Home / Browse projects / Pune, Maharashtra / ROHAN ANANTA PHASE III
ROHAN ANANTA PHASE III
By ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
RG-MH-03464 · RERA P52100019997 · Last updated on MahaRERA portal: 27 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- Completion date moved by 9 months
- 1 extension taken
- Rs 163.46 crore secured on the land, in favour of Aditya Birla Finance Limited
Clear
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
ROHAN ANANTA PHASE III is a Residential / Group Housing project by ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100019997 on 15 Mar 2019. Possession is promised by 31 Dec 2026. The completion date has moved by 9 months from the original filing. 430 of the 435 units on this registration are recorded sold or booked, and 50 of 55 construction stages are filed complete.
At a glance
Project
- NameROHAN ANANTA PHASE III
- TypeResidential / Group Housing
- Location
- Mumbai Bengaluru Bypass
- Tathawade
- Tathwade
- Mulshi
- Pune
- 411033
- Pincode411033
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100019997
- ReraGenie IDRG-MH-03464
Builder
- NameROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
- Entity typeCompany
- CINU45202PN2001PTC016352
- GSTIN27AABCR8171R1ZL
- DirectorsSUHAS KUSHALCHAND LUNKAD, SANJAY KUSHALCHAND LUNKAD, MILIND KUSHALCHAND LUNKAD, DEEPAK KUSHALCHAND BHATEWARA
- Other registrations27 more →
- Completed15 of 28
- Declared earlier projects15 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on15 Mar 2019
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2026)
- Buildings5 building records
- Documents filed147 files
Current status
Figures as on 27 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| WING B1 | NA | 14 | 11 | 84 | 0 | 84 |
| WING B2 | NA | 14 | 0 | 84 | 0 | 84 |
| WING B3 | NA | 14 | 0 | 84 | 0 | 84 |
| WING B4 | NA | 14 | 0 | 86 | 0 | 86 |
| WING C | NA | 11 | 0 | 97 | 0 | 97 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 27 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
50 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Stilt Floor, at 0%.
WING B191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING B491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
WING C91%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 27 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 100% |
| Open Parking | Yes | 0% |
Parking filed411
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| WING B1 | 58 | 0 | 58 |
| WING B2 | 90 | 5 | 95 |
| WING B3 | 86 | 9 | 95 |
| WING B4 | 66 | 5 | 71 |
| WING C | 92 | 0 | 92 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| WING B1 | NA | Rs 85.20 cr | Rs 88.97 cr |
| WING B2 | NA | Rs 85.20 cr | Rs 88.97 cr |
| WING B3 | NA | Rs 85.20 cr | Rs 88.97 cr |
| WING B4 | NA | Rs 85.20 cr | Rs 88.97 cr |
| WING C | NA | Rs 85.20 cr | Rs 88.97 cr |
| - | NA | Rs 15.61 cr | Rs 15.61 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ankur Associates |
| Architect | Ar Shashank P Phadke |
| Engineer | Mahesh Balurgi |
| Engineer | Jitendra Kumar Jain - |
| Chartered Accountant | Khandelwal Jain & Associates |
| Chartered Accountant | Golesha & Company |
| Partner | Role in project |
|---|---|
| ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe delay in the completion of the real estate project has been primarily caused by a delay in OC. The project is 100% completed, and we have received the Full Occupancy Certificate for the said Project in three parts for Wing B1 and Wing B2, Wing B3 and Wing B4 and Wing C as on dated 06/05/2024, 06/11/2023 and 17/02/2023 respectively and we have also initiated the process for the possession as well. However there is mismatch occurred in certain details on the MahaRERA profile as compared with the sanctioned plans, such as the sanctioned built-up area, permissible built-up area, total units, s
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 1318/2018/2018 | Joint CJSD | Suit filed by promoter Summons to defendant |
| 1318/2018 | Joint CJSD | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 14 Feb 2019 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 7 Oct 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 14 Feb 2019 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 7 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 18 Feb 2025
Documents filed147
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 147 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 27 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 Rohan Ananta P III.pdf | 27 Aug 2026 |
| Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf | 27 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 1File: Form 1 - Architect Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 2File: Form 2 - Engineer Certificate.pdf | 21 Aug 2026 |
| Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf | 21 Aug 2026 |
| Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf | 21 Aug 2026 |
| Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf | 21 Aug 2026 |
| Withdrawal Update Form 3File: Rohan Ananta P3 June 24.pdf | 21 Aug 2026 |
| Form 2A (FY 2025-2026)File: Form 2A_FY_2024-25- Ph III Signed.pdf | 21 Aug 2026 |
| Form 2A (FY 2024-2025)File: Rohan ananta Phase 3.pdf | 1 Oct 2025 |
| Form 5 (FY 2024-2025)File: Rohan Ananta Phase 3.pdf | 15 Sep 2025 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Form 4 with OC.pdf | 18 Feb 2025 |
| Other - TechnicalFile: Form 4 with OC.pdf | 18 Feb 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Ananta Phase 3 FY 23-24.pdf | 9 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - Ananta Phase 3 FY 23-24.pdf | 9 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Anata P III Jun 24.pdf | 20 Jul 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Rohan Ananta P III.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Rohan Ananta III.pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: Rohan Ananta P3 June 24.pdf | 20 Jul 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Rohan Ananta Ph 3 Mar 24.pdf | 20 Apr 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Rohan Ananta Ph 3 Mar 24.pdf | 20 Apr 2024 |
| Form 2AFile: Inventory Update Rohan Ananta Ph 3 Mar 24.pdf | 20 Apr 2024 |
| Form 2AFile: Quality Assurance Rohan Ananta Ph 3 Mar 24.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Update Rohan Ananta Ph 3 Mar 24.pdf | 20 Apr 2024 |
| Certificates of CA (Form 3)File: CA Cert Rohan Anata Ph 3 Mar 24.pdf | 20 Apr 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Rohan Ananta Ph 3 Dec 23.pdf | 20 Jan 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Rohan Ananta Ph III Dec 23.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Ph 3 Dec 23.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: CA Cert Rohan Ananta Ph 3 Dec 23.pdf | 20 Jan 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Cert Ananta phase 3 Sep -23.pdf | 19 Oct 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta III Sep 23.pdf | 19 Oct 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Phase 3 Sep 23.pdf | 19 Oct 2023 |
| Certificates of CA (Form 3)File: CA Cert Rohan Ananta Phase 3 Sep 23.pdf | 19 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 23 ANANTA PH 3.pdf | 30 Sep 2023 |
| Other - TechnicalFile: Completion Certificate C Wing.pdf | 24 Aug 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Arch Cert Ananta Ph 3.pdf | 20 Jul 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ananta Ph 3.pdf | 20 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Ph 3.pdf | 20 Jul 2023 |
| Certificates of CA (Form 3)File: Form 3 CA Cert Ananta Ph 3.pdf | 20 Jul 2023 |
| Disclosure of sold/ booked inventoryFile: Inv Update Q4 Ananta 3.pdf | 26 Apr 2023 |
| Certificates of CA (Form 3)File: CA Cert Ananta Ph 3 Q4.pdf | 26 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta Ph 3 Q4.pdf | 20 Apr 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta Ph 3 Q4.pdf | 20 Apr 2023 |
| Form 2AFile: Form 2A Q4 Ananta Ph 3.pdf | 20 Apr 2023 |
| Certificates of CA (Form 3)File: CA Cert Ananta Ph 3 Q4.pdf | 20 Apr 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta 3 Dec 22.pdf | 20 Jan 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta 3 Dec 22.pdf | 20 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Inv update Ananta 3 Dec 22.pdf | 20 Jan 2023 |
| Certificates of CA (Form 3)File: CA Cert Ananta 3 Dec 22.pdf | 20 Jan 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta Phase 3 Sep 22.pdf | 7 Oct 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta Phase 3 Sep 22.pdf | 7 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Inv Update Ananta 3 Sep 22.pdf | 7 Oct 2022 |
| Certificates of CA (Form 3)File: CA Cert Ananta Phase III Sep 22.pdf | 7 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 3 Ananta III FY 21 22.pdf | 30 Sep 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ananta Ph 3.pdf | 7 Jul 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Ananta Ph 3.pdf | 7 Jul 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Update Ananta Ph 3.pdf | 7 Jul 2022 |
| Certificates of CA (Form 3)File: Form 3 Ananta Ph 3.pdf | 7 Jul 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Ananta Ph 3 Mar 22.pdf | 7 Apr 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engg Cert Ananta Phase III Mar 22.pdf | 7 Apr 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A QA Certificate_Ananta Ph 3 Mar 22.pdf | 7 Apr 2022 |
| Disclosure of sold/ booked inventoryFile: Inventory Ananta Ph 3 Mar 22.pdf | 7 Apr 2022 |
| Certificates of CA (Form 3)File: Form 3 Ananta Ph 3 Mar 22.pdf | 7 Apr 2022 |
| Certificates of CA (Form 3)File: CA Cert Dec 21 Ananta III.pdf | 28 Feb 2022 |
| Disclosure of sold/ booked inventoryFile: Ananta III Dec 21.pdf | 24 Feb 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Arch Cert Ananta Phase III Dec 21.pdf | 7 Jan 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Eng Ananta III Dec21.pdf | 7 Jan 2022 |
| Layout approvalFile: Revised sanction Ananta.pdf | 7 Oct 2021 |
| Copy of Layout Approval (in case of layout)File: Revised sanction Ananta.pdf | 7 Oct 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised CC Ananta.pdf | 7 Oct 2021 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Ananta Phase III Sept 21.pdf | 7 Oct 2021 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Ananta Phase III Engg Sep 21.pdf | 7 Oct 2021 |
| Form 2AFile: Ananta Phase III 2A - Sep 21.pdf | 7 Oct 2021 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Rohan Ekam Phase 2PR1261012502532 | Balewadi, Pune | 100 | Feb 2026 | Ongoing | Mar 2030 | Not due yet |
| Rohan Ekam Phase 1P52100052298 | Balewadi, Pune | 414 | Aug 2023 | Ongoing | Dec 2027 | Not due yet |
| ROHAN VITIP52100046719 | Wakad, Pune | 93 | Sep 2022 | Ongoing | Dec 2027Registered original: Dec 2025 | Not due yet |
| ROHAN ANAND PHASE IIP52100023451 | SOMATANE PHATA, Pune | 241 | Dec 2019 | Ongoing | Dec 2026Registered original: Dec 2025 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 27 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 147 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep ROHAN ANANTA PHASE III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Tathawade13,700+ in Pune
Filed coordinates, straight-line distance. 255 registered projects within 2 km.
Construction of 24 LIG, 768 MIG and commercial
Pune Housing & Area Development Board
Kohinoor Avantara
Intofinity Promoters Private Limited
AISHWARYAM INSIGNIA
VIKSAK VINODE INFRATECH LLP
KOHINOOR UPTOWN AVENUE
MOONSTONE REALINFRA PRIVATE LIMITED
LUSH RESIDENCES
LUSH RESIDENCES LLP
RENUKA PANCHATATTVA
Renuka Realty Private Limited
Builder: ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED has 28 registrations on MahaRERA, including ROHAN KRITIKA WINGS A C and ROHAN LEHER 2 WING A. Its filings disclose 15 earlier MahaRERA projects: declares 9 of 10 past projects completed on time. Litigation is declared on 8 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if ROHAN ANANTA PHASE III is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of ROHAN ANANTA PHASE III?
The registered promoter entity is ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED, a company as per the filing. Its CIN U45202PN2001PTC016352 and GSTIN 27AABCR8171R1ZL can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in ROHAN ANANTA PHASE III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for ROHAN ANANTA PHASE III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at ROHAN ANANTA PHASE III?
The professionals named in the filing: Architect: Ankur Associates; Architect: Ar Shashank P Phadke; Engineer: Mahesh Balurgi; Engineer: Jitendra Kumar Jain -; Chartered Accountant: Khandelwal Jain & Associates; Chartered Accountant: Golesha & Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in ROHAN ANANTA PHASE III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.