Red flags

  • Possession 1 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
0 of 33Construction stages doneacross 3 buildings; furthest along: Excavation, 0%
96 of 138Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 111 documents Report an error

Rose Gardenia Phase II is a Residential / Group Housing project by Rose Dream Developers in Pune, Maharashtra, registered with MahaRERA as P52100035063 on 4 May 2022. Possession was promised by 30 Sep 2026 and is now 1 months past that date. 42 of the 138 units on this registration are recorded sold or booked, and 0 of 33 construction stages are filed complete.

At a glance

Project

  • NameRose Gardenia Phase II
  • TypeResidential / Group Housing
  • Location
    • Sr. No. 9
    • Hissa No - B/1/1 & B/1/2
    • Kiwale
    • Pune
    • Pimpri Chinchawad (M Corp.)
    • Haveli
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100035063
  • ReraGenie IDRG-MH-79622

Builder

  • NameRose Dream Developers
  • Entity typePartnership
  • PartnersKaran Gulab Ratnani, Sunil H Ramchandani, Vishal Rajkumar Dharmani, Jeetu Kishinchand Kukreja, Navin Rajkumar Dharmani
  • Other registrations2 more →
  • No longer live1 lapsed, de-registered or revoked
  • Past their filed date2
  • Declared earlier projects1 →

Key dates

1 months past promisethis monthRegisteredMay 2022PromisedSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on4 May 2022
  • Promised completion30 Sep 2026
  • Revised completionNone
  • Buildings3 building records
  • Documents filed111 files

Current status

30%42 of 138 units booked

Figures as on 16 Oct 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
C- WingNA161482082
D- WingNA161456056
E -WINGNA60000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 16 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Excavation, at 0%.

C- Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
D- Wing0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
E -WING0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership9

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area6,165 sq m
Land owned byThe promoter, with other names on the file
Named landowners9
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Oct 2025
LandownerVillageDistrict
Mr Prathmesh KochetaLatur (M Cl)Latur
Mrs Badambai KochetaLatur (M Cl)Latur
Mr Bharat AgroyaPune (M Corp.)Pune
Mrs LaxmiBai HalikarLatur (M Cl)Latur
Mr Sudhir HalikarLatur (M Cl)Latur
Mr Ninad PatilPune (M Corp.)Pune
Mrs Ananda KochetaLatur (M Cl)Latur
Mrs Roli AgroyaPune (M Corp.)Pune
Mrs Vaishali HalikarPune (M Corp.)Pune

Approvals and building plan

Sanctioning authoritypimpri chinchawed Municipal Corparation Authority
Permissible FSI17163.45
Proposed, not sanctioned17,163 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchDEHU ROAD

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSangram Salunke Salunke
EngineerSayabanna Sadashiv Natikar
EngineerNitin Arun Khobare
Chartered AccountantVinod Sabu
Chartered Accountantpriyesh Prakash JAIN
Chartered AccountantNilesh Raut
PartnerRole in project
Rose Dream Developers-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 22 Mar 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 22 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed111

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2022-2023)File: Form-5 RERA Audit Report FY 2022-23.pdf16 Oct 2025
Form 5 (FY 2023-2024)File: Form-5 RERA Audit Report FY 2023-24.pdf16 Oct 2025
Form 5 (FY 2024-2025)File: Form-5 RERA Audit Report FY 2024-25.pdf16 Oct 2025
Form 1File: Form-1 Architect Certificate 30062022.pdf14 Oct 2025
Form 2File: Form-2 Engineer Certificate 30062022.pdf14 Oct 2025
Form 3File: Form-3 CA Certificate 30062022.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062022.pdf14 Oct 2025
Form 1File: Form-1 Architect Certificate 31032023.pdf14 Oct 2025
Form 2File: Form-2 Engineer Certificate 31032023.pdf14 Oct 2025
Form 3File: Form-3 CA Certificate 31032023.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31032023.pdf14 Oct 2025
Form 1File: Form-1 Architect Certificate 30062023.pdf14 Oct 2025
Form 2File: Form-2 Engineer Certificate 30062023.pdf14 Oct 2025
Form 3File: Form-3 CA Certificate 30062023.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062023.pdf14 Oct 2025
Form 1File: Form-1 Architect Certificate 30092024.pdf14 Oct 2025
Form 2File: Form-2 Engineer Certificate 30092024.pdf14 Oct 2025
Form 3File: Form-3 CA Certificate 30092024.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092024.pdf14 Oct 2025
Form 1File: Form-1 Architect Certificate 31032025.pdf14 Oct 2025
Form 2File: Form-2 Engineer Certificate 31122024.pdf14 Oct 2025
Form 3File: Form-3 CA Certificate 31032025.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31032025.pdf14 Oct 2025
Form 1File: Form-1 Architect Certificate 30062025.pdf14 Oct 2025
Form 2File: Form-2 Engineer Certificate 30062025.pdf14 Oct 2025
Form 3File: Form-3 CA Certificate 30062025.pdf14 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062025.pdf14 Oct 2025
Form 2A (FY 2022-2023)File: Form-2A Quality Assurance FY 2022-23.pdf14 Oct 2025
Form 2A (FY 2023-2024)File: Form-2A Quality Assurance FY 2023-24.pdf14 Oct 2025
Form 2A (FY 2024-2025)File: Form-2A Quality Assurance FY 2024-25.pdf14 Oct 2025
Form 1File: Form-1 Architect Certificate 30092022.pdf8 Oct 2025
Form 2File: Form-2 Engineer Certificate 30092022.pdf8 Oct 2025
Form 3File: Form-3 CA Certificate 30092022.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092022.pdf8 Oct 2025
Form 1File: Form-1 Architect Certificate 31122022.pdf8 Oct 2025
Form 2File: Form-2 Engineer Certificate 31122022.pdf8 Oct 2025
Form 3File: Form-3 CA Certificate 31122022.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122022.pdf8 Oct 2025
Form 1File: Form-1 Architect Certificate 31122024.pdf8 Oct 2025
Form 2File: Form-2 Engineer Certificate 31122024.pdf8 Oct 2025
Form 3File: Form-3 CA Certificate 31122024.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122024.pdf8 Oct 2025
Form 1File: Form-1 Architect Certificate 30062024.pdf8 Oct 2025
Form 2File: Form-2 Engineer Certificate 30062024.pdf8 Oct 2025
Form 3File: Form-3 CA Certificate 30062024.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30062024.pdf8 Oct 2025
Form 1File: Form-1 Architect Certificate 31032024.pdf8 Oct 2025
Form 2File: Form-2 Engineer Certificate 31032024.pdf8 Oct 2025
Form 3File: Form-3 CA Certificate 31032024.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31032024.pdf8 Oct 2025
Form 1File: Form-1 Architect Certificate 31122023.pdf8 Oct 2025
Form 2File: Form-2 Engineer Certificate 31122023.pdf8 Oct 2025
Form 3File: Form-3 CA Certificate 31122023.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 31122023.pdf8 Oct 2025
Form 1File: Form-1 Architect Certificate 30092023.pdf8 Oct 2025
Form 2File: Form-2 Engineer Certificate 30092023.pdf8 Oct 2025
Form 3File: Form-3 CA Certificate 30092023.pdf8 Oct 2025
Disclosure of Sold and Booked InventoryFile: Sold Booked Inventory 30092023.pdf8 Oct 2025
Declaration in FORM BFile: Form B - new.pdf30 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - CA Certificate-compressed (1).pdf30 Apr 2022
Proforma of Allotment letterFile: Performa Allotment Letter.pdf30 Apr 2022
Declaration in FORM BFile: Form B.pdf21 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_compressed (1).pdf21 Apr 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA_compressed (1).pdf18 Apr 2022
Copy of the legal title reportFile: Legal Title Report.pdf14 Apr 2022
Details of encumbrancesFile: Self Declaration.pdf14 Apr 2022
Commencement Certificates / NA Order for plotted developmentFile: Declaration about CC.pdf14 Apr 2022
Declaration in FORM BFile: Form B.pdf14 Apr 2022
CERSAI detailsFile: CERSAI_Search_Report_200233162533_For_Asset_Based_Search_23_03_2022_12_56_55_816.pdf23 Mar 2022
Layout approvalFile: scan0675 1_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 2_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 3_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 4_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 5_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 6_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 7_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 8_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 9_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 11_compressed.pdf22 Mar 2022
Layout approvalFile: scan0675 12_compressed.pdf22 Mar 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsStatusPromisedDelivered
Rose GardeniaS no 9 B P Kiwale Pune182CompletedJan 2024Jan 2024

How this compares with Pune

30%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rose Gardenia Phase II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kiwale, Pune13,700+ in Pune

2 kmRose Gardenia Phase IICompleted 65Lapsed / revoked 35Other 127Dot size: filed unitsN

Filed coordinates, straight-line distance. 227 registered projects within 2 km.

Builder: Rose Dream Developers

Rose Dream Developers has 3 registrations on MahaRERA, including Rose Galaxy and Rose Gardenia. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Rose Gardenia Phase II is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rose Gardenia Phase II?

The registered promoter entity is Rose Dream Developers, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rose Gardenia Phase II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rose Gardenia Phase II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rose Gardenia Phase II?

The professionals named in the filing: Architect: Sangram Salunke Salunke; Engineer: Sayabanna Sadashiv Natikar; Engineer: Nitin Arun Khobare; Chartered Accountant: Vinod Sabu; Chartered Accountant: priyesh Prakash JAIN; Chartered Accountant: Nilesh Raut. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rose Gardenia Phase II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rose Gardenia Phase II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rose Gardenia Phase II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.