Red flags
- 1 complaint at MahaRERA
- Completion date moved by 3 months
- 1 extension taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
RIYASAT SHOPPING COMPLEX is a Commercial project by Riyasat Infra Developers Private Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000080641 on 23 Jun 2025. The registration is recorded completed; possession was promised by 31 Oct 2025. The completion date has moved by 3 months from the original filing. 0 of the 24 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.
At a glance
Project
- NameRIYASAT SHOPPING COMPLEX
- TypeCommercial
- Location
- NH 4
- Mumbai Pune Highway
- Nadhal
- Khalapur
- Raigarh
- 410206
- Pincode410206
- RERA no.P52000080641
- ReraGenie IDRG-MH-33288
Builder
- NameRiyasat Infra Developers Private Limited
- Entity typeCompany
- CINU70109RJ2021PTC074734
- GSTIN27AAKCR9676A1ZZ
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- Managing DirectorSUMER SINGH SAINI
- DirectorSUBHASH Chand SAINI
- Other registrations6 more →
- Completed5 of 7
- Declared earlier projects5 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on23 Jun 2025
- Promised completion31 Oct 2025
- Revised completionRevised to 31 Oct 2025 (originally 31 Jul 2025)
- Buildings1 building record
- Documents filed63 files
Current status
Figures as on 9 Mar 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| RIYASAT SHOPPING COMPLEX | NA | 2 | 2 | 0 | 24 | 24 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 9 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 55%.
RIYASAT SHOPPING COMPLEX: 96% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 55% |
Progress on shared amenities15
As on 9 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed38
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| RIYASAT SHOPPING COMPLEX | NA | Rs 3.00 cr | Rs 2.91 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MR PRANAY P PASHILKAR |
| Engineer | CREATOR RCC CONSULTANT LLP RUTVIJ PATEL |
| Chartered Accountant | S D PARANJPE & ASSOCIATES CA SHATANU PARANJAPE |
| Chartered Accountant | S D PARANJPE & ASSOCIATES CA SHANTANU PARANJAPE |
| Chartered Accountant | Bharat A Choudhary and Co |
| Partner | Role in project |
|---|---|
| Riyasat Infra Developers Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterOur project registration got delayed as we had applied in January 2025 and received the registration certificate June 2025. Also, currently the work was halted due to rain and hence work could not be completed within the completion date estimated earlier. Thus for the completion of the development work within next 3 months, we are applying for extension of the project completion date upto 31/10/2025.
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC12503679 | SHAILEY MANISH CHHEDA | Riyasat Infra Developers Private Limited | 15/10/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 12 Feb 2025 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Jun 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 28 Jul 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed63
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: OC LETTER C1.pdf | 9 Mar 2026 |
| Withdrawal Update Form 1File: Form 1 31-10-2025 RSC.pdf | 30 Jan 2026 |
| Withdrawal Update Form 2File: Form 2 31-10-2025 RSC.pdf | 30 Jan 2026 |
| Withdrawal Update Form 3File: Form 3 RSC 31-10-2025_compressed.pdf | 30 Jan 2026 |
| Withdrawal Update Form 1File: Form 1 RSC.pdf | 28 Oct 2025 |
| Withdrawal Update Form 2File: Form 2 RSC.pdf | 28 Oct 2025 |
| Withdrawal Update Form 3File: Form 3 RSC.pdf | 28 Oct 2025 |
| Building plan approval or NA orderFile: NA Order for Plot.pdf | 28 Jul 2025 |
| Commencement certificateFile: CC.pdf | 28 Jul 2025 |
| Declaration and undertaking (Annexure A)File: Annexure A Declaration.pdf | 28 Jul 2025 |
| Withdrawal Update Form 1File: Form -1 Riyasat Shopping Complex.pdf | 28 Jul 2025 |
| Withdrawal Update Form 1File: Form -1 Riyasat Shopping Complex.pdf | 28 Jul 2025 |
| Withdrawal Update Form 1File: Form -1 Riyasat Shopping Complex.pdf | 28 Jul 2025 |
| Withdrawal Update Form 2File: Form -2 Riysath Shoping Complex_0001.pdf | 28 Jul 2025 |
| Withdrawal Update Form 2File: Form -2 Riysath Shoping Complex_0001.pdf | 28 Jul 2025 |
| Withdrawal Update Form 2File: Form -2 Riysath Shoping Complex_0001.pdf | 28 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Riyasat Shooping Complex 300625 Signed.pdf | 28 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Riyasat Shooping Complex 300625 Signed.pdf | 28 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Riyasat Shooping Complex 300625 Signed.pdf | 28 Jul 2025 |
| Withdrawal Update Form 1File: Form -1 Riyasat Shopping Complex.pdf | 26 Jul 2025 |
| Withdrawal Update Form 2File: Form -2 Riysath Shoping Complex_0001.pdf | 26 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Riyasat Shooping Complex 300625 Signed.pdf | 26 Jul 2025 |
| Withdrawal Update Form 1File: Form -1 Riyasat Shopping Complex.pdf | 25 Jul 2025 |
| Withdrawal Update Form 1File: Form -1 Riyasat Shopping Complex.pdf | 25 Jul 2025 |
| Withdrawal Update Form 2File: Form -2 Riysath Shoping Complex_0001.pdf | 25 Jul 2025 |
| Withdrawal Update Form 2File: Form -2 Riysath Shoping Complex_0001.pdf | 25 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Riyasat Shooping Complex 300625 Signed.pdf | 25 Jul 2025 |
| Withdrawal Update Form 3File: Form 3 Riyasat Shooping Complex 300625 Signed.pdf | 25 Jul 2025 |
| Layout approvalFile: 3500.pdf | 17 Jun 2025 |
| Copy of Layout Approval (in case of layout)File: 3500.pdf | 17 Jun 2025 |
| Other - LegalFile: 3500.pdf | 16 Jun 2025 |
| Other - LegalFile: Ferfar (2).pdf | 21 Feb 2025 |
| Other - LegalFile: 37 Acres Kajap With Sign.pdf | 21 Feb 2025 |
| Other - LegalFile: 153 7-12-1.pdf | 21 Feb 2025 |
| Other - TechnicalFile: Declaration-Cum-Undertaking - Annexure A.pdf | 19 Feb 2025 |
| Layout approvalFile: Layout ddgdg_compressed.pdf | 12 Feb 2025 |
| Building plan approvalFile: NA PERMISSION.pdf | 12 Feb 2025 |
| PAN CardFile: Riyasat PAN.pdf | 12 Feb 2025 |
| Copy of the legal title reportFile: TSR - 1 (1).pdf | 12 Feb 2025 |
| Copy of the legal title reportFile: TSR (1).pdf | 12 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: Finance and Legal_merged (6).pdf | 12 Feb 2025 |
| Details of encumbrances concerned to FinanceFile: Legal and Finance_merged (7).pdf | 12 Feb 2025 |
| Copy of Layout Approval (in case of layout)File: Layout ddgdg_compressed.pdf | 12 Feb 2025 |
| Proforma of Allotment letterFile: ALLOTMENT LETTER.pdf | 12 Feb 2025 |
| Declaration in FORM BFile: Form B - New.pdf | 12 Feb 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate.pdf | 12 Feb 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 12 Feb 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate.pdf | 12 Feb 2025 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 12 Feb 2025 |
| Building Plan Approval / NA Order for plotted developmentFile: NA PERMISSION.pdf | 12 Feb 2025 |
| Declaration about Commencement CertificateFile: CC Declaration - New.pdf | 12 Feb 2025 |
| CERSAI detailsFile: Cersai n Mortgage.pdf | 12 Feb 2025 |
| Declaration about all RERA Designated Bank Accounts (Format A)File: Bank Format A.pdf | 12 Feb 2025 |
| Deviation Report with respect to Allotment letterFile: Deviation of Allotment Letter_compressed.pdf | 12 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Finance and Legal_merged (6).pdf | 12 Feb 2025 |
| Details of encumbrances concerned to LegalFile: Legal and Finance_merged (7).pdf | 12 Feb 2025 |
| Other - FinanceFile: BR_0001.pdf | 12 Feb 2025 |
| Deviation Report with respect to model copy of AgreementFile: Deviation of AFS.pdf | 12 Feb 2025 |
| Proforma of Agreement for saleFile: AFS - Commercial.pdf | 12 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - SC.pdf | 12 Feb 2025 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of interest - SS.pdf | 12 Feb 2025 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank certificate Format B.pdf | 12 Feb 2025 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for secured or unsecured finance.pdf | 12 Feb 2025 |
Promoter's earlier projects4
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| RIYASAT BLISSP52000079379 | Village Panshil and Talegaon, Raigarh | 243 | Mar 2025 | Ongoing | Apr 2026Registered original: Dec 2025 | Not delivered |
| THE RIYASAT SANKALPP52000054353 | Village Nadhal, Raigarh | 325 | Jan 2024 | Completed | Oct 2025 | Late, Nov 2025 |
| Riyasat Sankalp extension secondPP1270002500477 | Nadhal, Raigarh | 13 | Aug 2025 | Completed | Oct 2025 | Late, Nov 2025 |
| Riyasat Sankalp extension firstPP1270002500558 | Nadhal, Raigarh | 13 | Aug 2025 | Completed | Oct 2025 | Oct 2025 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 6 other registrations, which the RERA portal never shows together
- All 63 filed documents as one ZIP, foldered, with a manifest
Keep RIYASAT SHOPPING COMPLEX on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Mumbai Pune Highway5,900+ in Raigarh
SHREE RAM DELTA
Shreenathji Enterprises
Brillante
Callista Realty Limited
SAI SUNCITY PHASE 3
Chariot Properties LLP
ANANDAM PHASE - II
TODAY GLOBAL HOMES
Maximus Residency Phase-I
Superb Maa Developers LLP
Sai Vrindavan Dham
KT & LK SWEET HOMES
See every Raigarh project, with the district possession charts
Builder: Riyasat Infra Developers Private Limited
Riyasat Infra Developers Private Limited has 7 registrations on MahaRERA, including THE RIYASAT SANKALP and RIYASAT BLISS. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 3 past projects completed on time. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if RIYASAT SHOPPING COMPLEX is delayed beyond 31 Oct 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of RIYASAT SHOPPING COMPLEX?
The registered promoter entity is Riyasat Infra Developers Private Limited, a company as per the filing. Its CIN U70109RJ2021PTC074734 and GSTIN 27AAKCR9676A1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in RIYASAT SHOPPING COMPLEX?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against RIYASAT SHOPPING COMPLEX?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for RIYASAT SHOPPING COMPLEX?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at RIYASAT SHOPPING COMPLEX?
The professionals named in the filing: Architect: MR PRANAY P PASHILKAR; Engineer: CREATOR RCC CONSULTANT LLP RUTVIJ PATEL; Chartered Accountant: S D PARANJPE & ASSOCIATES CA SHATANU PARANJAPE; Chartered Accountant: S D PARANJPE & ASSOCIATES CA SHANTANU PARANJAPE; Chartered Accountant: Bharat A Choudhary and Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in RIYASAT SHOPPING COMPLEX?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback