Home / Browse projects / Thane, Maharashtra / Rosa Oasis Phase 2

Completed No litigation declared Residential / Group Housing project

Rosa Oasis Phase 2

By Uma Enterprises

RG-MH-10912 · RERA P51700005311 · Last updated on MahaRERA portal: 5 Sep 2022

Source: official MahaRERA filing

Red flags

  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2019Possession promisedregistration recorded completed
28 of 33Construction stages doneacross 3 buildings; furthest along: Internal walls, 98%
0Complaints at MahaRERAon this registration
Jump to the 37 documents Report an error

Rosa Oasis Phase 2 is a Residential / Group Housing project by Uma Enterprises in Thane, Maharashtra, registered with MahaRERA as P51700005311 on 11 Aug 2017. The registration is recorded completed; possession was promised by 31 Dec 2019. The completion date has moved by 12 months from the original filing.

At a glance

Project

  • NameRosa Oasis Phase 2
  • TypeResidential / Group Housing
  • Location
    • Thane (M Corp.)
    • Thane
    • 400615
  • Pincode400615
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700005311
  • ReraGenie IDRG-MH-10912

Builder

  • NameUma Enterprises
  • Entity typePartnership
  • PartnersJagdish Kanayalal Khetwani, Naresh Sudama Khetwani, Suresh Devichand Mehta, Manoj Sudama Khetwani, Manoj Girdharilal Matlani, Jayesh Lakhamshi Malde, Jayantilal Pukhraj Sanghvi, Umesh Dahyalal Nathani, Paresh Dahyalal Nathani, Dhirajlal Govind Patel, Hasnraj Danabhai Patel, Jitendra Manilal Patel and 2 more
  • Other registrations1 more →
  • Completed2 of 2

Key dates

this monthRegisteredAug 2017First promiseDec 2018Revised toDec 2019Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on11 Aug 2017
  • Promised completion31 Dec 2019
  • Revised completionRevised to 31 Dec 2019 (originally 31 Dec 2018)
  • Buildings3 building records
  • Documents filed37 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Bldg No 3NA240000
Bldg no 4NA240000
Bldg no 5NA240000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 5 Sep 2022, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

28 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Internal walls, at 98%.

Bldg No 3100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bldg no 4100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Bldg no 597%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities15

As on 5 Sep 2022, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes70%
Street LightingYes85%
Community BuildingsYes80%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes60%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes55%
Open ParkingYes75%

Parking filed266

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots266
Closed/Covered237
Open Space29
BuildingClosed/CoveredOpen SpaceTotal
Bldg No 3801090
Bldg no 4771087
Bldg no 580989

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,473 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Darshan EnterprisesThane (M Corp.)Thane

Approvals and building plan

Permissible FSI13192.91
Proposed, not sanctioned13,193 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNear Muchala Polytechnic College G B Road Thane West 400615

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectShri Suvarna Ghosh
EngineerR C Tipnis
PartnerRole in project
Uma Enterprises-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51700001103Dec 2018 → Dec 2019

Reason as filed by the promoterThe fire department of Thane municipal corporation has revised norms for firefighting equipment. Additional provision for firefighting sprinklers had to be created in all the residential units forming part of building number 3, 4 and 5. Occupancy certificate for building number 3 has been granted, occupancy certificate for building number 4 has been applied and we have applied for NOC from the concerned departments for grant of occupancy certificate for building number 5.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 28 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed37

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: BUILDING NO-3 SOCIETY CERTIFICATE.pdf5 Sep 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: BUILDING NO-4.pdf5 Sep 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: BUILDING NO-5.pdf5 Sep 2022
Certificates of Architect (Form 4)File: Form 4 Oasis Phase 2.pdf29 May 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate Ph 2 7th.pdf11 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certi Ph 2 7th.pdf11 Feb 2019
Certificates of CA (Form 3)File: Ca Uma Phase 2 7th.pdf11 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Oasis Form 1 uma phase 2.pdf17 Nov 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng cer ph2 6th.pdf17 Nov 2018
Certificates of CA (Form 3)File: Ca Uma Phase 2 6th.pdf17 Nov 2018
Certificates of CA (Form 5)File: Form 5_Uma Enterprises.pdf30 Oct 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: architect certificate phase 2 5th-ilovepdf-compressed.pdf9 Aug 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer cert ph 2 5th.pdf9 Aug 2018
Certificates of CA (Form 3)File: Ca uma Phase 2 5th.pdf9 Aug 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: ROSA OASIS Ph 2 soc letter.pdf19 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: form 1 uma ph 2 4th.pdf11 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: engineer certi ph 2 4th.pdf11 May 2018
Certificates of CA (Form 3)File: Ca Uma Phase 2 4th.pdf11 May 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer certi phase 2 3rd.pdf8 Feb 2018
Certificates of CA (Form 3)File: Ca Certifi phase 2 3rd-compressed.pdf8 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architech Certificate (Suvarna Ghosh).pdf10 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Roasis.pdf10 Nov 2017
Certificates of CA (Form 3)File: Uma CA 2 .pdf10 Nov 2017
Layout approvalFile: 01 cop1y.pdf28 Jul 2017
Building plan approvalFile: Copy of IOD.pdf28 Jul 2017
PAN CardFile: UMA ENT- PAN CARD.pdf28 Jul 2017
Copy of the legal title reportFile: Title Certificate Rosa Oasis.pdf28 Jul 2017
Details of encumbrancesFile: Encumbrance certificate.pdf28 Jul 2017
Copy of Layout Approval (in case of layout)File: 01 cop1y.pdf28 Jul 2017
Building Plan Approval (IOD)File: Copy of IOD.pdf28 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC dated 03 03 2017.pdf28 Jul 2017
Declaration in FORM BFile: Declaration from B.pdf28 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect certificate form 1.pdf28 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineer Certificate form 2.pdf28 Jul 2017
Certificates of CA (Form 3)File: CA certificate Form 3.pdf28 Jul 2017
Proforma of Allotment letterFile: Oasis Flat Sale Agreement.pdf28 Jul 2017
Proforma of Allotment letterFile: Allotment of Flat Rosa Oasis.pdf28 Jul 2017

How this compares with Thane

24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Rosa Oasis Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Thane (M Corp.)7,600+ in Thane

2 kmRosa Oasis Phase 2Completed 75Lapsed / revoked 25Other 50Dot size: filed unitsN

Filed coordinates, straight-line distance. 150 registered projects within 2 km.

Builder: Uma Enterprises

Uma Enterprises has 2 registrations on MahaRERA, including Rosa Oasis Phase 2 and Rosa Oasis Phase 3. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Rosa Oasis Phase 2 is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Rosa Oasis Phase 2?

The registered promoter entity is Uma Enterprises, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Rosa Oasis Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Rosa Oasis Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Rosa Oasis Phase 2?

The professionals named in the filing: Architect: Shri Suvarna Ghosh; Engineer: R C Tipnis. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Rosa Oasis Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Rosa Oasis Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Rosa Oasis Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.