Red flags

  • 7 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
May 2028Possession promisedno revision filed
0 of 55Construction stages doneacross 5 buildings; furthest along: Excavation, 0%
714 of 902Units unsoldnot recorded sold or booked
7Complaints at MahaRERAon this registration
Jump to the 174 documents Report an error

Brillante is a Others project by Callista Realty Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000005604 on 11 Aug 2017. Possession is promised by 30 May 2028. 188 of the 902 units on this registration are recorded sold or booked, and 0 of 55 construction stages are filed complete. 7 complaints are on record with the regulator.

At a glance

Project

  • NameBrillante
  • TypeOthers
  • Location
    • Kolkhe
    • Panvel
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000005604
  • ReraGenie IDRG-MH-53023

Builder

  • NameCallista Realty Limited
  • Entity typeCompany
  • GSTIN27AAECC6230H1ZU
  • Managing DirectorsVinayak Subhash Sonavane, Shobha Vinayak Sonavane, Sanjay Kumar KishanKumar Kedia

Key dates

this monthRegisteredAug 2017PromisedMay 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Aug 2017
  • Promised completion30 May 2028
  • Revised completionNone
  • Buildings5 building records
  • Documents filed174 files

Current status

21%188 of 902 units booked
0.0%Work done, per cost certificate

Figures as on 5 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
RENTAL HOUSING BUILDING A1NA1414000
Rental Housing Building- A2NA2626000
Brillante Wing ANA42352660266
Brillante Wing BNA40352300230
Brillante Wing B1NA40354060406

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 5 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Excavation, at 0%.

RENTAL HOUSING BUILDING A10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Rental Housing Building- A20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Brillante Wing A0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Brillante Wing B0%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Brillante Wing B10%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed943

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots943
Closed/Covered883
Open Space60
BuildingClosed/CoveredOpen SpaceTotal
RENTAL HOUSING BUILDING A118018
Rental Housing Building- A260060
Brillante Wing A20020220
Brillante Wing B20520225
Brillante Wing B140020420

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area18,320 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on2 Jun 2026

Approvals and building plan

Sanctioning authorityNAVI MUMBAI AIRPORT INFLUENCE NOTIFIED AREA (NAINA)
Permissible FSI73280.0
Proposed, not sanctioned73,280 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSomimur Apartment, Timber Estate, SV Road, Malad West, Mumbai 400064
Estimated costRs 225.00 cr
Work done0.0%
BuildingWingEstimatedIncurred
Brillante Wing BNARs 91.83 cr-
RENTAL HOUSING BUILDING A1NARs 60.59 cr-
Rental Housing Building- A2NARs 50.87 cr-
Brillante Wing B1NARs 19.86 cr-
Brillante Wing ANARs 1.86 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMS LENA GOSAVI
ArchitectDIMENSIONS ARCHITECTS PVT LTD
EngineerMahadeo Rahate
Chartered AccountantASHISH MAHESHWARI & ASSOCIATES
Chartered AccountantPODDAR A. & ASSOCIATES
Chartered AccountantRonak A Jain & Associates
Chartered AccountantDNJ & Associates
Chartered AccountantA V Santara & Co
PartnerRole in project
Callista Realty Limited-

Complaints filed with MahaRERA7

Case no.ComplainantRespondentFiled
CC006000000057654Mazdiyar BharuchaM/s Callista Reality Pvt Ltd, Arun Kedia 982004959024/02/2019
CC006000000193508Rajesh Kumar SwainCallista Realty Limited07/08/2020
CC006000000220970KiritKumar Bhavanishankar JoshiCallista Realty Ltd26/04/2022
CC12400810Manish JainCallista Realty Limited18/11/2024
CC12501810SUJOY JAYANT GUPTACallista Realty Limited02/06/2025
CC12501809SUJOY JAYANT GUPTACallista Realty Limited02/06/2025
CC12501991Ketan Nandlal DattaniCallista Realty Limited18/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 31 Jul 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Nov 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 May 2028

Documents filed174

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 174 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: 30-09-2017 form 1.pdf5 Jun 2026
Form 2File: Form 2 Sept 17.pdf5 Jun 2026
Form 3File: Form 3 Sept 2017.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Sept 2017.pdf5 Jun 2026
Form 1File: 31-12-2017 form 1.pdf5 Jun 2026
Form 2File: Form 2 Dec 17.pdf5 Jun 2026
Form 3File: Form 3 Dec 2017.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Dec 2017.pdf5 Jun 2026
Form 1File: 31-03-2018 form 1.pdf5 Jun 2026
Form 2File: Form 2 Mar 18.pdf5 Jun 2026
Form 3File: Form 3 March 2018.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2018.pdf5 Jun 2026
Form 1File: 30-06-2018 form 1.pdf5 Jun 2026
Form 2File: Form 2 June 18.pdf5 Jun 2026
Form 3File: Form 3 June 2018_9_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2018_11zon.pdf5 Jun 2026
Form 1File: 30-09-2018 form 1.pdf5 Jun 2026
Form 2File: Form 2 Sept 18.pdf5 Jun 2026
Form 3File: Form 3 Sept 2018_23_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Sept 2018_11zon.pdf5 Jun 2026
Form 1File: 31-12-2018 form 1.pdf5 Jun 2026
Form 2File: Form 2 Dec 18.pdf5 Jun 2026
Form 3File: Form 3 Dec 2018_2_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Dec 2018_11zon.pdf5 Jun 2026
Form 1File: 31-03-2019 form 1.pdf5 Jun 2026
Form 2File: Form 2 Mar 19.pdf5 Jun 2026
Form 3File: Form 3 March 2019.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2019_11zon.pdf5 Jun 2026
Form 1File: 30-06-2019 form 1.pdf5 Jun 2026
Form 2File: Form 2 June 19.pdf5 Jun 2026
Form 3File: Form 3 June 2019_10_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2019_11zon.pdf5 Jun 2026
Form 1File: 30-09-2019 from 1.pdf5 Jun 2026
Form 2File: Form 2 Sept 19.pdf5 Jun 2026
Form 3File: Form 3 Sept 2019_24_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Sept 2019_11zon.pdf5 Jun 2026
Form 1File: 31-12-2019 form 1.pdf5 Jun 2026
Form 2File: Form 2 Dec 19.pdf5 Jun 2026
Form 3File: Form 3 Dec 2019_3_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Dec 2019_11zon.pdf5 Jun 2026
Form 1File: 31-03-2020 form 1.pdf5 Jun 2026
Form 2File: Form 2 Mar 20.pdf5 Jun 2026
Form 3File: Form 3 March 2020.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Mar 2020_11zon.pdf5 Jun 2026
Form 1File: 30-06-2020 form 1.pdf5 Jun 2026
Form 2File: Form 2 June 20.pdf5 Jun 2026
Form 3File: Form 3 June 2020_11_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2020_11zon.pdf5 Jun 2026
Form 1File: 30-09-2020 form 1.pdf5 Jun 2026
Form 2File: Form 2 Sept 20.pdf5 Jun 2026
Form 3File: Form 3 Sept 2020_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Sept 2020_11zon.pdf5 Jun 2026
Form 1File: 31-12-2020 form 1.pdf5 Jun 2026
Form 2File: Form 2 Dec 20.pdf5 Jun 2026
Form 3File: Form 3 Dec 2020_4_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Dec 2020_11zon.pdf5 Jun 2026
Form 1File: 31-03-2021 form 1.pdf5 Jun 2026
Form 2File: Form 2 Mar 21.pdf5 Jun 2026
Form 3File: Form 3 March 2021_18_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2021_11zon.pdf5 Jun 2026
Form 1File: 30-06-2021 from 1.pdf5 Jun 2026
Form 2File: Form 2 June 21.pdf5 Jun 2026
Form 3File: Form 3 June 2021_12_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2021_11zon.pdf5 Jun 2026
Form 1File: 30-09-2021 form 1.pdf5 Jun 2026
Form 2File: Form 2 Sept 21.pdf5 Jun 2026
Form 3File: Form 3 Sept 2021_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Sept 2021_11zon.pdf5 Jun 2026
Form 1File: 31-12-2021 form 1.pdf5 Jun 2026
Form 2File: Form 2 Dec 21.pdf5 Jun 2026
Form 3File: Form 3 Dec 2021_5_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 Dec 2021_11zon.pdf5 Jun 2026
Form 1File: 31-03-2022 form 1.pdf5 Jun 2026
Form 2File: Form 2 Mar 22.pdf5 Jun 2026
Form 3File: Form 3 March 2022.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 March 2022_11zon.pdf5 Jun 2026
Form 1File: 30-06-2022 form 1.pdf5 Jun 2026
Form 2File: Form 2 June 22.pdf5 Jun 2026
Form 3File: Form 3 June 2022_13_11zon.pdf5 Jun 2026
Disclosure of Sold and Booked InventoryFile: Circular 29 June 2022_11zon.pdf5 Jun 2026

How this compares with Raigarh

21%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one has not
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Brillante on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Kolkhe5,900+ in Raigarh

2 kmBrillanteCompleted 33Lapsed / revoked 11Other 17Dot size: filed unitsN

Filed coordinates, straight-line distance. 61 registered projects within 2 km.

Builder: Callista Realty Limited

Callista Realty Limited has 1 registration on MahaRERA, including Brillante. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if Brillante is delayed beyond 30 May 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Brillante?

The registered promoter entity is Callista Realty Limited, a company as per the filing. Its GSTIN 27AAECC6230H1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Brillante?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Brillante?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Brillante?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Brillante?

The professionals named in the filing: Architect: MS LENA GOSAVI; Architect: DIMENSIONS ARCHITECTS PVT LTD; Engineer: Mahadeo Rahate; Chartered Accountant: ASHISH MAHESHWARI & ASSOCIATES; Chartered Accountant: PODDAR A. & ASSOCIATES; Chartered Accountant: Ronak A Jain & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Brillante?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Brillante. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Brillante to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.