Registered Litigation declared Residential / Group Housing project

ROHAN ANANTA PHASE III

By ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED

RG-MH-03464 · RERA P52100019997 · Last updated on MahaRERA portal: 27 Aug 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • Completion date moved by 9 months
  • 1 extension taken
  • Rs 163.46 crore secured on the land, in favour of Aditya Birla Finance Limited

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 9 months from the original
50 of 55Construction stages doneacross 5 buildings; furthest along: Stilt Floor, 0%
5 of 435Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 147 documents Report an error

ROHAN ANANTA PHASE III is a Residential / Group Housing project by ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100019997 on 15 Mar 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 9 months from the original filing. 430 of the 435 units on this registration are recorded sold or booked, and 50 of 55 construction stages are filed complete.

At a glance

Project

  • NameROHAN ANANTA PHASE III
  • TypeResidential / Group Housing
  • Location
    • Mumbai Bengaluru Bypass
    • Tathawade
    • Tathwade
    • Mulshi
    • Pune
    • 411033
  • Pincode411033
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100019997
  • ReraGenie IDRG-MH-03464

Builder

  • NameROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45202PN2001PTC016352
  • GSTIN27AABCR8171R1ZL
  • DirectorsSUHAS KUSHALCHAND LUNKAD, SANJAY KUSHALCHAND LUNKAD, MILIND KUSHALCHAND LUNKAD, DEEPAK KUSHALCHAND BHATEWARA
  • Other registrations27 more →
  • Completed15 of 28
  • Declared earlier projects15 →

Key dates

this monthRegisteredMar 2019First promiseMar 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Mar 2019
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2026)
  • Buildings5 building records
  • Documents filed147 files

Current status

99%430 of 435 units booked
104.3%Work done, per cost certificate

Figures as on 27 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING B1NA141184084
WING B2NA14084084
WING B3NA14084084
WING B4NA14086086
WING CNA11097097

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 27 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

50 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 0%.

WING B191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING B491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
WING C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes100%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes0%

Parking filed411

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots411
Closed/Covered392
Open Space19
BuildingClosed/CoveredOpen SpaceTotal
WING B158058
WING B290595
WING B386995
WING B466571
WING C92092

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,544 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Finance Limited
Secured amountRs 163.46 crore
Declared on30 Sep 2024

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI23175.72
Proposed, not sanctioned5,216 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAXIS BANK LTD PUNE MAIN, INDRA PUSHTI, OPP FERGUSSON COLLEGE GATE NO 2, PUNE 411004
Estimated costRs 441.61 cr
Cost incurredRs 460.46 cr
Work done104.27%
BuildingWingEstimatedIncurred
WING B1NARs 85.20 crRs 88.97 cr
WING B2NARs 85.20 crRs 88.97 cr
WING B3NARs 85.20 crRs 88.97 cr
WING B4NARs 85.20 crRs 88.97 cr
WING CNARs 85.20 crRs 88.97 cr
-NARs 15.61 crRs 15.61 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnkur Associates
ArchitectAr Shashank P Phadke
EngineerMahesh Balurgi
EngineerJitendra Kumar Jain -
Chartered AccountantKhandelwal Jain & Associates
Chartered AccountantGolesha & Company
PartnerRole in project
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA21082622320Mar 2026 → Dec 2026

Reason as filed by the promoterThe delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Full Occupancy Certificate for the said Project in three parts for Wing B1 and Wing B2, Wing B3 and Wing B4 and Wing C as on dated 06/05/2024, 06/11/2023 and 17/02/2023 respectively and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, permissible built-up area, total units, s

Litigation declared2

CaseCourtStatus
1318/2018/2018Joint CJSDSuit filed by promoter Summons to defendant
1318/2018Joint CJSDOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 14 Feb 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Oct 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Feb 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 7 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Feb 2025

Documents filed147

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 147 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf27 Aug 2026
Withdrawal Update Form 2File: Form 2 Rohan Ananta P III.pdf27 Aug 2026
Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf27 Aug 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf21 Aug 2026
Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf21 Aug 2026
Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf21 Aug 2026
Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf21 Aug 2026
Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf21 Aug 2026
Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf21 Aug 2026
Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf21 Aug 2026
Form 2A (FY 2025-2026)File: Form 2A_FY_2024-25- Ph III Signed.pdf21 Aug 2026
Form 2A (FY 2024-2025)File: Rohan ananta Phase 3.pdf1 Oct 2025
Form 5 (FY 2024-2025)File: Rohan Ananta Phase 3.pdf15 Sep 2025
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 with OC.pdf18 Feb 2025
Other - TechnicalFile: Form 4 with OC.pdf18 Feb 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Ananta Phase 3 FY 23-24.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Ananta Phase 3 FY 23-24.pdf9 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Anata P III Jun 24.pdf20 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rohan Ananta P III.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Rohan Ananta III.pdf20 Jul 2024
Certificates of CA (Form 3)File: Rohan Ananta P3 June 24.pdf20 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Rohan Ananta Ph 3 Mar 24.pdf20 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Rohan Ananta Ph 3 Mar 24.pdf20 Apr 2024
Form 2AFile: Inventory Update Rohan Ananta Ph 3 Mar 24.pdf20 Apr 2024
Form 2AFile: Quality Assurance Rohan Ananta Ph 3 Mar 24.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: Inventory Update Rohan Ananta Ph 3 Mar 24.pdf20 Apr 2024
Certificates of CA (Form 3)File: CA Cert Rohan Anata Ph 3 Mar 24.pdf20 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Rohan Ananta Ph 3 Dec 23.pdf20 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Rohan Ananta Ph III Dec 23.pdf20 Jan 2024
Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Ph 3 Dec 23.pdf20 Jan 2024
Certificates of CA (Form 3)File: CA Cert Rohan Ananta Ph 3 Dec 23.pdf20 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Ananta phase 3 Sep -23.pdf19 Oct 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta III Sep 23.pdf19 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Phase 3 Sep 23.pdf19 Oct 2023
Certificates of CA (Form 3)File: CA Cert Rohan Ananta Phase 3 Sep 23.pdf19 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 23 ANANTA PH 3.pdf30 Sep 2023
Other - TechnicalFile: Completion Certificate C Wing.pdf24 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Cert Ananta Ph 3.pdf20 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ananta Ph 3.pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Ph 3.pdf20 Jul 2023
Certificates of CA (Form 3)File: Form 3 CA Cert Ananta Ph 3.pdf20 Jul 2023
Disclosure of sold/ booked inventoryFile: Inv Update Q4 Ananta 3.pdf26 Apr 2023
Certificates of CA (Form 3)File: CA Cert Ananta Ph 3 Q4.pdf26 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta Ph 3 Q4.pdf20 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta Ph 3 Q4.pdf20 Apr 2023
Form 2AFile: Form 2A Q4 Ananta Ph 3.pdf20 Apr 2023
Certificates of CA (Form 3)File: CA Cert Ananta Ph 3 Q4.pdf20 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta 3 Dec 22.pdf20 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta 3 Dec 22.pdf20 Jan 2023
Disclosure of sold/ booked inventoryFile: Inv update Ananta 3 Dec 22.pdf20 Jan 2023
Certificates of CA (Form 3)File: CA Cert Ananta 3 Dec 22.pdf20 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta Phase 3 Sep 22.pdf7 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta Phase 3 Sep 22.pdf7 Oct 2022
Disclosure of sold/ booked inventoryFile: Inv Update Ananta 3 Sep 22.pdf7 Oct 2022
Certificates of CA (Form 3)File: CA Cert Ananta Phase III Sep 22.pdf7 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 3 Ananta III FY 21 22.pdf30 Sep 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ananta Ph 3.pdf7 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ananta Ph 3.pdf7 Jul 2022
Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Ph 3.pdf7 Jul 2022
Certificates of CA (Form 3)File: Form 3 Ananta Ph 3.pdf7 Jul 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ananta Ph 3 Mar 22.pdf7 Apr 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta Phase III Mar 22.pdf7 Apr 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A QA Certificate_Ananta Ph 3 Mar 22.pdf7 Apr 2022
Disclosure of sold/ booked inventoryFile: Inventory Ananta Ph 3 Mar 22.pdf7 Apr 2022
Certificates of CA (Form 3)File: Form 3 Ananta Ph 3 Mar 22.pdf7 Apr 2022
Certificates of CA (Form 3)File: CA Cert Dec 21 Ananta III.pdf28 Feb 2022
Disclosure of sold/ booked inventoryFile: Ananta III Dec 21.pdf24 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta Phase III Dec 21.pdf7 Jan 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Ananta III Dec21.pdf7 Jan 2022
Layout approvalFile: Revised sanction Ananta.pdf7 Oct 2021
Copy of Layout Approval (in case of layout)File: Revised sanction Ananta.pdf7 Oct 2021
Commencement Certificates / NA Order for plotted developmentFile: Revised CC Ananta.pdf7 Oct 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ananta Phase III Sept 21.pdf7 Oct 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ananta Phase III Engg Sep 21.pdf7 Oct 2021
Form 2AFile: Ananta Phase III 2A - Sep 21.pdf7 Oct 2021

Promoter's earlier projects4

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

4 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Rohan Ekam Phase 2PR1261012502532Balewadi, Pune100Feb 2026OngoingMar 2030Not due yet
Rohan Ekam Phase 1P52100052298Balewadi, Pune414Aug 2023OngoingDec 2027Not due yet
ROHAN VITIP52100046719Wakad, Pune93Sep 2022OngoingDec 2027Registered original: Dec 2025Not due yet
ROHAN ANAND PHASE IIP52100023451SOMATANE PHATA, Pune241Dec 2019OngoingDec 2026Registered original: Dec 2025Not due yet

How this compares with Pune

99%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 9 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ROHAN ANANTA PHASE III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Tathawade13,700+ in Pune

2 kmROHAN ANANTA PHASE IIICompleted 107Lapsed / revoked 37Other 111Dot size: filed unitsN

Filed coordinates, straight-line distance. 255 registered projects within 2 km.

Builder: ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED

ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED has 28 registrations on MahaRERA, including ROHAN KRITIKA WINGS A C and ROHAN LEHER 2 WING A. Its filings disclose 15 earlier MahaRERA projects: declares 9 of 10 past projects completed on time. Litigation is declared on 8 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if ROHAN ANANTA PHASE III is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ROHAN ANANTA PHASE III?

The registered promoter entity is ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45202PN2001PTC016352 and GSTIN 27AABCR8171R1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ROHAN ANANTA PHASE III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for ROHAN ANANTA PHASE III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ROHAN ANANTA PHASE III?

The professionals named in the filing: Architect: Ankur Associates; Architect: Ar Shashank P Phadke; Engineer: Mahesh Balurgi; Engineer: Jitendra Kumar Jain -; Chartered Accountant: Khandelwal Jain & Associates; Chartered Accountant: Golesha & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ROHAN ANANTA PHASE III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ROHAN ANANTA PHASE III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ROHAN ANANTA PHASE III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.