Home / Browse projects / Raigarh, Maharashtra / ANANDAM PHASE - II

Registered No litigation declared Residential / Group Housing project

ANANDAM PHASE - II

By TODAY GLOBAL HOMES

RG-MH-04327 · RERA P52000021559 · Last updated on MahaRERA portal: 21 Sep 2026

Source: official MahaRERA filing

Red flags

  • 34 complaints at MahaRERA
  • Completion date moved by 22 months
  • 3 extensions taken
  • Rs 70.00 crore secured on the land, in favour of AXIS FINANCE LIMITED
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.
Oct 2026Possession promisedmoved 22 months from the original
29 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 95%
215 of 655Units unsoldnot recorded sold or booked
34Complaints at MahaRERAon this registration
Jump to the 238 documents Report an error

ANANDAM PHASE - II is a Residential / Group Housing project by TODAY GLOBAL HOMES in Raigarh, Maharashtra, registered with MahaRERA as P52000021559 on 8 Jul 2019. Possession is promised by 30 Oct 2026. The completion date has moved by 22 months from the original filing. 440 of the 655 units on this registration are recorded sold or booked, and 29 of 44 construction stages are filed complete. 34 complaints are on record with the regulator.

At a glance

Project

  • NameANANDAM PHASE - II
  • TypeResidential / Group Housing
  • Location
    • ROHINJAN
    • PANVEL
    • Raigarh
    • 410206
  • Pincode410206
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52000021559
  • ReraGenie IDRG-MH-04327

Builder

  • NameTODAY GLOBAL HOMES
  • Entity typePartnership
  • PartnersBHADRESH RAJESH SHAH, BHAVESH RAJESH SHAH, SUNIL JAGDISH AGRAWAL, RAJESH BHOGILAL SHAH
  • Other registrations3 more →
  • Completed1 of 4

Key dates

this monthRegisteredJul 2019First promiseDec 2024Revised toOct 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on8 Jul 2019
  • Promised completion30 Oct 2026
  • Revised completionRevised to 30 Oct 2026 (originally 30 Dec 2024)
  • Buildings4 building records
  • Documents filed238 files

Current status

67%440 of 655 units booked
89.5%Work done, per cost certificate

Figures as on 21 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO - 4NA28231820182
BUILDING NO - 5ANA31251300130
BUILDING NO - 5 BNA31262130213
BUILDING NO - 5CNA31271300130

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 21 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 95%.

BUILDING NO - 4100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
BUILDING NO - 5A84%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
BUILDING NO - 5 B85%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises60%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%
BUILDING NO - 5C83%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises55%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.80%

Progress on shared amenities15

As on 21 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes75%
Street LightingNoNot applicable
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed600

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots600
Closed/Covered600
BuildingClosed/CoveredTotal
BUILDING NO - 4150150
BUILDING NO - 5A150150
BUILDING NO - 5 B150150
BUILDING NO - 5C150150

Land and ownership7

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area11,624 sq m
Land owned byThe promoter, with other names on the file
Named landowners7
Encumbrance on the landDeclared present
Charge in favour ofAXIS FINANCE LIMITED
Secured amountRs 70.00 crore
CERSAI search filedYes
Declared on11 Sep 2025
LandownerVillageDistrict
RAVINDRA PANDURANG PATILRohinjanRaigarh
ARCHANA RAGHUNATH PATILPanvelRaigarh
KACHRU BHOKYA PATILRohinjanRaigarh
YOGESH YASHWANT PATILRohinjanRaigarh
BAIJUNATH VASANT PATILRohinjanRaigarh
GURUNATH VASANT PATILRohinjanRaigarh
SHRIPAT KALURAM PATILRohinjanRaigarh

Approvals and building plan

Sanctioning authoritypanvel municipal corporation
Permissible FSI52580.65
Proposed, not sanctioned52,581 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVASHI
Estimated costRs 167.46 cr
Cost incurredRs 149.81 cr
Work done89.46%
BuildingWingEstimatedIncurred
BUILDING NO - 5 BNARs 59.33 crRs 51.11 cr
BUILDING NO - 4NARs 45.26 crRs 45.26 cr
BUILDING NO - 5ANARs 34.37 crRs 30.41 cr
BUILDING NO - 5CNARs 23.51 crRs 23.04 cr
-NARs 5.00 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectACUBE ARCHITECTS
EngineerSTRUCTURAL CONCEPT DESIGNS PRIVATE LIMITED
EngineerAADESH SHAH SHAH
Chartered AccountantMAIDAWAT & ASSOCIATES
Chartered AccountantCA SWATI
Chartered AccountantBhavik J Velani
PartnerRole in project
TODAY GLOBAL HOMES-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52000026000Dec 2024 → Dec 2025

Reason as filed by the promoterShortage of Skilled Labor: In addition to the material shortages, the construction industry has also been severely impacted by an acute shortage of skilled labor, including masons, earthworkers, carpenters, plumbers, and other specialized trades. The COVID-19 pandemic has resulted in the migration of a large proportion of the labor force, particularly migrant workers, back to their native regions due to lockdowns, health concerns, and other social and economic factors. As a consequence, a substantial number of workers previously engaged on-site have been unable to return, thereby halting criti

EA27122519055Dec 2024 → Jun 2026

Reason as filed by the promotercovid, planning authority delay

P52000021559/WarDec 2024 → Oct 2026

Reason as filed by the promoterNA

Complaints filed with MahaRERA34

Case no.ComplainantRespondentFiled
CC12601517Shashikant KedareTODAY GLOBAL HOMES19/03/2026
CC12501220Ravindra Ashok KumbhavdekarToday Global Homes12/04/2025
CC12501972ASIT BARAN SAMUITODAY GLOBAL HOMES17/06/2025
CC12504581SAMEER DIPAK KAPURETODAY GLOBAL HOMES22/12/2025
CC12600448Shyjamol SebastianTODAY GLOBAL HOMES24/01/2026
CC12600840DHIRAJ B MAGARETODAY GLOBAL HOMES14/02/2026
CC12600837Sachin AgarwalTODAY GLOBAL HOMES14/02/2026
CC12600878Braja Kishore RoutTODAY GLOBAL HOMES17/02/2026
CC12600839Sachin Sopan FulsundarTODAY GLOBAL HOMES14/02/2026
CC12600966RAJESH RANJANTODAY GLOBAL HOMES22/02/2026
CC12600897Rajwinder Kaur UppalTODAY GLOBAL HOMES18/02/2026
CC12600847Roshan Chandrahasa KarkeraTODAY GLOBAL HOMES15/02/2026
CC12600874Lineesh Maliyakkal JamesTODAY GLOBAL HOMES17/02/2026
CC12601093Anuj SaxenaTODAY GLOBAL HOMES28/02/2026
CC12600896Zinat Jahan Zuber KhanTODAY GLOBAL HOMES18/02/2026
CC12600972Bhupendra Shivaji AhireTODAY GLOBAL HOMES22/02/2026
CC12601031Raghvendra SinghTODAY GLOBAL HOMES25/02/2026
CC12601008ASHUTOSH KUMARTODAY GLOBAL HOMES24/02/2026
CC12601114Alok Omprakash TuleTODAY GLOBAL HOMES01/03/2026
CC12601142RAJIV RANJANTODAY GLOBAL HOMES02/03/2026
CC12601188Fahim ChougleTODAY GLOBAL HOMES04/03/2026
CC12601190Binish Fahim ChougleTODAY GLOBAL HOMES05/03/2026
CC12601202Nitil Ashwin JoshiTODAY GLOBAL HOMES05/03/2026
CC12602511Ajay Vilas ParabTODAY GLOBAL HOMES29/04/2026
CC12601514Tarun Singh AswalTODAY GLOBAL HOMES19/03/2026
CC12602011Abinash KumarTODAY GLOBAL HOMES05/04/2026
CC12602312Sajid ShaikhTODAY GLOBAL HOMES19/04/2026
CC12602450Abhiruchi AnandTODAY GLOBAL HOMES26/04/2026
CC12603087Balram ChauhanTODAY GLOBAL HOMES24/05/2026
CC12602542SIYARAM SAHTODAY GLOBAL HOMES01/05/2026
CC12602631RAVINDRA CHANDRABHAN GODETODAY GLOBAL HOMES06/05/2026
CC12603504Sanober Zaheer KhanTODAY GLOBAL HOMES06/06/2026
CC12604802Kanchan Pravin MadhaviTODAY GLOBAL HOMES30/07/2026
CC12605809Nazia Yakub MolkarTODAY GLOBAL HOMES07/09/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Jul 2019
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 May 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Nov 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 May 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Oct 2026

Documents filed238

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 238 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1.pdf21 Sep 2026
Withdrawal Update Form 2File: FORM 2.pdf21 Sep 2026
Withdrawal Update Form 3File: FORM 3.pdf21 Sep 2026
Form 5 (FY 2025-2026)File: Scan Form-5 TGH 1559.pdf27 Aug 2026
Withdrawal Update Form 1File: 2332_001.pdf1 Jun 2026
Withdrawal Update Form 2File: form 02.pdf1 Jun 2026
Withdrawal Update Form 3File: 2335_001.pdf1 Jun 2026
Form 2A (FY 2025-2026)File: form 2a (2).pdf1 Jun 2026
Withdrawal Update Form 1File: form 02-1.pdf31 Jan 2026
Withdrawal Update Form 2File: FORM 2_ JUNE 25_ ANANDAM PHASE II.pdf31 Jan 2026
Withdrawal Update Form 3File: From-03_0001_compressed.pdf31 Jan 2026
Withdrawal Update Form 1File: 01_ARCHITECT CERTIFICATE- WORK STATUS TILL SEPTEMBER 2025 (Anandam 1).pdf27 Dec 2025
Withdrawal Update Form 2File: FORM 2_ JUNE 25_ ANANDAM PHASE II.pdf27 Dec 2025
Withdrawal Update Form 3File: From-03_0001_compressed.pdf27 Dec 2025
Form 2A (FY 2024-2025)File: ANANDAM PHASE 2_FORM 2A.pdf27 Dec 2025
Form 5 (FY 2024-2025)File: Scan Form-5 TGH-559.pdf9 Oct 2025
Withdrawal Update Form 1File: FORM 1_ JUNE 25_ ANANDAM PHASE II.pdf12 Sep 2025
Withdrawal Update Form 2File: FORM 2_ JUNE 25_ ANANDAM PHASE II.pdf12 Sep 2025
Withdrawal Update Form 3File: withdrawal update_ FORM 3_ JUNE 25_ ANANDAM PHASE II_compressed.pdf12 Sep 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form -1.pdf22 May 2025
Certificates of CA (Form 3)File: Anandam I-Form 2 Q3_0001.pdf22 May 2025
Certificates of CA (Form 3)File: Anandam I-Form 3 Q3_0001_compressed.pdf22 May 2025
Certificates of CA (Form 3)File: Anandam I-Form 3_0001_compressed.pdf22 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anandam I-Form 2 Q3_0001.pdf22 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Anandam I-Form 2_0001.pdf22 May 2025
Disclosure of sold/ booked inventoryFile: inventory com.pdf22 May 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Anandam I-Form 2A_0001.pdf22 May 2025
Declaration in FORM BFile: P52000021559_FileName_5.pdf21 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf1 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 14 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf1 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 24 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf1 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 24 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf1 Jan 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow1 Jan 2025
Building plan approvalFile: PLAN.pdf21 Nov 2024
Building plan approvalFile: PLAN.pdf21 Nov 2024
Building Plan Approval (IOD)File: PLAN.pdf21 Nov 2024
Building Plan Approval (IOD)File: PLAN.pdf21 Nov 2024
Building plan approvalFile: 1_compressed.pdf29 Oct 2024
Building Plan Approval (IOD)File: 1_compressed.pdf29 Oct 2024
Certificates of CA (Form 3)File: form 3 Q2-1 revised_11zon (1).pdf26 Oct 2024
Building plan approvalFile: 14.pdf25 Oct 2024
Building plan approvalFile: 15.pdf25 Oct 2024
Building plan approvalFile: 16.pdf25 Oct 2024
Building plan approvalFile: 17.pdf25 Oct 2024
Building plan approvalFile: 18.pdf25 Oct 2024
Building plan approvalFile: 19.pdf25 Oct 2024
Building plan approvalFile: 20.pdf25 Oct 2024
Building plan approvalFile: 21.pdf25 Oct 2024
Building plan approvalFile: 22.pdf25 Oct 2024
Building plan approvalFile: 23.pdf25 Oct 2024
Building plan approvalFile: 24.pdf25 Oct 2024
Building plan approvalFile: 25.pdf25 Oct 2024
Building plan approvalFile: 26.pdf25 Oct 2024
Building plan approvalFile: 27.pdf25 Oct 2024
Building plan approvalFile: 28.pdf25 Oct 2024
Building plan approvalFile: 29.pdf25 Oct 2024
Building plan approvalFile: 30.pdf25 Oct 2024
Building plan approvalFile: 31.pdf25 Oct 2024
Building plan approvalFile: 32.pdf25 Oct 2024
Building plan approvalFile: 33.pdf25 Oct 2024
Building plan approvalFile: 34.pdf25 Oct 2024
Building plan approvalFile: 35.pdf25 Oct 2024
Building plan approvalFile: 36.pdf25 Oct 2024
Building plan approvalFile: 37.pdf25 Oct 2024
Building plan approvalFile: 38.pdf25 Oct 2024
Building plan approvalFile: 39.pdf25 Oct 2024
Building plan approvalFile: 40.pdf25 Oct 2024
Building plan approvalFile: 41.pdf25 Oct 2024
Building plan approvalFile: 42.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 01 ARCHITECT CERTIFICATE.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 01 ARCHITECT CERTIFICATE.pdf25 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 01 ARCHITECT CERTIFICATE.pdf25 Oct 2024
Certificates of CA (Form 3)File: FORM 03.pdf25 Oct 2024
Building Plan Approval (IOD)File: 31.pdf25 Oct 2024
Building Plan Approval (IOD)File: 30.pdf25 Oct 2024
Building Plan Approval (IOD)File: 32.pdf25 Oct 2024
Building Plan Approval (IOD)File: 33.pdf25 Oct 2024
Building Plan Approval (IOD)File: 34.pdf25 Oct 2024
Building Plan Approval (IOD)File: 35.pdf25 Oct 2024
Building Plan Approval (IOD)File: 36.pdf25 Oct 2024

How this compares with Raigarh

67%of this project is bookeddistrict median 29%
20%of Raigarh projects moved their completion datethis one moved by 22 months
26%of Raigarh registrations have lapsed or been cancelledthis one is on the register

Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.

Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ANANDAM PHASE - II on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PANVEL5,900+ in Raigarh

2 kmANANDAM PHASE - IICompleted 12Lapsed / revoked 26Other 49Dot size: filed unitsN

Filed coordinates, straight-line distance. 87 registered projects within 2 km.

Builder: TODAY GLOBAL HOMES

TODAY GLOBAL HOMES has 4 registrations on MahaRERA, including ANANDAM - PHASE I and ANANDAM PHASE - II. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Raigarh district page.

Frequently asked questions

What are my rights if ANANDAM PHASE - II is delayed beyond 30 Oct 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ANANDAM PHASE - II?

The registered promoter entity is TODAY GLOBAL HOMES, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ANANDAM PHASE - II?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ANANDAM PHASE - II?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ANANDAM PHASE - II?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ANANDAM PHASE - II?

The professionals named in the filing: Architect: ACUBE ARCHITECTS; Engineer: STRUCTURAL CONCEPT DESIGNS PRIVATE LIMITED; Engineer: AADESH SHAH SHAH; Chartered Accountant: MAIDAWAT & ASSOCIATES; Chartered Accountant: CA SWATI; Chartered Accountant: Bhavik J Velani. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ANANDAM PHASE - II?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ANANDAM PHASE - II. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ANANDAM PHASE - II to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.