali Hills_1.pdf19 Sep 2025
Withdrawal Update Form 3File: Form 3 Mahakali Hills_1.pdf19 Sep 2025
Form 1File: Mohid Form 1 Mahakali hills 31325.pdf4 Jun 2025
Form 2File: Mohid Form 2 Mahakali hills 31325.pdf4 Jun 2025
Form 3File: Mohid Form 3 Mahakali hills 31325.pdf4 Jun 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 31_12_24 Mahakali Hills.pdf6 Mar 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Mahakali Hills 31_12_24.pdf6 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 MAHAKALI HILLS 30_9_24.pdf3 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_FY 23-24_signed.pdf21 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 MAHAKALI -C and D WING 30_09_24.pdf9 Dec 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_FY 31_3_24 Agreed and Aceepted.pdf9 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_FY 31_3_24 Agreed and Accepted.pdf9 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure sold inventory_30_9_24.pdf26 Nov 2024
Declaration in FORM BFile: Form B.pdf25 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form3- 30_09_2024 Mahakali Hills.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 MAHAKALI HILLS 30_9_2024.pdf25 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form3- 30_09_2024 Mahakali Hills.pdf25 Nov 2024
Commencement Certificates / NA Order for plotted developmentFile: CC -Mahakali Hills_compressed.pdf25 Nov 2024
Declaration about Commencement CertificateFile: Declaration about CC_Format D.pdf25 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A 31_3_24 Mahakali Hills.pdf25 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Mahakali Hills -A wing 30_9_24.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form_3 AS ON _30_09_24.pdf18 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM_2_Rera_Certificates-_Engineer_30_9_24.pdf18 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New FORM 3 30-06-24_compressed.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New FROM 3 31-03-24.pdf12 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: New From 3 31-12-23_compressed.pdf12 Nov 2024
Declaration about all RERA Designated Bank Accounts (Format A)File: Order no 56 _FORMAT A.pdf22 Oct 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Kotak Bank Letter_Format B.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahakali Hills Arch cert WING A Qtr ends 31 12 23.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahakali Hills Arch Cert WING-C D Qtr ends 3112 23.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahakali Hills Arch Cert WING A Qtr ends 31 3 24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahakali Hills Arch Cert WING C D Qtr ends 31 3 24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE A WING_30 6 24.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE C D WING_30 6 24.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 30 6 24_compressed.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 31 3 24_compressed.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: form3 31 12 2023_compressed.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3_FORM_2_Rera_Certificates-_Engineer_30 6 24.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_FORM_2_Rera_Certificates-_Engineer_31 3 24.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1_FORM_2_Rera_Certificates-_Engineer_31 12 23.pdf8 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Mohid Form 5 Mahakali hills FY 2022-23.pdf29 Dec 2023
Layout approvalFile: a plans scan.pdf25 Nov 2023
Copy of Layout Approval (in case of layout)File: a plans scan.pdf25 Nov 2023
Layout approvalFile: 1_1-2.pdf18 Nov 2023
Layout approvalFile: 1_3-end.pdf18 Nov 2023
Layout approvalFile: 2_1-2.pdf18 Nov 2023
Layout approvalFile: 2_3-end.pdf18 Nov 2023
Layout approvalFile: 3_1-2.pdf18 Nov 2023
Layout approvalFile: 3_3-end.pdf18 Nov 2023
Layout approvalFile: 4.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: 1_1-2.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: 1_3-end.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: 2_1-2.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: 2_3-end.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: 3_1-2.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: 3_3-end.pdf18 Nov 2023
Copy of Layout Approval (in case of layout)File: 4.pdf18 Nov 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Mahakali Hills -Form 3.pdf2 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 03 23.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 06 23.pdf19 Oct 2023

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered late
ProjectLocationFlatsStatusPromisedDelivered
MOHID HEIGHTS825 PART OF VILLAGE AMBIVALI SR NO 111D ANDHERI MUMBAI193CompletedJan 2007Late, Oct 2011

How this compares with Mumbai Suburban

70%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 24 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MAHAKALI HILLS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ANDHERI EAST6,700+ in Mumbai Suburban

2 kmMAHAKALI HILLSCompleted 162Lapsed / revoked 94Other 163Dot size: filed unitsN

Filed coordinates, straight-line distance. 419 registered projects within 2 km.

Builder: Mohid Construction Co

Mohid Construction Co has 3 registrations on MahaRERA, including SWIZ HEIGHTS and MAHAKALI HILLS. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MAHAKALI HILLS is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MAHAKALI HILLS?

The registered promoter entity is Mohid Construction Co, an others as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MAHAKALI HILLS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MAHAKALI HILLS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MAHAKALI HILLS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MAHAKALI HILLS?

The professionals named in the filing: Architect: IBADUT REHMAN MOMIN; Engineer: Ziaur Rehman Khan; Chartered Accountant: Mahesh Bajaj; Chartered Accountant: ADP & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MAHAKALI HILLS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MAHAKALI HILLS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MAHAKALI HILLS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.