Home / Browse projects / Riverdale Suites

Registration lapsed No litigation declared Residential / Group Housing project

Riverdale Suites

By Duville Estates Private Limited

RG-MH-26372 · RERA P52100014163 · Last updated on MahaRERA portal: 5 Dec 2024

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 23 months past the filed date
  • 5 complaints at MahaRERA
  • Completion date moved by 20 months
  • 2 extensions taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Nov 2024Possession promised23 months past this date
7 of 22Construction stages doneacross 2 buildings; furthest along: Basement (if any), 0%
5Complaints at MahaRERAon this registration
Jump to the 197 documents Report an error

Riverdale Suites is a Residential / Group Housing project by Duville Estates Private Limited in New Kharadi Behind Zensar IT Park, 411014, registered with MahaRERA as P52100014163 on 10 Nov 2017. Possession was promised by 30 Nov 2024 and is now 23 months past that date. The completion date has moved by 20 months from the original filing. 5 complaints are on record with the regulator.

At a glance

Project

  • NameRiverdale Suites
  • TypeResidential / Group Housing
  • Location
    • Shivane Riverside Road
    • New Kharadi Behind Zensar IT Park
    • 411014
  • Pincode411014
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100014163
  • ReraGenie IDRG-MH-26372

Builder

  • NameDuville Estates Private Limited
  • Entity typeCompany
  • GSTIN27AACCC8436BIZW
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • DirectorTushad Behram Dubash
  • Other registrations7 more →
  • Completed4 of 8
  • No longer live3 lapsed, de-registered or revoked
  • Declared earlier projects2 →

Key dates

23 months past promisethis monthRegisteredNov 2017First promiseMar 2023Revised toNov 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on10 Nov 2017
  • Promised completion30 Nov 2024
  • Revised completionRevised to 30 Nov 2024 (originally 30 Mar 2023)
  • Buildings2 building records
  • Documents filed197 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B9NA280000
B8NA70000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 5 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Basement (if any), at 0%.

B964%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B80%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 5 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed130

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots130
Closed/Covered130
BuildingClosed/CoveredTotal
B911
B8129129

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area5,170 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
Ramesh Dattatraya AdhavVIMANNAGARPune

Approvals and building plan

Permissible FSI15684.14
Proposed, not sanctioned15,684 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGround Floor, Manekji Wadia Bldg, Nanik Motwani Marg, Fort, Mumbai 400001

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectPinnac AECl Consultancy Pvt Ltd
EngineerMasters Management Consultants Pvt Ltd
PartnerRole in project
Duville Estates Private Limited-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100012969Mar 2023 → Mar 2024

Reason as filed by the promoterDue to Covid-19 Pandemic, project work got hampered due to inadequate manpower and difficulty in re-mobilization of resources. As a result there is a delay in completion of project within stipulated timelines. We humbly request you to grant an extension for a period of 1 year.

EXT52100025027Mar 2023 → Nov 2024

Reason as filed by the promoterDue to Covid-19 pandemic the work in the said Project has got delayed due to inadequate manpower and difficulty in re-mobilisation of resources. We had applied for extension of project registration under Section 6 of the Real Estates Regulation Act, 2016 (the ‘Act’) and the validity of the said Project had been extended by MahaRERA till 29th March, 2023. We have completed the construction of the said Project and possession of flats has already been delivered to the flat owners. Since the final Occupancy Certificate dated 7th February, 2024 has been received after expiry of validity of the proj

Litigation declared7

CaseCourtStatus
226/2015Court of Civil Judge Senior Division PunePending
597/2015Court of Civil Judge Senior Division PunePending
48/2016Pune Civil CourtPending
221/2014Sub Divisional Officer PuneDismissed
254/2016Additional Collector PuneDismissed
182/2016Sub Divisional Officer PuneDismissed
1774/2015Court of Civil Judge Senior Division PuneDismissed by Honble District and Sessions Court Pune

Complaints filed with MahaRERA5

Case no.ComplainantRespondentFiled
CC005000000085510Duville estates through Shrinivas Sharad KulkarniSeher Siraj01/06/2021
CC005000000085627Duville estates through authorised signatory Mr Shrinivas Sharad KulkarniChendur V Parandhanam06/07/2021
CC005000000085633Duville estates through authorised signatory Shrinivas KulkarniPragya Tiwari06/07/2021
CC005000000177720RIVERDALE SUITES RESIDENTS ASSOCIATIONDuville Estates Private Limited06/11/2022
CC005000000340817RUPESH MUNDRADUVILLE ESTATES PRIVATE LIMITED24/04/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Oct 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Apr 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 31 May 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jan 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 8 Nov 2024

Documents filed197

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 197 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: form 4 - Riverdale Suites 8th October 2024.pdf5 Dec 2024
Certificates of CA (Form 3)File: Form 3 B9 Sept 2024.pdf19 Nov 2024
Certificates of CA (Form 3)File: Form 3 B9 Sept 2024.pdf19 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: B9 Form 2.pdf14 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A)File: Form-2A - Riverdale Suites - Sep 2024.pdf14 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Riverdale Suites - Sep 2024.pdf12 Nov 2024
Certificates of CA (Form 3)File: Form-3 - Riverdale Suites - Jun 2024.pdf12 Nov 2024
Disclosure of sold/ booked inventoryFile: RS.pdf12 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate B9 Bldg.pdf8 Nov 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Plot B9 - Occupancy Certificate - Shops.pdf8 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - RS - FY 2023-24.pdf10 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RS Form 1 June24.pdf12 Aug 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: B9 Form 2.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: B9 Inv.pdf7 Aug 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: B9 Form 1.pdf11 Jun 2024
Certificates of CA (Form 3)File: Form 3 RS B9.pdf24 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 B9 Suites.pdf9 May 2024
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A Suites.pdf9 May 2024
Disclosure of sold/ booked inventoryFile: Suites inv.pdf2 May 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Riverdale Suites - Dec 2023.pdf1 Mar 2024
Certificates of CA (Form 3)File: Form-3 - Riverdale Suites - Dec 2023.pdf1 Mar 2024
Disclosure of sold/ booked inventoryFile: 11 Inventory Details - Riverdale Suites - Dec 2023.pdf15 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Plot B - B9 - Form 1 - 31 Dec 2023.pdf12 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Riverdale Suites - Sep 2023.pdf2 Nov 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Riverdale Suites - Sep 2023.pdf2 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Form-2A - Riverdale Suites - Sep 2023.pdf2 Nov 2023
Disclosure of sold/ booked inventoryFile: 10 Inventory Details - Sep 2023.pdf2 Nov 2023
Certificates of CA (Form 3)File: Form-3 - Riverdale Suites - Sep 2023.pdf2 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - RS - FY 2022-23.pdf30 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Riverdale Suites - Jun 2023.pdf8 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - Riverdale Suites - Mar 2023.pdf8 Aug 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - Riverdale Suites - Jun 2023.pdf8 Aug 2023
Disclosure of sold/ booked inventoryFile: 9 Inventory Details - Jun 2023 - Compressed.pdf27 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Riverdale Suites - Jun 2023.pdf21 Jul 2023
Certificates of CA (Form 3)File: Form 3 - Riverdale Suites - June 2023.pdf21 Jul 2023
Building plan approvalFile: 04-17 - Basement Plan B6 B7 B8_compressed.pdf31 May 2023
Building Plan Approval (IOD)File: 04-17 - Basement Plan B6 B7 B8_compressed.pdf31 May 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Riverdale Suites - Mar 2023 - Counter Signed.pdf21 Apr 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Riverdale Suites - Mar 2023 - Counter Signed.pdf21 Apr 2023
Disclosure of sold/ booked inventoryFile: 8 Inventory Details - 31032023.pdf21 Apr 2023
Certificates of CA (Form 3)File: Form 3 - Riverdale Suites - Mar 2023.pdf21 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Sep 2021.pdf13 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Dec 2021.pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Plot B9 Form-2 Mar-2018- .pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Plot B9 Form-2 June-2018- .pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Plot B9 Form-2 Sep-2018- .pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 - Plot B9-Letter - Mar 2019.pdf13 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form - 2 - Plot B9-Letter - Jun 2019.pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Plot B9 Form-2A Dec-2019- .pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Plot B9 Form-2A Mar-2020- .pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Plot B9 Form-2A June-2020- .pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Plot B9 Form-2A Sep-2020- .pdf13 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Plot B9 Form-2A Dec-2020- .pdf13 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Mar 2018.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Jun 2018.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Sep 2018.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Dec 2018.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Mar 2019.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Sep 2019.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Dec 2019.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Mar 2020.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Sep 2020.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Jun 2020.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Dec 2020.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - Mar 2021.pdf6 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - B9 - June 2021.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1-Plot B9 - Suites 31-Mar-20.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2-Plot B9 - Suites 30-Jun-20.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3-Plot B9 - Suites 30-Sep-20.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4-Plot B9 - Suites 31-Dec-20.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Suites- Form2 FY-21 - Mar 21.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Suites- Form2 FY-21 - Jul 21.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Suites- Form2 FY-21 - Oct 21.pdf6 Feb 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Suites- Form2 FY-21 - Dec 21.pdf6 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: CC - 2753-21 - 16122021.pdf27 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Riverdale Suites - Dec 2022.pdf24 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - FY 2018 - Dec 2018.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - FY 2020 - Jan 2020.pdf23 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - B9 - Mar 2021.pdf23 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - B9 - Jul 2021.pdf23 Jan 2023

Keep Riverdale Suites on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near New Kharadi Behind Zensar IT Park

2 kmRiverdale SuitesCompleted 45Lapsed / revoked 24Other 40Dot size: filed unitsN

Filed coordinates, straight-line distance. 109 registered projects within 2 km.

Builder: Duville Estates Private Limited

Duville Estates Private Limited has 8 registrations on MahaRERA, including Riverdale Heights and Riverdale Residences-I. Its filings disclose 2 earlier MahaRERA projects: declares 0 of 2 past projects completed on time. Litigation is declared on 4 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that Riverdale Suites shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Riverdale Suites is delayed beyond 30 Nov 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Riverdale Suites?

The registered promoter entity is Duville Estates Private Limited, a company as per the filing. Its GSTIN 27AACCC8436BIZW can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Riverdale Suites?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Riverdale Suites?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Riverdale Suites?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Riverdale Suites?

The professionals named in the filing: Architect: Pinnac AECl Consultancy Pvt Ltd; Engineer: Masters Management Consultants Pvt Ltd. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Riverdale Suites?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Riverdale Suites. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Riverdale Suites to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.