Riyasat Infra Developers Private Limited has 7 registrations in this build, including THE RIYASAT SANKALP and RIYASAT BLISS. Its filings disclose 5 earlier MahaRERA projects: 1 of 3 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| THE RIYASAT SANKALP | Raigarh, Maharashtra | 325 | 70% | Completed |
| RIYASAT BLISS | Raigarh, Maharashtra | 243 | 47% | Completed |
| RIYASAT SHOPPING COMPLEX | Raigarh, Maharashtra | 24 | 0% | Completed |
| Riyasat Sankalp extension first | Raigarh, Maharashtra | 13 | 0% | Completed |
| Riyasat Sankalp extension second | Raigarh, Maharashtra | 13 | 8% | Completed |
| RIYASAT ROYALCREST | Raigarh, Maharashtra | 207 | 0% | Registered |
| RIYASAT MONTERA | Raigarh, Maharashtra | 206 | 0% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| THE RIYASAT SANKALP P52000054353 | 31 Oct 2025 | 18 Nov 2025 | +1 months |
| Riyasat Sankalp extension first PP1270002500558 | 31 Oct 2025 | 27 Oct 2025 | On time |
| Riyasat Sankalp extension second PP1270002500477 | 31 Oct 2025 | 18 Nov 2025 | +1 months |
| RIYASAT SHOPPING COMPLEX P52000080641 | 31 Oct 2025 | Not completed yet | Ongoing |
| RIYASAT BLISS P52000079379 | 30 Apr 2026 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify Riyasat Infra Developers Private Limited as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U70109RJ2021PTC074734 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Riyasat Infra Developers Private Limited?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.