Home / Browse projects / Thane, Maharashtra / Riverwood Park Building No -1

Registered No litigation declared Residential / Group Housing project

Riverwood Park Building No -1

By Shree Khidkaleshwar Property Developers Pvt. Ltd.

RG-MH-96807 · RERA P51700032548 · Last updated on MahaRERA portal: 10 Aug 2026

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA
  • Completion date moved by 15 months
  • 1 extension taken
  • Rs 50.00 crore secured on the land, in favour of RELIANCE HOME FINANCE LTD

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2027Possession promisedmoved 15 months from the original
4 of 11Construction stages donefurthest along: Slabs of Super Structure, 81%
69 of 170Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 85 documents Report an error

Riverwood Park Building No -1 is a Residential / Group Housing project by Shree Khidkaleshwar Property Developers Pvt. Ltd. in Thane, Maharashtra, registered with MahaRERA as P51700032548 on 10 Jan 2022. Possession is promised by 31 Mar 2027. The completion date has moved by 15 months from the original filing. 101 of the 170 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NameRiverwood Park Building No -1
  • TypeResidential / Group Housing
  • Location
    • Kalyan Shill Road
    • Sagarli
    • Dombivali East
    • Thane (M Corp.)
    • Thane
    • 421204
  • Pincode421204
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700032548
  • ReraGenie IDRG-MH-96807

Builder

  • NameShree Khidkaleshwar Property Developers Pvt. Ltd.
  • Entity typeCompany
  • CINU45400MH2014PTC254482
  • GSTIN27AAUCS4319K1ZP
  • Managing DirectorBharat Shah
  • Other registrations4 more →
  • Completed3 of 5

Key dates

this monthRegisteredJan 2022First promiseDec 2025Revised toMar 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Jan 2022
  • Promised completion31 Mar 2027
  • Revised completionRevised to 31 Mar 2027 (originally 31 Dec 2025)
  • Buildings1 building record
  • Documents filed85 files

Current status

59%101 of 170 units booked
44.6%Work done, per cost certificate

Figures as on 10 Aug 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Building No - 1NA23221700170

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 10 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 81%.

Building No - 1: 60% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure81%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises81%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks50%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes10%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes10%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed183

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots183
Closed/Covered60
Open Space123

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,275 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofRELIANCE HOME FINANCE LTD
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on17 Jul 2025

Approvals and building plan

Sanctioning authorityThane Municipal Corporation
Permissible FSI10829.99
Proposed, not sanctioned10,830 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch215, FREE PRESS HOUSE, FREE PRESS MARG, NARIMAN POINT MUMBAI 400021
Estimated costRs 42.62 cr
Cost incurredRs 19.02 cr
Work done44.63%
BuildingWingEstimatedIncurred
Building No - 1NARs 40.49 crRs 18.88 cr
-NARs 2.13 crRs 13.92 lakh

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVasturachna
EngineerSK Consultants & Engineers
EngineerHarish Vispute
Chartered AccountantNB Sayed & Associates
Chartered AccountantVinod Patil & Associates
PartnerRole in project
Shree Khidkaleshwar Property Developers Pvt. Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA20122518869Dec 2025 → Mar 2027

Reason as filed by the promoterThe project has been delayed due to non-performance and repeated lapses by the appointed contractor, including failure to deploy adequate manpower, irregular work progress, and delays in material supply. Despite multiple notices and follow-ups, the contractor was unable to adhere to the agreed timelines, which caused unavoidable delays in construction. To protect the interest of homebuyers and maintain quality standards, the contractor is replaced, resulting in additional time required for mobilization of new resources

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12503207vijay Shivaji PatilShree Khidkaleshwar Property Developers Pvt. Ltd.10/09/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 27 Dec 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Dec 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 20 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Dec 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2027

Documents filed85

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 85 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - Riverwood Park Building No - 1 as on March 2026.pdf10 Aug 2026
Withdrawal Update Form 1File: Riverwood_Park_Building_No_-1_Form1_Q1_2026-27_05-08-2026_07-51.pdf10 Aug 2026
Withdrawal Update Form 2File: Form 2 - Riverwood Park Building No - 1 as on March 2026.pdf10 Aug 2026
Withdrawal Update Form 2File: Riverwood_Park_Building_No_-1_Form2_Q1_2026-27_05-08-2026_07-51.pdf10 Aug 2026
Withdrawal Update Form 3File: Form 3 - Riverwood Park Building No - 1 as on March 2026.pdf10 Aug 2026
Withdrawal Update Form 3File: Riverwood_Park_Building_No_-1_Form3_Q1_2026-27_05-08-2026_07-15_doc1.pdf10 Aug 2026
Form 2A (FY 2021-2022)File: Form 2A Riverwood park building no-01 for 2021-2022.pdf18 Jun 2026
Form 2A (FY 2022-2023)File: Form 2A Riverwood park building no-01 for 2022-2023.pdf18 Jun 2026
Form 2A (FY 2023-2024)File: Form 2A Riverwood park building no-01 for 2023-2024.pdf18 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A Riverwood park building no-01 for 2024-2025.pdf18 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A Riverwood park building no-01 for 2025-2026.pdf18 Jun 2026
Form 5 (FY 2024-2025)File: Form-5 Riverwood Park Building No 1 For 2024-25.pdf18 Jun 2026
Withdrawal Update Form 1File: Form 1 of Riverwood Park Building No1 as on 31-12-2025.pdf15 May 2026
Withdrawal Update Form 2File: Form 2 of Riverwood Park Building No1 as on 31-12-2025.pdf15 May 2026
Withdrawal Update Form 3File: Form 3 of Riverwood Park Building No1 as on 31-12-2025.pdf15 May 2026
Withdrawal Update Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf20 Dec 2025
Withdrawal Update Form 1File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf20 Dec 2025
Withdrawal Update Form 2File: Form 2 of Riverwood Park Building No 1 as on 30-06-2024.pdf20 Dec 2025
Withdrawal Update Form 2File: Form 2 of Riverwood Park Building No 1 as on 30-06-2024.pdf20 Dec 2025
Withdrawal Update Form 3File: 11 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf20 Dec 2025
Withdrawal Update Form 3File: 11 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf20 Dec 2025
Form 1File: Form 1-Riverwood Park Blgd no-1 as on March 2025.pdf11 Sep 2025
Form 2File: Form 2 - Riverwood Park Building No 1 as on March 2025.pdf11 Sep 2025
Form 3File: Form 3 - Riverwood Park Building No 1 as on March 2025.pdf11 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Riverwood Park Building No 1 as on March 2025.pdf11 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Riverwood Park Building No 1 as on Dec 2024.pdf24 Mar 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Riverwood Park Building No 1 as on Dec 2024.pdf24 Mar 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 8 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf15 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 14 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf15 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 12 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf15 Feb 2025
Building plan approvalFile: Bldg No 1 Aprovved Plan Typical and Refuge Plan converted.pdf20 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: Bldg No 1 Aprovved Plan Typical and Refuge Plan converted.pdf20 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate- Sept 2024.pdf4 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Riverwood Park Building No 1 as on Sep 2024.pdf3 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Riverwood Park Building No 1 as on Sep 2024.pdf3 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Riverwood Park Building No 1 as on 30-06-2024.pdf11 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 of Riverwood Park Building No 1 as on 30-06-2024.pdf11 Nov 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 6 Architect’s Certificate of Percentage of Completion of Work (Form 1) (1).pdf16 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 9 Engineer’s Certificate on Cost Incurred on Project (Form 2) (1).pdf16 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 11 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf16 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Riverwood Park Building No 1 as on March 2024.pdf20 Jun 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Riverwood Park Building No 1 as on March 2024.pdf7 Jun 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Riverwood Park Building No 1 as on March 2024.pdf7 Jun 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 building no1.pdf6 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Certificate bldg 2023.pdf4 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Riverwood Park Building No 1 as on Dec 2023.pdf27 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Riverwood Park Building No 1 as on Dec 2023.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Riverwood Park Building No - 1 Sept 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Riverwood Building No - 1 as on June 2023.pdf20 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Riverwood Building No - 1 as on September 2023.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Final Form 3 of Riverwood Park Building No -1 as on 30-09-2023.pdf20 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Riverwood Park Building No 1 as on 30-06-2023.pdf21 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Building 1.pdf13 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Riverwood Park Building No 1 as on 31-03-23.pdf27 Jun 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Riverwood Park Building No 1 as on 31-03-2023.pdf20 Jun 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Riverwood Park Building No 1 as on 31-03-2023.pdf20 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Riverwood Park Building No 1.pdf14 Jun 2023
Disclosure of sold/ booked inventoryFile: Circular 29- Riverwood Building No 1.pdf14 Jun 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1- Riverwood Park Building No 1.pdf7 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Riverwood Park Building No 1 Dec 22 - Form 2.pdf3 Apr 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Riverwood Park Building No 1 as on December 2022.pdf3 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 Building No 1 2021 2022.pdf16 Feb 2023
Details of encumbrancesFile: Riverwood Park Building 1- Encumbrance letter.pdf18 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March 2022.pdf7 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Riverwood Park Building No 1 as on June 2022.pdf7 Jan 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Riverwood Park Building No 1 as on September 2022.pdf7 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_Riverwood Park Building No-1_March 2022 (1).pdf7 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 of Riverwood Park Building No 1 as on June 2022.pdf7 Jan 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3- Riverwood Park Building No1 as on September 2022.pdf7 Jan 2023
Copy of the legal title reportFile: 1 Copy of the legal title report.pdf27 Dec 2021
Details of encumbrancesFile: Building No- 1 Encumbrance Letter_0001.pdf27 Dec 2021
Declaration about Commencement CertificateFile: Bld No-1 FORM D.pdf27 Dec 2021
Declaration in FORM BFile: Bld No- 1 Declaration.pdf27 Dec 2021
CERSAI detailsFile: Riverwood Park 1.pdf27 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 (1).pdf27 Dec 2021
Proforma of Allotment letterFile: Agreement draft Riverwood Park RERA bldg no 1.pdf27 Dec 2021
Proforma of Allotment letterFile: Allotment Letter.pdf27 Dec 2021
Layout approvalFile: Plan Page 1.pdf24 Dec 2021
Building plan approvalFile: Building No 1 typical Refuje_compressed.pdf24 Dec 2021
Building plan approvalFile: Building No 1 Section.pdf24 Dec 2021

How this compares with Thane

59%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 15 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Riverwood Park Building No -1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Sagarli , Dombivali East7,600+ in Thane

2 kmRiverwood Park Building Completed 12Lapsed / revoked 3Other 23Dot size: filed unitsN

Filed coordinates, straight-line distance. 38 registered projects within 2 km.

Builder: Shree Khidkaleshwar Property Developers Pvt. Ltd.

Shree Khidkaleshwar Property Developers Pvt. Ltd. has 5 registrations on MahaRERA, including Riverwood Park Building No. 2 and Riverwood Park Building No. 4. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Riverwood Park Building No -1 is delayed beyond 31 Mar 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Riverwood Park Building No -1?

The registered promoter entity is Shree Khidkaleshwar Property Developers Pvt. Ltd., a company as per the filing. Its CIN U45400MH2014PTC254482 and GSTIN 27AAUCS4319K1ZP can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Riverwood Park Building No -1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Riverwood Park Building No -1?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Riverwood Park Building No -1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Riverwood Park Building No -1?

The professionals named in the filing: Architect: Vasturachna; Engineer: SK Consultants & Engineers; Engineer: Harish Vispute; Chartered Accountant: NB Sayed & Associates; Chartered Accountant: Vinod Patil & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Riverwood Park Building No -1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Riverwood Park Building No -1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Riverwood Park Building No -1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.